VA Primavera P6: Creating a Project and Work Breakdown Structure (WBS) Department of Veterans Affairs Office of Information and Technology IT Workforce.

Similar presentations


Presentation on theme: "VA Primavera P6: Creating a Project and Work Breakdown Structure (WBS) Department of Veterans Affairs Office of Information and Technology IT Workforce."— Presentation transcript:

1 VA Primavera P6: Creating a Project and Work Breakdown Structure (WBS) Department of Veterans Affairs Office of Information and Technology IT Workforce Development (ITWD) in collaboration with Product Development

2 Welcome and Introduction Slide 2 of 60 VA Primavera P6: Creating a Project and WBS VA Primavera Team: Mairye Bates IT Specialist / OIT PD/Open Source, Configuration & Tools Management Division Charlene Murray IT Specialist / OIT PD/Open Source, Configuration & Tools Management Division

3 Training Objectives Identify basic VA Primavera navigation Create projects in VA Primavera Create a Work Breakdown Structure (WBS) Slide 3 of 60 VA Primavera P6: Creating a Project and WBS

4 Training Overview Audience −Project managers and planners who need to create project plans Prerequisites −Understand how to connect and launch VA Primavera Project Management −Licensed user of Project Management Slide 4 of 60 VA Primavera P6: Creating a Project and WBS

5 CREATING A PROJECT AND WBS: PARTS OF THE SCREEN Section 1: VA Primavera P6: Creating a Project and WBS Slide 5 of 60

6 Parts of the Screen VA Primavera P6: Creating a Project and WBS Slide 6 of 60 Menu bar Windows bar Directory buttons

7 Parts of the Screen VA Primavera P6: Creating a Project and WBS Slide 7 of 60 Navigation bar Status bar

8 Maximizing Work Area Command bar VA Primavera P6: Creating a Project and WBS Slide 8 of 60

9 CREATING A PROJECT AND WBS: VA PRIMAVERA BASICS Section 2: VA Primavera P6: Creating a Project and WBS Slide 9 of 60

10 VA Primavera Basics User PreferencesEdit menu User Preferences HelpHelp menu Hint HelpView menu Hint Help VA Primavera P6: Creating a Project and WBS Slide 10 of 60

11 CREATING A PROJECT AND WBS: THE PROJECT MANAGEMENT PROCESS Section 3: VA Primavera P6: Creating a Project and WBS Slide 11 of 60

12 High Level Overview VA Primavera P6: Creating a Project and WBS Slide 12 of 60 Planning Ongoing Analysis Create project; set Project Attributes Define Work Breakdown Structure (WBS) Create Activities; set Activity Attributes Resource Attributes; Assign Resources Link activities in an Activity Network Set Initial Planning Baseline and OMB300 Baseline, if required Set the Project Status to Active Enter and submit Timesheets in Progress Reporter Progress the project: Approve Timesheets, Apply Actuals, & Reschedule Perform variance analysis Re-plan and reschedule as needed

13 CREATING A PROJECT AND WBS: INFORMATION NEEDED TO START A PROJECT FILE Section 4: VA Primavera P6: Creating a Project and WBS Slide 13 of 60

14 Start a Project File VA Primavera P6: Creating a Project and WBS Slide 14 of 60 Project Information  Project ID & Project Name  Responsible Manager (RM)  Enterprise Project Structure (EPS) node  Planned start date EPS URL: http://vaww.oed.portal.va.gov/program_management/p po/eps/default.aspx http://vaww.oed.portal.va.gov/program_management/p po/eps/default.aspx

15 CREATING A PROJECT AND WBS: STARTING A PROJECT FILE Section 5: VA Primavera P6: Creating a Project and WBS Slide 15 of 60

16 Create a Project File VA Primavera P6: Creating a Project and WBS Slide 16 of 60 Three ways to Create a New Project 1.Start a new project, or 2.Copy an existing project, or 3.Import a project

