Download presentation
Presentation is loading. Please wait.
Published byRoxanne Simpson Modified over 8 years ago
1
Programming Taija Puolitaival, Department of Construction, Unitec 2014
2
Project stages (Scofield and Wilkinson,2010) Taija Puolitaival, Department of Construction, Unitec 2014
3
Programme: Agenda, timetable, calendar, list, schedule, to-do-list, plan, rota/roster Programming Arrange or plan (an event) to take place at a particular time. Make arrangements for (someone or something) to do something. Setting an order and time for planned events Definitions: Programming Taija Puolitaival, Department of Construction, Unitec 2014
4
Bar charts Linked bar charts Arrow diagrams Node/Precedence diagrams Flowline diagrams …… Programming techniques (adapted from Cooke & Williams 2010) CPM Method Taija Puolitaival, Department of Construction, Unitec 2014
5
‘a graphic representation of project activities, shown in a time-scaled bar line with no links shown between activities’ (Mubarak 2010, p. 14) = Gantt chart, after Henry Gantt 1917 Bar chart Taija Puolitaival, Department of Construction, Unitec 2014
6
Bar chart Taija Puolitaival, Department of Construction, Unitec 2014
7
Easy to create Easy to understand Simplicity in general Time-scaled unlike networks Bar chart -advantages (Hinze 2012, Mubarak 2010) Taija Puolitaival, Department of Construction, Unitec 2014
8
Lack of logical representation (relationships) Not practical for complex projects, unless You use summary bars Show just a part of the project: One subcontractor at a time Certain section of the project Certain phase of the project Not practical for projects with repetitive tasks Does not show the productivity Does not show clashes Bar chart -disadvantages (Hinze 2012, Mubarak 2010) Taija Puolitaival, Department of Construction, Unitec 2014
9
Create a bar chart -slab on ground, 200 m² Excavation Site clearance Reinforcement Pour concrete Formwork Taija Puolitaival, Department of Construction, Unitec 2014
10
Line of balance Time-location matrix Time-space scheduling Location-based scheduling Location-based management Flowline Linear scheduling = (Andersson & Christensen, 2007) Taija Puolitaival, Department of Construction, Unitec 2014
11
Simple Flowline Calendar Tasks Locations Taija Puolitaival, Department of Construction, Unitec 2014
12
Location specific task bars 50 tasks in LOB can be 15,000 tasks in Gantt! 1 task in flowline = 8 in Gantt view Gantt chart vs. location-based Taija Puolitaival, Department of Construction, Unitec 2014
13
continuous flow of work through locations location is free of unnecessary materials and other crews optimum productivity rates optimum safety optimum craftsmanship Linear scheduling -advantages Taija Puolitaival, Department of Construction, Unitec 2014
14
Activityproductivity rate, metres/day Backfill200 Prepare sub base125 Compact the backfill150 Lay pipe75 Excavation100 Leave a minimum 1 day buffer between the activities LSM for a 1000 m pipeline (Mubarak, 2010) Taija Puolitaival, Department of Construction, Unitec 2014
15
Logic diagram Solution, pipeline A BCE D Taija Puolitaival, Department of Construction, Unitec 2014
16
ActivityDurationStartFinishBuffer A100 1 B83111 C144181 D514191 E715221 Solution, pipeline Taija Puolitaival, Department of Construction, Unitec 2014
17
Network diagrams/models = time oriented model of the project with strong emphasis on the order of activities = network of activity paths Taija Puolitaival, Department of Construction, Unitec 2014
18
Arrow diagram = Activity On Arrow = AOA Node diagram = Activity On Node = AON Network types Taija Puolitaival, Department of Construction, Unitec 2014
19
Critical path = which activity path drives the schedule in every project there is at least one Activities on the critical path = any delay in the start or finish of the activity will delay the entire project Critical Path Method (CPM) Taija Puolitaival, Department of Construction, Unitec 2014
20
Finding the critical path How many different paths does the network have? How long does each of them take? Which path is the longest? (= Critical Path) Taija Puolitaival, Department of Construction, Unitec 2014
