ECAL status and plans C-side A-side Further plans People involved: Alexander Arefiev, Boris Bobchenko, Yury Gilitskiy, Tengiz Kvaratskheliya, Irina Machikhiliyan,

Similar presentations


Presentation on theme: "ECAL status and plans C-side A-side Further plans People involved: Alexander Arefiev, Boris Bobchenko, Yury Gilitskiy, Tengiz Kvaratskheliya, Irina Machikhiliyan,"— Presentation transcript:

1 ECAL status and plans C-side A-side Further plans People involved: Alexander Arefiev, Boris Bobchenko, Yury Gilitskiy, Tengiz Kvaratskheliya, Irina Machikhiliyan, Olga Zhiryakova Special thanks to Iouri Guz for support

2 MESSAGE TO GLOBAL COMMISSIONERS on behalf of ECAL group DURING YOUR TESTS DO NOT TOUCH ECAL CABLING! CALL US AND CONSULT FIRST! IF YOU THINK YOU BURNED SOMETHING – DO NOT KEEP IT SECRET. SHARE IT WITH US. MONDAY SITUATION: SOMEBODY DISCONNECTED SOME POWER LINES FROM BOX #7. ECAL GROUP WAS NOT INFORMED, NO ENTRY INTO LOGBOOK.

3 PMTs / LEDs / interconnecting cabling are checked; malfunctions/mistakes found are (mostly) fixed PMTs / LEDs / interconnecting cabling are checked; malfunctions/mistakes found are not yet fixed PMTs / LEDs / interconnecting cabling are not yet checked (mostly due to missing parts of necessary hardware) ECAL commissioning: status (I)

4 ECAL commissioning: status (II), C-side  1 week access (end of October);  Post-access situation: 99.7% of PM channels / 100% of LED channels are operational; connections mapping (PM/LED control part) is updated in DB; integrators for PM current measurement are installed on the wall. minor optimization of voltage delivery/control boxes to stabilize output voltage - is done for 3 boxes (test batch to see unexpected behaviour if any);  Pending tasks:  integrators: fine adjustment (access to the wall is needed);  integrators readout: install additional voltage delivery/control box under ECAL platform;  PIN-diodes: check system serviceability and complete fine gain tuning to account for large PM gains spread over ECAL (access is not needed);  Hardware missing:  2 FEBs to readout PIN output signals;

5 ECAL commissioning: status (III), A-side  Wall became accessible week ago;  Current situation: 86% of PM channels / 89% of LED channels are checked;  problematic channels are under study / connections mapping in DB is under correction; integrators for PM current measurement are installed on the wall. To readout them additional voltage delivery/control box is installed under ECAL platform; missing voltage delivery/control boxes are installed; minor optimization of voltage delivery/control boxes to stabilize output voltage - is done for 4 boxes (test batch to see unexpected behaviour if any);  Pending tasks:  PM/LEDs (R/O crate #21): finish quick check of PM/LED channels serviceability;  PIN-diodes: check system serviceability and complete fine gain tuning to account for large PM gains spread over ECAL (access is not needed);  integrators: fine adjustment (access to the wall is needed);  Hardware missing:  One R/O crate (#21) is not equipped with MARATON power supply;  6 FEBs to readout PM output signals;  R/O crate 15 has defective slot, therefore one LED TSB unit can not be installed;

6 ECAL commissioning: further steps:  This week: repair of A-side  Further steps:  finish quick check of PM/LED channels serviceability for R/O crate 21;  check PIN-diodes system;  when global tests will be finished: check again C-side; start to measure PM regulation curves (DAQ is required);  optimize the rest of voltage delivery/control boxes (if no unexpected behaviour will be observed in test batch);  Access request: January 2008, both C and A-sides;

7 Measurement of the relative time spread in the cabling of Monitoring System on behalf of Ilya Kudryashov (MSU) in the context of the preparation to ECAL time alignment  LED fire / PIN signal cable lengths are measured (reflections method) and tabulated;  Selected results for lengths spread:  LED fire cables:  r. m. s. < 0.1m  max spread < 0.6m  PIN signal cables:  r. m. s. < 0.17m  max < 0.6m  Major source of systematics : time precision of generator fronts reproduction (dominated by temperature dependence); found to be 0.7 ns / cable length