ERIC J. COBERLY, P.E., CHIEF OFFICE OF ABANDONED MINE LANDS
2
2006 AMENDMENT REAUTHORIZED FEE COLLECTION FOR THE AML PROGRAMS THROUGH 2022 AMENDMENT RESULTED IN A NUMBER OF POSITIVE RESULTS FOR WEST VIRGINIA PROGRAM
3
EFFECTIVELY BUMPS WV ANNUAL ALLOCATION TO BETWEEN $50 AND $70 MILLION THROUGH 2022 INCLUDES SEVEN YEAR ANNUAL REPAYMENT OF $20.8 MILLION FROM 2007 TO 2014 FROM THE UNAPPROPRIATED BALANCE FUNDS FOR STATE AND HISTORICAL SHARE BASED ON FEE COLLECTIONS WV IS ALLOCATED MOST AMONG STATES IN STATE SHARE AND 2 ND MOST IN HISTORICAL SHARE
4
WATERLINE FUNDING CAP REMOVED ALLOWED TO SET ASIDE UP TO 30% OF ELIGIBLE GRANT FUNDS IN AMD FUND VERSUS 10% IN PRIOR AMENDMENTS PHASED FEE REDUCTION FOR THE COAL INDUSTRY
5
HEALTH AND SAFETY WATERLINE EXTENSION OR SYSTEM UPGRADE AMD SET ASIDE PROJECT EMERGENCY
6
PROJECT TYPES INCLUDE LANDSLIDES, HIGHWALLS, PORTALS, SUBSIDENCE, DRAINAGE CONTROL AND REFUSE OR SPOIL AREAS. CURRENT APPROVED WV AML INVENTORY OF UNFUNDED PRIORITY 1OR 2 SITES IS $925 MILLION
7
UTILIZE REGULAR AML ALLOCATION FOR FUNDING AML INVESTIGATES AND PLANS PROJECT, OBTAINS RIGHTS OF ENTRY, DESIGNS IN HOUSE OR PROCURES DESIGN CONSULTANT, PARTICIPATES IN BIDDING AND MONITORS CONSTRUCTION
8
GOVERNOR MANCHIN HAS DIRECTED WVDEP TO ELIMINATE THE WATERLINE PROJECT BACKLOG AND COMPLETE OTHER ELIGIBLE WATERLINE PROJECTS THAT RESULT FROM CURRENT OR FUTURE FEASIBILITY STUDIES AML ANTICIPATES SPENDING APPROXIMATELY $20 MILLION PER YEAR OVER THE NEXT SEVERAL YEARS
9
CURRENTLY SEVEN (7) PROJECTS UNDER CONSTRUCTION AT AN AML SHARE AMOUNT OF $14 MILLION THIRTY (30) PROJECTS HAVE BEEN DECLARED ELIGIBLE THAT ARE NOT UNDER CONSTRUCTION AT AN AML SHARE AMOUNT OF $68 MILLION 26 FEASIBILITY STUDIES FOR ELIGIBILITY DETERMINATION ARE UNDERWAY 17 NEW APPLICATIONS RECEIVED SINCE NOVEMBER 2008
10
FUND STATUS ◦ $21.5 MILLION CURRENTLY IN THE FUND ◦ INTEREST EARNED ON FUND HAS DECREASED FROM $40,000 PER MONTH AT THE BEGINNING OF THE FISCAL YEAR TO JUST OVER $20,000 PER MONTH PRESENTLY
11
PROJECTCOST ESTIMATEPROJECTED O&MSTATUS LAUREL CREEK DOSER $275,347STATE OF MDUNDER CONSTRUCTION PAINT CREEK$233,725$26,000/YRBIDDING ABRAMS CREEK$930,000$75-100,000/YRBIDDING THREE FORKS$684,000$172,000/YROBTAINING EASEMENTS
12
SHORT TERM – BUILD CURRENT PROJECTS AND STUDY RESULTS PRIOR TO UNDERTAKING ADDITIONAL PROJECTS LONG TERM – DO NOT BUILD BEYOND MEANS TO FUND O&M FOR TREATMENT PERPETUALLY DEPOSIT ADDITIONAL FUNDS INTO ACCOUNT AS FINANCES AND COMMITMENTS ALLOW
13
BLACKWATER DOSER STATION ($85,000 THIS FISCAL YEAR) GRASSY RUN TREATMENT DURING TYGART RIVER LOW FLOWS ($107,000 THIS FISCAL YEAR) LIMESTONE SAND SITES MATCHING DOLLARS AT ALBERT HIGHWALL AGREEMENT TO ASSIST ON O&M ON UPPER DECKERS CREEK MAINTENANCE ON EXISTING PROJECTS
14
ULTIMATE GOAL IN PROJECT PRIORITIZATION AND SELECTION IS THE PREDICTED RETURN OF FISHABLE MILES OF STREAMS CURRENTLY DEVELOPING A STATEWIDE LIST OF THE AMD IMPACTED STREAMS WITH ASSISTANCE FROM THE DNR FISH BIOLOGISTS THE STREAMS WILL BE RATED IN TERMS OF HOW GOOD AND WHAT TYPE OF FISHERY WOULD RESULT FROM SUCCESSFUL TREATMENT
15
GROUP INVESTIGATES, OBTAINS EASEMENTS, PREPARES DESIGNS, BIDS AND MONITORS CONSTRUCTION FOR PROJECTS THAT OCCUR SUDDENLY AND PRESENT AN IMMEDIATE THREAT TO THE PUBLIC AVERAGES $2 -$3 MILLION PER YEAR – PROGRAM HAS SPENT AS MUCH AS $7 MILLION IN ONE YEAR FUNDING IS CURRENTLY IN ADDITION TO THE REGULAR GRANT FUNDING; HOWEVER, PROPOSALS FROM THE FEDERAL GOVERNMENT WOULD FUND FROM REGULAR AML GRANT
16
PRESIDENTS PROPOSED DRAFT BUDGET ELIMINATES FUNDING TO CERTIFIED STATES A REVISION TO THE 2006 AMENDMENT WOULD BE REQUIRED ALTHOUGH FURTHER DETAILS ARE NOT AVAILABLE, WV WILL SEE SOME REDUCTION IN FUNDING IF THIS PROPOSAL IS APPROVED EMERGENCY FUNDING PROPOSAL