Download presentation
Published byColleen Newton Modified over 8 years ago
1
Kansai International Airport (Phase-I) Foundation Case Study
By Rajul Teredesai CE 5333-Foundation Engineering Spring 2005
2
Overview Kansai International Airport (KIA)
3
Key Features Located on a biggest man-made island in Osaka Bay, Japan
Constructed cost over $14 billion The island of 4 X 1 km, constructed in around 18m of water, entirely from landfill Project Started in 1986 Opened for flights in 1996 The ASCE named KIA the #2 civil engineering project of the 20th century, second only to the Panama Canal
4
Kansai Airport Aerial View
5
Construction of Airport
Stage Activity Time I Subsurface Investigation 1 year II Sea Wall Construction 2 years III Landfilling 4 years IV Terminal Construction
6
Bore Hole Locations
7
Subsurface of the Kansai Airport Foundation
8
Seawall Construction Up to 40 ft. above sea level
Tripod blocks on seaward side for dissipation of wave energy
9
Seawall After Completion
Seawall Construction
10
Mechanism of Sand Drains
11
Advantage of Sand Drains
The weight of the piled sand forces the water in the clay to move outward along the sand piles.
12
Application of One Million Sand Drain at KIA
13
Reclamation Three distinct grades of sand, gravel and rock from nearby mountains Four years and 750 million cubic feet of fill Transportation on Ground: Conveyor Water: Barges
14
KIA Terminal Building Architect: Renzo Piano
15
Settlement Predictions
Lack of experience with construction on deep deposit of diluvial clay Expected settlement = 19 to 25 ft Actual settlement = 27 ft (by the end of island construction in 1990) It continued at the rate of 2 in/month
16
Settlement Calculations
Consolidation Settlement: Time Rate of Consolidation (Terzaghi 1925):
17
What Went Wrong in Predictions?
Un-conservative estimation of consolidation settlement Wrong estimate of the time required for completion of consolidation settlement Ineffectiveness of the sand drains in achieving the required success 100%
18
Incomplete Consolidation
19
Underestimation of Excess Pore Water Pressure
Airport Started Settlement Continued
20
Coping With The Problem of Continued Settlement
Basement of the terminal was lined with a quarter of a million tons of iron ore. Result: Island sank faster than the building it is trying to hold Installation of hydraulic jacks under the colums Result: No differential settlement between the columns of entire building
21
Learning From Mistakes
Using data actual settlement data obtained from 1st phase of project Analysis of 400-m-deep boring exploration State-of-the-art soil test methods Expected Settlement = 18 m
22
References A report by Justin Phalen, UC-Davis, 2002
The official website of KIA
23
Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.