17 Start a New Project VA Primavera P6: Creating a Project and WBS Slide 17 of 60 1.Select File 2.Select New… 1.Select File 2.Select New… Create a New Project Wizard

18 Start a New Project Wizard VA Primavera P6: Creating a Project and WBS Slide 18 of 60

19 Start a New Project Wizard VA Primavera P6: Creating a Project and WBS Slide 19 of 60 1. Select the EPS node where the project will be created 2. Enter the Project ID & Project Name 1 2

20 Start a New Project Wizard VA Primavera P6: Creating a Project and WBS Slide 20 of 60 3. Set project’s Planned Start 4. Select Responsible Manager 3 4

21 Start a New Project Wizard VA Primavera P6: Creating a Project and WBS Slide 21 of 60 6 6. Select No, do not run the Project Architect. & select Finish 5 5. Leave the default Rate Type value as Price/Unit & Select Next

22 Copy an Existing Project VA Primavera P6: Creating a Project and WBS Slide 22 of 60 1. Select source Project to be copied 2. Select Copy 1. Select source Project to be copied 2. Select Copy 3. Select Node 4. Select Paste 3. Select Node 4. Select Paste 2 1 3 4

23 Copy an Existing Project VA Primavera P6: Creating a Project and WBS Slide 23 of 60 Customize your new Project

24 Copy an Existing Project Open Projects VA Primavera P6: Creating a Project and WBS Slide 24 of 60 Project ID & Project Name

25 Import a Project VA Primavera P6: Creating a Project and WBS Slide 25 of 60 Importing Files Not generally recommended Import files (resources excluded) from another instance of Primavera or from other software Can only be done in the Planning stage Select Import from the File menu and follow the prompts

26 CREATING A PROJECT AND WBS: PROJECT ATTRIBUTES Section 6: VA Primavera P6: Creating a Project and WBS Slide 26 of 60

27 Open a Project In Projects view locate and open the project in the EPS –Tip: An easy way to find a project is to use the keyboard shortcut, Control (CTRL) key + F key and search for Project ID or Project Name VA Primavera P6: Creating a Project and WBS Slide 27 of 60

28 Projects View and Project Status VA Primavera P6: Creating a Project and WBS Slide 28 of 60 Planning stage Project Status is set to Planned

29 Project Attributes VA Primavera P6: Creating a Project and WBS Slide 29 of 60 Set Project Attributes according to the Minimum Schedule Requirements (MSR) Show/Hide Bottom Layout

30 General Tab VA Primavera P6: Creating a Project and WBS Slide 30 of 60 Status set to Planned Project ID & Project Name Responsible Manager Project Web Site URL Status set to Planned Project ID & Project Name Responsible Manager Project Web Site URL

31 Dates Tab VA Primavera P6: Creating a Project and WBS Slide 31 of 60 Finish Actual Start Actual Finish Planned Start date Anticipated Dates generally not used Must Finish By

32 Notebook Tab VA Primavera P6: Creating a Project and WBS Slide 32 of 60 Notes

33 Notebook Tab VA Primavera P6: Creating a Project and WBS Slide 33 of 60 2 1 1. Select Notebook Topic 2. Select Add 1. Select Notebook Topic 2. Select Add

34 Budget Related Tabs VA Primavera P6: Creating a Project and WBS Slide 34 of 60 Budget tabs not in use

35 Codes Tab VA Primavera P6: Creating a Project and WBS Slide 35 of 60 Project Code: Administration Code Value: VHA Code Description: Veteran’s Health Administration Project Code: Administration Code Value: VHA Code Description: Veteran’s Health Administration

36 Codes Tab VA Primavera P6: Creating a Project and WBS Slide 36 of 60 1 1. Select Assign

37 Codes Tab VA Primavera P6: Creating a Project and WBS Slide 37 of 60 2 2. Select Assign

38 Defaults Tab VA Primavera P6: Creating a Project and WBS Slide 38 of 60 Suggestion: Set an Activity ID Prefix for your project

