July 29, 2013. Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.

Similar presentations


Presentation on theme: "July 29, 2013. Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to."— Presentation transcript:

1 July 29, 2013

2 Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to finish up tunnel work – vacuum issues TeV & Muon Rings – Partially available for tours with approval and appropriate training

3 Power Outages  PS3 Power Outage Oil Switch Replacement Impacts PS3, PW5, & PC3 Run on generator for ~1 week Connect generator Monday, July 29 th @ 0800 – 1000 Disconnect generator Friday, August 2 nd @ 0800- 1000

4 Power Failures  Feeder 46B Wednesday, July 24 th @ 2142 Impact – Possible F0 ventilation system Fault located between P71 & F4 Further isolation and repairs necessary

5

6 MSS Bypass Project – Impact Areas Cont.  CHL ~5 day outage/reduction (only house power available) Monday, June 24 th through Friday, June 28th Two 5 minute power outages needed Monday, June 24 th @ 0730 – 0735 (Completed) Friday, June 28 th @ 0700 – 0705 (Completed) Cable pulls and splices in PMH 210  Meson Two 15 minute outages one week apart Monday, June 17 th @ 0700 – 0715 (Completed) Monday, June 24 th @ 0700 – 0715 (Completed) Monday, June 24 th @ 0815-1215 (Bonus MCC-2 outage @ MS3) Cable pulls and splices in PMH 110 Impacts MCC, Holometer, MW9, all enclosures, systems, and buildings

7 Kautz Road SubStation  Status MI backfed from Master SubStation ○ Using Feeder 45 for MI conventional power which is normally T85 on KRS We ordered 6+ new surge arrestors (4.7k each) from Hubbell and wait for delivery expected (Friday, July 26 th ) Schedule a ~1 day KRS outage (not really an outage, we can’t run power supplies) to replace all surge arrestors on transformers T85 & T87. Looks like the week of August 5 th. There will be a 20 minute outage to remove the backfeed after the surge arrestors are installed

8 MI Startup Activities (~1 Week)  Turn on power supplies and establish ramps  Establish 8 Gev beam  Match MI8 line lattice with IPM  Tune abort line @8 Gev  Establish 120 Gev beam  Smooth orbits up the ramp  Tune abort line @ 120 Gev  High field Orbit smoothing (quad moves)  Requires tunnel access (2x8 hrs)  Calibrate tune table  MI8 line lattice matching  Dedicated beam study  Extraction line tune up (NuMI)  Tune up for operation  Deliver low intensity beam to NuMI beam line for target scans  Estimated to take an additional week after MI is tuned up for operations

9

10 Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations ScheduleOperations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.htmlhttp://www-ad.fnal.gov/ops/schedule.html