2 GUNDLAKAMMA RESERVOIR PROJECT
1 Project Profile: Across river Gundlakamma near Chinnamallavaram (V), Prakasam District 2 Administrative Sanction : G.O.Ms.No.163, Dt Rs Crs. G.O.Ms.No.243, dt , Amt. Rs Crs. 3 No. of EPC Packages 2 No 4 Agreement value of 2 packages Rs Crs. 5 Budget provision for Rs Crs. 6 Expenditure of the project 2004 – 05 Rs Crs. 2005 – 06 Rs Crs. Cum. Exp. Rs Crs 7 Utilisation 14 TMC 8 Ayacut New Ayacut 80,060 acres 9 Drinking water 2.56 Lakh people 10 Land Acquisition Required 7891 acres Requisitioned 7051 acres Acquired 3262 acres

3 11 Estimated Cost of LA : Rs Crs. 12 Estimated Cost of R & R Rs Crs. Clearances CWC & Environmental Clearance obtained 13 Mob. Advance (Rs. in Crores) Paid Recovered Total 14 Target date of completion 8/2007

4 GUNDLAKAMMA RESERVOIR PROJECT
PKG No. Description Agt. Value & Date Agt. Period Name of the contractor 1 Formation of Left Earth dam including construction of Left sluice & spillway. Rs Cr. Dt: 18 months M/s NCC Ltd, Hyderabad 2 Formation of Right Earth bund and excavation of Left & Right main canals, CM&CD works and distributory system. Rs Cr Dt: 30 months M/s Maytas – NCC (J.V), Hyderabad 3 Supply and fixing of spillway gates Rs Crs. M/s AARPI Engineering Co. Nagpur

5 GUNDLAKAMMA RESERVOIR PROJECT
Pkg.No. 1 : Formation of left earth dam including Construction of Head Sluice and Spillway of Gundlakamma Reservoir Project. Name of the Contractor : M/s. Nagarjuna Constructions Agreement Amount : Rs Crs. Agreement Date : Period of completion : 18 Months (6 milestones) Target date of completion : 1/2006 Investigation : Completed Designs : Completed Execution : in progress Qty. of earth work done : 17,73,185 cum against 21,00,440 cum Qty. of concrete work done : 61,044 cum against 75,609 cum Machinery : 44 Nos. deployed (Excavators-4, Tippers-25, concrete mixers 10 etc.) Expenditure : Rs Crs. Rs Crs. Cum. Exp. Inc.Mob. Adv. only - Rs Crs. Land Acquisition : Required Acres, Acquired Acres

6 GUNDLAKAMMA RESERVOIR PROJECT
Pkg.No. 2 : i)Formation of Right Earth Bund, ii) Closing of Gorge Portion by Earth Bund, iii) Excavation of Left and Right Canals, iv) Construction of Right Head Sluice, v) CM&CD works and vi) distributary system for an ayacut of 80,000 Acres. Name of the Contractor : M/s. Maytas-NCC Ltd (JV) Agreement Amount : Rs Crs. Agreement Date : Period of completion : 30 Months (10 milestones) Target date of completion : 8/2007 Investigation : Km length against Km. Designs approved : 14 Km length against Km. Execution : 9 Km length against Km Qty. of earth work done : 4,07,000 cum against Lakh cum Qty. of concrete done : 1060 cum against 40,825 cum Machinery : Deployed 39 Nos. (Excavators-6, Tippers-25, Rollers-3 etc.) Expenditure : Rs Crs. Rs Crs. Cum. Exp. Inc. Mob. Adv. only - Rs Crs. Land Acquisition : Required Acres, Acquired Acres