39 Resources Tab VA Primavera P6: Creating a Project and WBS Slide 39 of 60 Project Manager decides how Resources interact with the schedule 1

40 Resources Tab VA Primavera P6: Creating a Project and WBS Slide 40 of 60 Project Manager decides how Resources interact with the schedule 2

41 Resources Tab VA Primavera P6: Creating a Project and WBS Slide 41 of 60 Project Manager decides how Resources interact with the schedule 3

42 Settings Tab VA Primavera P6: Creating a Project and WBS Slide 42 of 60 Summarized Data

43 Settings Tab VA Primavera P6: Creating a Project and WBS Slide 43 of 60 Project Settings

44 Calculations Tab – Activities VA Primavera P6: Creating a Project and WBS Slide 44 of 60 Default Price / Unit for activities without resource or role Price/Units to $100/h Select Activity percent complete based on activity steps if you are using steps Leave defaults

45 VA Primavera P6: Creating a Project and WBS Slide 45 of 60 Select Update units when costs change on resource assignments Select Subtract Actual from At Completion Calculations Tab – Resource Assignments

46 CREATING A PROJECT AND WBS: WORK BREAKDOWN STRUCTURES (WBS) Section 7: VA Primavera P6: Creating a Project and WBS Slide 46 of 60

47 Format Selection Decide what format to use –Deliverable based –Phase or time based Things to consider –Development method – Agile, Waterfall, other –Organizational requirements - standard WBS –Management of work by different people VA Primavera P6: Creating a Project and WBS Slide 47 of 60

48 WBS View and WBS Status VA Primavera P6: Creating a Project and WBS Slide 48 of 60 Ensure WBS Status is set to Planned

49 WBS Elements VA Primavera P6: Creating a Project and WBS Slide 49 of 60 Add to create a WBS element Arrows to promote, demote or reorder WBS elements

50 General Tab VA Primavera P6: Creating a Project and WBS Slide 50 of 60 Edit WBS Code & WBS Name Set Status & Responsible Manager Edit WBS Code & WBS Name Set Status & Responsible Manager Anticipated Dates generally not used

51 Earned Value Tab VA Primavera P6: Creating a Project and WBS Slide 51 of 60 Using steps? Select Activity percent complete Using steps? Select Activity percent complete Not using steps? Select Custom percent complete set to 2 Not using steps? Select Custom percent complete set to 2 or

52 Notebook Tab VA Primavera P6: Creating a Project and WBS Slide 52 of 60 Notebook Topic Notes

53 WBS Milestones Tab VA Primavera P6: Creating a Project and WBS Slide 53 of 60 WBS Milestones

54 CREATE A PROJECT AND WBS: GENERAL SOFTWARE TIPS Section 8: VA Primavera P6: Creating a Project and WBS Slide 54 of 60

55 General Software Tips VA Primavera P6: Creating a Project and WBS Slide 55 of 60 General Software Tips To force a save File – Commit Changes (F10) To update to the latest information File – Refresh data (F5) When project updates are complete & before exiting PM; saves project changes to the database File – Close All (Ctrl+W) To leave PM and save user attributes to the server File – Exit In general, use the Primavera controls to close windows, not the Windows “X” in the upper right corner

56 Customize Columns VA Primavera P6: Creating a Project and WBS Slide 56 of 60 A-Z Z-A Hierarchy Column Order: Customize columns Column Sort: Some columns have a 3-level sort Column Sort: Some columns have a 3-level sort Column Sort: Select column headers

57 Group and Sort VA Primavera P6: Creating a Project and WBS Slide 57 of 60 Group By Group By Options Sort…

58 Creating a Project and WBS –– User Support Email Primavera@va.gov Slide 58 of 60 VA Primavera P6: Creating a Project and WBS


Download ppt "VA Primavera P6: Creating a Project and Work Breakdown Structure (WBS) Department of Veterans Affairs Office of Information and Technology IT Workforce."