Top 10 Things that Can and Do Go Wrong at the Department Level CReATE ver. 04/08 © 2008 Florida State University. All rights reserved
2
Number One Failure to submit proposal to SRS for review and approval prior to submission to sponsor
3
Number Two Principal Investigators, Chairs and/or Deans sign and accept award on behalf of FSU
4
Number Three Failure to obtain Chair and Dean approval for cost sharing/matching commitments or requests for indirect costs waivers prior to submitting to SRS
5
Number Four Applying wrong indirect cost rate in a proposal (i.e., using main campus rate when work will be performed at NHMFL; using off-campus rate when work will be performed on campus; using OSA rate for a research project)
6
Number Five Treating FSU faculty in proposal as a consultant
7
Number Six Expectation of receiving a salary increase simply because proposal included funds to cover an increase
8
Number Seven Expectation of receiving a salary increase simply because proposal included funds to cover an increase
9
Number Eight Performing work and/or delivering the results to a sponsor prior to receiving an award
10
Number Nine Authorizing personnel without an appointment to work on a project
11
Number Ten Subcontracting out more than 50% of an award
12
Number Eleven Making i nappropriate charges to projects and untimely initiation of cost transfers
13
Number Twelve Documenting or certifying an effort report without “a suitable means of verification” (i.e., first- hand knowledge) of work performance
14
Number Thirteen Failure to satisfy and/or properly document cost sharing commitments
15
Number Fourteen Nepotism – PI employing relatives on a project
16
Number Fifteen Relying on a program officer’s authorization for prior approvals required by terms of award
17
Questions