Download presentation
Presentation is loading. Please wait.
Published byAlbert Sanders Modified over 8 years ago
1
Normanton/Karumba WTP Upgrade Matt Fanning Director TBG Pty Ltd
2
Normanton/Karumba Shire pop: 2100 (Wet season) Karumba residents: 600 Karumba tourists: 2,000 Industry: Mining, tourism fishing
3
Existing Scheme Normanton/Karumba Water Treatment Plant –1963 – Normanton Water Supply Established –1982 – New 300mm rising main and Clear water storage, 23km rising main –1985-87 Karumba connected 42km rising main –1999 – capacity upgrade (copied existing clarifiers), new storages both Normanton and Karumba –Capacity of 3.5 ML/day, –Storage Capacity 2.36ML Normanton, 5ML Karumba
4
Project Summary Normanton/Karumba Water Treatment Plant –2000 – Planning report – $1.68M –2003 – SCAP funding awarded - $3M grant –2004 – Glenore Weir raising investigation –2006 – Telemetry system implemented (basic automation, but mainly alarms and reporting) –2006-2008 further investigations little traction –October 2009 – Peer Review Hyder Consulting –2009 – Advised by State that SCAP Funding Withdrawn loss of $1M back to Government –November 2009 – Design Awarded to BTO –December 2010 – Works commenced –June 2011 – Works completed
5
Scheme Issues High Operator costs – Manual processes Difficult to operate – SCADA not full automation High risk of water quality failure Changing water quality guidelines Building required renewal Equipment out dated and high maintenance Upgrade could only occur during the wet season
6
Scheme Vision To implement a cost effective and reliable Water Treatment System for the towns of Normanton and Karumba.
7
Basic Principles of WTP Pump water from source location
8
Basic Principles of WTP Remove large particles in clarifier Coagulant
9
Basic Principles of WTP Remove fine particles in gravity filter
10
Basic Principles of WTP Apply disinfection – generally chlorine TO SUPPLY
11
Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Clarifier 2 Filter 1 Clarifier 1 Washwater Air Scour Raw Water Existing Building Res. #1 Res. #3Res. #2 Dosing Points Existing Plant Overview
14
State of WTP in 2009 WTP review (2009) 1. Catchment management issues leading to raw water contamination; 2. Extremes of turbidity in the raw water difficult to treat; 3. High filtered water turbidity leading to risk of pathogen shielding and breakthrough; 4. Elevated iron levels leading to oxidant consumption and discoloured treated water; 5. Compromised disinfection efficiency; 6. Presence of Hydrogen Sulphide in Supply Sources; 7. Tastes and odours in the treated water.
15
State of WTP in 2009 Existing chemical systems Did not meet Workplace H&S standards Chemical make-up labour intensive Chemical quality open to human error Chemical dosing set by operator Dosing not proportional with flow
16
Dosing System
17
State of WTP in 2009 Existing Clarifiers Poor performance at high flows Poor performance when high turbidity Problems de-sludging Odour problems Solids carry-over to filter
18
Clarifiers
20
State of WTP in 2009 Existing Filters Poor filtration (poor water quality) Manual washing; Labour intensive Damage to filter media
21
Poor filter Performance
22
Old Backwash system (used to clean filters) Flow too low (poor washing of media) No standby pump Difficult to prime Labour intensive No NRV fitted to pump State of WTP in 2009
23
Backwash Pump Air Blower Poor Backwash System
24
State of WTP in 2009 Old Air Scour (used to help wash filters) Air flow too low (poor agitation of media) No standby blower Labour intensive
25
Poor Air Scour System
27
State of WTP in 2009 Chlorine dosing Not proportional to flow No gas detection & alarm Labour intensive
28
Poor Chlorine Dosing System
29
State of WTP in 2009 General state of building Not cyclone rated Termite damage Leaking Possible asbestos
31
Risk? Risk Assessment Risk CategoryRisk ItemPROBCON Risk ScoreRisk Rating Water Quality Protozoa470280 Very High Bacteriological470280Very High Disinfection By-Products31030Moderate Aesthetics (Taste, Staining)51050High Water Supply Short Term Loss of Supply450200Very High Extended Loss of Supply370210Very High Health & Safety Building & Stairways470280Very High Chemical Handling350150High
32
Why Automate? Main reasons to automate the WTP –Reduce labour costs ($200k/yr) –Improve quality of water –Optimise chemical use (save $$$) –Improve reliability of plant –Accurate reporting and alarming
33
First Step? Options study –1 – Refurbish existing plant –2 – New clarifier & refurbish existing filters –3 – New clarifier & membrane filtration –4 – Membrane filtration only Include –New intake at Glenore Weir
34
Which Option? CAPEX Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only $ 2,401,000$ 3,046,000$ 4,346,000$ 4,355,000 OPEX Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only $ 277,000$ 253,000$ 369,000$ 359,000
35
Which Option? Estimated NPV Year Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only 15$ 4,595,000$ 4,986,000$ 7,183,000$ 7,106,000 20$ 4,943,000$ 5,305,000$ 7,647,000$ 7,558,000 25$ 5,181,000$ 5,522,000$ 7,964,000$ 7,865,000 30$ 5,315,000$ 5,644,000$ 8,142,000$ 8,039,000
36
Preferred Option New clarifier & refurbish existing filters –New air scour system –New washwater system –New chemical dosing –New buildings –Complete automation
37
Actiflo Clarifier
38
Implementation Construction issues –Operational plant (Normanton & Karumba) –Remote location (Materials & skilled labour) –Procurement (Australian & New Zealand) –WEATHER! –4 phase construction
39
Construction Sequence 1 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 ACTIFLO
40
Temp chemical dosing systems
41
Demolition
42
Construction Sequence 2 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
43
Fabrication
44
Staff Induction Training!
45
Construction Sequence 3 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
46
New pipe work and control valves
47
New Clarifier
48
Construction Sequence 4 Filter 6 Clarifier 6 Filter 5 Clarifier 5 Filter 4 Clarifier 4 Filter 3 Clarifier 3 Filter 2 Filter 1 Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
49
New MCC Building
50
Filter Refurbishment
52
Filter Control
53
New chemical Dosing System
54
New WTP Building
56
WTP Performance Old Performance –Raw water quality Turbidity = 50 NTU –Old clarifiers Turbidity = 3 NTU –After refurbished filtersTurbidity = 1 NTU –Maximum flow (3 filters)= 36l/s! New Performance –Raw water quality Turbidity = 50 NTU –After Actiflo clarifier Turbidity = 1 NTU –After refurbished filtersTurbidity = 0.045 NTU –Maximum flow (3 filters)= 50l/s!
57
WTP Performance
58
What Else? Additions to main contract –Norman River PS –Karumba chlorination system upgrade –Telemetry system upgrade –Procurement –Construction management –Commissioning
59
Lessons Learnt? Keep it simple Appreciation of location –Supply of materials –Available labour/contractors –Weather Build as much off site as possible Good working relationship with client
60
Why Use BTO? Excellence in Water & Wastewater Engineering They delivered on their promises: –on time –with clear reports & designs –with staff / resources promised –on budget BTO don’t just write reports – they get things done and deliver!
61
QUESTIONS???
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.