21
Shows dependencies Shows complex interrelationships Benefits of CPM Taija Puolitaival, Department of Construction, Unitec 2014
22
Project completion date Start and end of a specific activity Coordination among trades and subcontractors Predict and calculate cash flow Improve work efficiency Use as a project control tool Evaluate the effect of changes and prove delay claims Programming (Mubarak, 2010) Taija Puolitaival, Department of Construction, Unitec 2014
23
1.Determine the work activities 2.Determine activities duration 3.Determine activities relationships 4.Review and analyse the programme 5.Cost/resource allocation 6.Resource levelling 7.Implement the programme 8.Monitor and control the programme 9.Revise the database and record feedback Programming steps (adapted from Mubarak 2010) Taija Puolitaival, Department of Construction, Unitec 2014
24
WBS / Programme Distinction WBS Comprehensive classification of project scope Contains no activity duration No resource assignments No dependencies Programme Actual work to be done (only the activities on the last level of the WBS) Contains activity durations Contains assignment of resources to activities Contains dependencies Taija Puolitaival, Department of Construction, Unitec 2014
25
Duration of activities Example: Excavation of 90 m³ Labour constant (Machine excavation): 0.20 hours/m³ Duration = Total quantity of the activity x Labour constant Duration = 90 m³ x 0.20 h/m³ = 18 h = 2.25 days = 3 days (Mubarak 2010) When rounding the numbers, always round up to full days. Normal rounding rules don’t apply. E.g. 2.25 days is 3 days, not 2. Taija Puolitaival, Department of Construction, Unitec 2014
26
Guesstimating vs. Estimating You are not allowed to just guess. If you are not able to access all the information that you need to calculate the durations, you have to use the information that you have got and based on that make an educated guess. Taija Puolitaival, Department of Construction, Unitec 2014
27
1.Nature of the work/homogeneity 2.Location/floor 3.Size/duration 4.Timing/chronology 5.Responsibility 6.Others = programmer’s mentality in breaking down the project (Mubarak 2010) determining of work activities things to be considered Taija Puolitaival, Department of Construction, Unitec 2014
28
Quantity Take-off Construction manager’s point of view - order of the activities - right size activities how to build the building vs. Quantity surveyor’s point of view - what is the total amount of quantities how much does it cost to build the building Taija Puolitaival, Department of Construction, Unitec 2014
29
Four different types Finish to Start (FS) Example: Concrete can not be placed before formwork has been built Start to Start (SS) Example: Formwork can not start before trench excavation has started Finish to Finish (FF) Example: Landscaping can not finish before the driveway is finished Start to Finish (SF) Example: ? Activity relationship types (Mubarak 2010) Taija Puolitaival, Department of Construction, Unitec 2014
30
Constraints HARD LOGIC Physical constraints = logical relationship SOFT LOGIC Resource constraints Safety constraints Financial constraints Environmental constraints Contractual constraints Regulatory constraints Other constraints (Hinze 2008) Taija Puolitaival, Department of Construction, Unitec 2014
31
Andersson, N., and Christensen, K. (2007). Location-based Scheduling – Vurdering af LBS- metodens anvendelse i byggeprojekter. Rapport BYG DTU T-167, Danmarks Tekniske Universitet, Department of Civil Engineering, Lyngby. Cooke, B. and Williams, P. (2009). Construction Planning, Programming and Control (3 rd ed.). West Sussex, UK: John Wiley & Sons. Hinze, J.W. (2012). Construction Planning and Scheduling. New Jersey: Pearson Education. Mubarak, S. (2010). Scheduling and control (2 nd ed.). Hoboken, New Jersey: John Wiley & Sons Scofield, R., Wilkinson, S. (2010). Management for the New Zealand Construction Industry (2 nd ed.). North Shore, NZ: Pearson. References Taija Puolitaival, Department of Construction, Unitec 2014
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.