Download presentation
Presentation is loading. Please wait.
Published byIsabella McLaughlin Modified over 8 years ago
1
July 29, 2013
2
Startup 2013 Machine Status: Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster Main Injector Trying to finish up tunnel work – vacuum issues TeV & Muon Rings – Partially available for tours with approval and appropriate training
3
Power Outages PS3 Power Outage Oil Switch Replacement Impacts PS3, PW5, & PC3 Run on generator for ~1 week Connect generator Monday, July 29 th @ 0800 – 1000 Disconnect generator Friday, August 2 nd @ 0800- 1000
4
Power Failures Feeder 46B Wednesday, July 24 th @ 2142 Impact – Possible F0 ventilation system Fault located between P71 & F4 Further isolation and repairs necessary
6
MSS Bypass Project – Impact Areas Cont. CHL ~5 day outage/reduction (only house power available) Monday, June 24 th through Friday, June 28th Two 5 minute power outages needed Monday, June 24 th @ 0730 – 0735 (Completed) Friday, June 28 th @ 0700 – 0705 (Completed) Cable pulls and splices in PMH 210 Meson Two 15 minute outages one week apart Monday, June 17 th @ 0700 – 0715 (Completed) Monday, June 24 th @ 0700 – 0715 (Completed) Monday, June 24 th @ 0815-1215 (Bonus MCC-2 outage @ MS3) Cable pulls and splices in PMH 110 Impacts MCC, Holometer, MW9, all enclosures, systems, and buildings
7
Kautz Road SubStation Status MI backfed from Master SubStation ○ Using Feeder 45 for MI conventional power which is normally T85 on KRS We ordered 6+ new surge arrestors (4.7k each) from Hubbell and wait for delivery expected (Friday, July 26 th ) Schedule a ~1 day KRS outage (not really an outage, we can’t run power supplies) to replace all surge arrestors on transformers T85 & T87. Looks like the week of August 5 th. There will be a 20 minute outage to remove the backfeed after the surge arrestors are installed
8
MI Startup Activities (~1 Week) Turn on power supplies and establish ramps Establish 8 Gev beam Match MI8 line lattice with IPM Tune abort line @8 Gev Establish 120 Gev beam Smooth orbits up the ramp Tune abort line @ 120 Gev High field Orbit smoothing (quad moves) Requires tunnel access (2x8 hrs) Calibrate tune table MI8 line lattice matching Dedicated beam study Extraction line tune up (NuMI) Tune up for operation Deliver low intensity beam to NuMI beam line for target scans Estimated to take an additional week after MI is tuned up for operations
10
Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations ScheduleOperations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.htmlhttp://www-ad.fnal.gov/ops/schedule.html
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.