ROV for telescope construction: possible use of Cougar Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Jean Roux, AIM for CPPM Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
2
ROV for telescope construction Do we need Rov? Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Jean Roux, AIM for CPPM
3
Junction Box SJB1 Package IL SJB2SJB3 shore Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
4
BJ frame Turret IL 2600m IL 1 Reprise d’effort Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
5
Câble eop Fast winch hook, camera, propulsion xy Deployment Pegasus Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
6
Approch Pegasus Propulsion IL 1 camera Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
7
Hook and lift IL Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
8
Interlink Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
9
Interlink DU meoc Connect DU on deck Test DU via BJ Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
10
DU deployment Interlink meoc Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
11
ROV for telescope construction and maintenance YES we need To do what? Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
12
Telescope construction & maintenance underwater operations MEOC survey and current check MEOC survey and current check Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
13
MEOC survey and current check MEOC survey and current check DU visual inspection DU visual inspection Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Telescope construction & maintenance underwater operations
14
MEOC survey and current check MEOC survey and current check DU visual inspection DU visual inspection Sismo installation Sismo installation Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Telescope construction & maintenance underwater operations
15
MEOC survey and current check MEOC survey and current check DU visual inspection DU visual inspection Sismo installation Sismo installation Unscrew BSS release bolts Unscrew BSS release bolts Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Telescope construction & maintenance underwater operations
16
MEOC survey and current check MEOC survey and current check DU visual inspection DU visual inspection Sismo installation Sismo installation Unscrew BSS release bolts Unscrew BSS release bolts Manipulate IL turrets Manipulate IL turrets Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Telescope construction & maintenance underwater operations
17
MEOC survey and current check MEOC survey and current check DU visual inspection DU visual inspection Sismo installation Sismo installation Unscrew BSS release bolts Unscrew BSS release bolts Manipulate IL turrets Manipulate IL turrets Operate wet meatable connectors Operate wet meatable connectors…..and….. Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Telescope construction & maintenance underwater operations
19
MEOC survey and current check MEOC survey and current check DU visual inspection DU visual inspection Sismo installation Sismo installation Unscrew BSS release bolts Unscrew BSS release bolts Manipulate IL turrets Manipulate IL turrets Operate wet meatable connectors Operate wet meatable connectors Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 ROV for telescope construction & maintenance underwater operations 80% unexpected 20% expected
20
Possible use of COUGAR Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
23
Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
24
Cougar versus Victor Cougar Victor Cougar Victor no dive lot of dives no dive lot of dives freelance crew permanent crew freelance crew permanent crew no ballast 70kg ballast no ballast 70kg ballast no basket large basket no basket large basket 2 five functions man 1 five functions man 2 five functions man 1 five functions man + a XYZ man & 1 seven functions man + a XYZ man & 1 seven functions man same power same power same power same power small support vessel big support vessel small support vessel big support vessel available not so available available not so available cheaper more expensive cheaper more expensive Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
25
Cougar Victor Cougar Victor no dive lot of dives no dive lot of dives freelance crew permanent crew freelance crew permanent crew no ballast 70kg ballast no ballast 70kg ballast no basket large basket no basket large basket 2 five functions man 1 five functions man 2 five functions man 1 five functions man + a XYZ man & 1 seven functions man + a XYZ man & 1 seven functions man same power same power same power same power small support vessel big support vessel small support vessel big support vessel available not so available available not so available cheaper more expensive cheaper more expensive Suggestion: find other activities before KM3 construction & try to contract same crew everytime Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
26
Cougar Victor Cougar Victor no dive lot of dives no dive lot of dives freelance crew permanent crew freelance crew permanent crew no ballast 70kg ballast no ballast 70kg ballast no basket large basket no basket large basket 2 five functions man 1 five functions man 2 five functions man 1 five functions man + a XYZ man & 1 seven functions man + a XYZ man & 1 seven functions man same power same power same power same power small support vessel big support vessel small support vessel big support vessel available not so available available not so available cheaper more expensive cheaper more expensive Suggestion: think about a large tool box deployed on sea bed or on the TMS if weather fine Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
27
Cougar Victor Cougar Victor no dive lot of dives no dive lot of dives freelance crew permanent crew freelance crew permanent crew no ballast 70kg ballast no ballast 70kg ballast no basket large basket no basket large basket 2 five functions man 1 five functions man 2 five functions man 1 five functions man + a XYZ man & 1 seven functions man + a XYZ man & 1 seven functions man same power same power same power same power small support vessel big support vessel small support vessel big support vessel available not so available available not so available cheaper more expensive cheaper more expensive manipulation could take more time Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
28
Cougar Victor Cougar Victor no dive lot of dives no dive lot of dives freelance crew permanent crew freelance crew permanent crew no ballast 70kg ballast no ballast 70kg ballast no basket large basket no basket large basket 2 five functions man 1 five functions man 2 five functions man 1 five functions man + a XYZ man & 1 seven functions man + a XYZ man & 1 seven functions man same power same power same power same power small support vessel big support vessel small support vessel big support vessel cheaper more expensive cheaper more expensive available not so available available not so available Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
29
Cougar Victor Cougar Victor no dive lot of dives no dive lot of dives freelance crew permanent crew freelance crew permanent crew no ballast 70kg ballast no ballast 70kg ballast no basket large basket no basket large basket 2 five functions man 1 five functions man 2 five functions man 1 five functions man + a XYZ man & 1 seven functions man + a XYZ man & 1 seven functions man same power same power same power same power small support vessel big support vessel small support vessel big support vessel cheaper more expensive cheaper more expensive available not so available available not so available Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009
30
Keys for success High level of activities High level of activities Trained Rov crew Trained Rov crew Procedures written and discussed Procedures written and discussed Expertise of operation manager Expertise of operation manager Reasonnable tasks for Rov class Reasonnable tasks for Rov class Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009 Joint meeting WP2, WP3, WP4, WP5 Paris 23-24 February 2009