Dane BatemaBenoit Blier Drew Capps Patricia Roman Kyle Ryan Audrey Serra John TapeeCarlos Vergara Team 1: Prototype Fabrication, Economic, & Test Plan.

Similar presentations


Presentation on theme: "Dane BatemaBenoit Blier Drew Capps Patricia Roman Kyle Ryan Audrey Serra John TapeeCarlos Vergara Team 1: Prototype Fabrication, Economic, & Test Plan."— Presentation transcript:

1 Dane BatemaBenoit Blier Drew Capps Patricia Roman Kyle Ryan Audrey Serra John TapeeCarlos Vergara Team 1: Prototype Fabrication, Economic, & Test Plan QDR

2 AAE 451 Team 1 2 Preconstruction Plans

3 AAE 451 Team 1 3 Airfoil Fabrication

4 AAE 451 Team 1 4 Fuselage Construction

5 AAE 451 Team 1 5 Propulsion/Wing Economics

6 AAE 451 Team 1 6 Other Economics If small budget exceedance is problematic, donations can easily be secured.

7 AAE 451 Team 1 7 Man-Hours Hours Worked to Date: 1250 man-hours Construction (Est): 850 man hours Total Hours: 2100 Typical Work Hours Estimate / Person

8 AAE 451 Team 1 8 1.Find Actual CG 1.Adjust if needed 2.Test 10g wing loading (before Sean) 3.Test control surfaces –w/o engine –w/ engine 4.Comms w/ and w/o engine running (check for interference) 5.Test comms at long distance (driving test) 6.Full motor power duration test (static) 7.Remote control and servo calibration 8.Rate gyro test and tuning 9.Takeoff test 10.Flight endurance test 11.Test high speed flight Test Schedule Thurs 11/16 Fri 11/17 Sat 11/18 Sun 11/19


Download ppt "Dane BatemaBenoit Blier Drew Capps Patricia Roman Kyle Ryan Audrey Serra John TapeeCarlos Vergara Team 1: Prototype Fabrication, Economic, & Test Plan."