Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016
2
Executive Summary Site Work: Site-Playfield Contract: Contractors staging area and safety fence has been installed and are maintained each day. All SWPPP requirements are in place per the contract drawings. Elementary Parking & Bus Drop Off- Existing Sidewalks & Paving Removed Drainage Piping & Structures @ the Bus Loop Subsurface Retention Basin New subgrade materials installed Exterior Lighting @ Elementary Bus loop Domestic Water Line in front of Elementary Ball Field- Topspoil Stripped- Main storm water lines and structures set Site Clearing for buried asbestos roofing Bus Garage Storm Line Work Courtyard Demolition
3
General Building: 500 Wing- Abatement, Walls, ceilings, floors demolished & removed 500 Wing Underlayment Rifle range(s) Demo’d * Lead Abated Bus garage – Abatement, Tanks Removed, Addition foundation(s) Interior Demolition Vestibule Foundations
4
Roofing Contract: Work Scheduled to start in 2-3 weeks Theatrical: No work yet
5
Plumbing Contract: Demolition in 500 Wing – Crawl Space & Classrooms Starting to run piping in crawl space(s) Demolition in Bus garage Water Service from building to main Removal of old storage tanks Mechanical Contract: 500 Wing – Piping & Duct Work& Insulation Demolition in Crawl Space(s) & Classrooms Rifle range demolition Bus Garage Demo Start of ductwork in crawl space and 500 Wing
6
Electrical Contract: 500 Wing – Demolition in Crawl Space & Classrooms Running feeders in basement & crawlspace Main Duct bank outside 400 wing Site lighting feeders @ bus loop area Demo in Bus Garage Geothermal Contract: Mobilized & starting to drill
7
Project Financials
8
Summary to Date Contract- Site-Cunningham Original Contract Sum: $ 4,416, 641 Net Change by Change Orders: $ 0 Contract Sum to date:$ 4416641 Construction Allowance: $ 40,000 Allowance Balance: $ 40,000 Potential Change Orders$ 0
9
Contract- General Contractor- Murnane. Original Contract Sum: $ 9, 054,000 Net Change Change Orders: $ 0 Contract Sum to date:$ 135,441 Construction Allowance: $ 440,000 Allowance Balance: $ 440,000 Potential Change Orders$ -11,138
10
Contract-Roofing - RSI. Original Contract Sum: $ 1,729,900 Net Change by Change Orders: $ 0 Contract Sum to date: $ 0 Construction Allowance: $ 100,000.00 Allowance Balance: $ 100,000 Potential Change Orders$ 0
11
Contract- Plumbing- Burns Brothers. Original Contract Sum: $ 1,282,000 Net Change By Change Orders: $ 0 Contract Sum to date: $ 103,479 Construction Allowance: $ 40,000 Allowance Balance:$ 40,000 Potential Change Orders$ 0
12
Contract-HVAC- Burns Brothers Original Contract Sum: $ 6,262,500 Net Change by Change Orders: $ 0 Contract Sum to date: $ 329,603 Construction Allowance: $ 140,000 Allowance Balance: $ 140,000 Potential Change Orders$ 0
13
Contract-Electrical- S&L Inc Original Contract Sum: $ 3,390,300 Net Change By Change Orders: $ 0 Contract Sum to date: $ 50,616 Construction Allowance: $ 157,500 Allowance Balance: $ 0 Potential Change Orders$ 0
14
Contract-Geo Thermal- American Auger Original Contract Sum: $ 843,770 Net Change By Change Orders: $ 0 Contract Sum to date: $ 23,750 Construction Allowance: $ 30,000 Allowance Balance: $ 0