Magic Valley Regional Airport Terminal Expansion and Remodel Magic Valley Regional Airport Terminal Modification Feasibility Study
2
Magic Valley Regional Airport Terminal Expansion and Remodel Background: Original air terminal constructed in 1946 Present terminal Bldg. constructed in 1996 September 11, 2001 October 2002-TSA deploys personnel, equipment, and new processes to United States airports. 2012- Twin Falls FAA Airport Master Plan formally identifies a need for improvements to the terminal.
3
Magic Valley Regional Airport Terminal Expansion and Remodel Background: Goals for the terminal improvements include- Increase capacity in the hold room, add restrooms Move checked bag screening “behind the wall” Improve circulation in the ticket lobby area March 2014-CSHQA Architects are hired to conduct a terminal modification feasibility study
4
Magic Valley Regional Airport Terminal Expansion and Remodel
5
Magic Valley Regional Airport Terminal Expansion and Remodel
6
Magic Valley Regional Airport Terminal Expansion and Remodel
7
Magic Valley Regional Airport Terminal Expansion and Remodel Phase I Terminal Study Process: 1.Stakeholder Involvement 2.Programming 3.Concept Design Alternatives 4.Schematic Design 5.Cost Estimating (Involving local contractors) 6.Financial Feasibility Study 7.Public Open House (Opportunity to review and comment) 8.Incorporating Sustainable Design
8
Schematic Design Magic Valley Regional Airport Terminal Expansion and Remodel
9
Schematic Design Magic Valley Regional Airport Terminal Expansion and Remodel SOUTHEAST PERSPECTIVE
10
Schematic Design Magic Valley Regional Airport Terminal Expansion and Remodel SOUTHEAST AERIAL NORTHEAST AERIAL
11
Schematic Design Magic Valley Regional Airport Terminal Expansion and Remodel HOLDROOM: LOOKING BACK TOWARD SCREENING HOLDROOM: VIEW FROM SCREENING
12
Magic Valley Regional Airport Terminal Expansion and Remodel Opinion of Probable Construction Costs: Building Remodel Area Construction Cost: $613,092 Building Expansion Area Construction Cost: $1,941,456 Total Construction Cost: $2,554,548 Includes 5% Contingency Total Design and Engineering Cost: $375,000 Total Project Cost: $2,929,548 Remodel Area = $124/sq. ft. Building Addition = $224/sq. ft.
13
Financial Feasibility Magic Valley Regional Airport Terminal Expansion and Remodel Project Cost Eligibility
14
Financial Feasibility Magic Valley Regional Airport Terminal Expansion and Remodel Project Funding Plan
15
Magic Valley Regional Airport Terminal Expansion and Remodel Summary of the Study A design concept which meets the goals identified in the Airport Master Plan A comprehensive cost estimate A funding approach which maximizes federal funding A project that improves the movement of passengers and baggage A project which cures current deficiencies and allows for future growth opportunities
16
Magic Valley Regional Airport Terminal Expansion and Remodel Questions ?