Download presentation
Presentation is loading. Please wait.
Published byJeffry Stephens Modified over 8 years ago
1
Field Office Construction, Technical Assistance and Quality Assurance NEDC Construction Inspection for Field Office Activities USDA is an equal opportunity provider and employer.
2
Objectives Field Office Technical Assistance Understand the Engineering Job Approval Authority chart Become aware of Statement of Work (SOW) Be able to list types of engineering documents that need to be delivered
3
Engineering Job Approval Authority Policy: National Engineering Manual (NEM Part 501.4 – Engineering Job Approval Authority) State Amendments (i.e. Part MI501 – Authorizations)
4
Job Approval Authority Director, Conservation Engineering Division State Conservation Engineer Area Engineer NRCS Area and Field Office Employees Non-NRCS Employees Concurrence by Line Supervisor Who delegates Approval Authority?
5
Practices are defined as Class I thru VIII Class I-V In-state approval authority Class VI-VIII State Conservation Engineer approval authority Job Approval Authority
6
Job Approval authority is required for: Design approval of all Job Classes States may also require Job Approval Authority for: Inventory and Evaluation (I&E or planning) Construction Job Approval Authority
7
Job Approval Authority Determining Job Class For each controlling factor Quantity shown is the max limit for that job class Use largest Class
8
Job Approval Authority Determining Job Class Here’s an example Grade Stabilization Structure, 410 Drainage area = 50 acres Effective Height = 24 feet Conduit = 6 inches (diameter) Storage x Height = 1327 (acft x ft)
9
Determining Job Class 50 ac is >20 but <99 24’ is >20 but <25 6” < 12 1000<1327<2000
10
Job Approval Authority Determining Job Class Grade Stabilization Structure, 410 Drainage area = 50 acres (Class II) Effective Height = 24 feet (Class III) Conduit = 6 inches (Class II) Storage x Height = 1327 (Class III) Therefore, this practice is Job Class III
11
Obtaining Job Approval Authority Work with Area Engineer Learn basics From colleges From engineer By doing Attend Training Demonstrate competency Designs, Construction plans, Inspection Thorough documentation
12
Delivery of Engineering Documents “Deliverables” can be found in the Statement of Work (SOW) for each conservation practice
13
SOW can be found in eFOTG eFOTG Section IV Conservation Practices Statement of Work Statement of Work
14
Design Installation Check Out SOW Sections: Practice Application Deliverables References
15
410 SOW - Design
16
410 SOW - Installation
17
410 SOW - Checkout
18
Objectives Field Office Quality Assurance Understand what Construction Inspection (QA) is. Understand the different intervals of NRCS QA Understand the different types of NRCS construction contracts Understand the roles and responsibilities of the contractor and NRCS in QC/QA
19
Objectives Field Office Quality Assurance Understand what Construction Inspection (QA) is.
20
Inspector Inspector (Webster) – a person employed to inspect something. Inspector (NEH 645) – is the person assigned to do such activities as observe construction and make tests in order to determine on a day-to-day basis that the construction meets the contract requirements.
21
Inspection Is observing construction methods and procedures, examining and testing material used, and examining and testing the resulting finished work.
22
Role of the Inspector To insure that a project is installed at the location and to the dimensions and grades using the construction materials specified in the plan. To verify work complies with the contract requirements. Responsible for completion certification.
23
Inspector Responsibilities Know the drawings and specifications well Communicate with the Contractor Establish firm position on issues (not combative) Be decisive Follow through on all issues Point out work which does not comply Documentation is critical Inspectors do not give Contractor orders
24
Objectives Field Office Quality Assurance Understand the different intervals of NRCS QA
25
Types of Inspection Continuous Intermittent (Periodic)
26
Continuous Inspection The continuous presence of an inspector to observe or perform tests and measurements at critical points in operations and be available for consultation or emergency.
27
Continuous Inspection Required for construction activities where the quality cannot be verified by intermittent observations and work that cannot readily be removed or replaced if it does not meet the contract requirements
28
Continuous Inspection Examples of items requiring continuous inspection Earthfill Concrete placement Installing drains and filters
29
Intermittent Inspection May be adequate for certain phases of project activities depending on the complexity and potential impacts to public safety.
30
Intermittent Inspection Examples of items requiring intermittent inspection Dewatering Excavation (such as channel excavation) Forming and placing steel Mulching Painting Fencing
31
Objectives Field Office Quality Assurance Understand the different types of NRCS construction contracts
32
Construction Contracts Federal Contracting Local Organization (CLO) Private
33
Federal Contracts This contract type is governed by the Federal Acquisition Regulation (FAR) and is administered by the NRCS. Examples PL-566 (Watershed Projects) WRP EWP
34
CLO Contracts This contract type is governed by a project agreement between NRCS and the local sponsor, and the local sponsor administers the contract. Examples PL-566 (Watershed Projects) WRP EWP
35
Private Contracts This contract type is between a private individual or group and a contractor. NRCS may have a financial agreement with the individual or group. NRCS does not administer the construction contract. Most common Field Office type of contract. Examples EQIP or WRP
36
Objective Staying Fully Engaged Be Back in Ten
37
Objectives Field Office Quality Assurance Understand the roles and responsibilities of the contractor and NRCS in QC/QA
38
Construction Quality Control and Construction Quality Assurance Contractor NRCS
39
Construction Quality Control / Quality Assurance Is a construction inspection process. Duties are defined within a Quality Assurance Plan. Is a Contractor/NRCS partnership for success. Is a shared responsibility
40
Washington – Contractor Quality Control
41
Construction Quality Control (Contractor) Activities performed by the contractor to document that the work installed meets the minimum requirements of the contract (NEM Part 512.31 A). Implements the technical processes that examine, measure, analyze, and report on the project’s progress and conformance against the performance requirements.
42
Construction Quality Control (Contractor) Making sure that the results of what you have done are what you expected. Is the follow-through to ensure the expectations and objectives of the construction activity are met.
43
Construction Quality Control?
44
Construction Quality Assurance (NRCS) Activities performed by or for the owner, including observing construction methods and procedures, reviewing the contractor’s quality control (CQC) testing activities and test results, conducting periodic material testing to evaluate the CQC system and other measures to ensure compliance with the contract provisions (NEM Part 512.31 B).
45
Construction Quality Assurance (NRCS) Establishes the managerial processes that determine the organization, design, objectives, and resources for QA. Makes sure you are doing the right things, the right way. Provides the performance standards and processes of performance feedback. Sets the tone for project oversight and getting expected results.
48
Objectives Field Office Construction Awareness of common types of construction for Field Office (FO) projects Learn the role and responsibilities of the NRCS construction inspector Learn the difference between QC and QA Understand the difference between Construction QA and Technical Assistance QA
49
California – Irrigation pipeline Michigan – Livestock pipeline
50
Michigan – Pipeline
51
Michigan – Watering Facility
52
Washington – Waste Storage Facility
53
Michigan – Waste Storage Facility
54
Washington – Waste Storage Structure
55
Michigan – Waste Transfer
56
Kansas - Concrete Drop Box Structure
58
Kansas - Concrete Drop Box Structure Failure
59
Montana – Pumping Plant
60
Michigan – Irrigation VSD Pump Controller
61
Michigan – Center Pivot Irrigation
63
Washington – Precast Concrete Riser
64
Michigan – Agrichenmical Handling Facility (AHF)
65
Michigan – Roof Runoff (Gutters)
66
Questions?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.