Details on the Accelerator Installation Plan E. Sargsyan & L. Lari www.europeanspallationsource.se 20 April 2016.

Similar presentations


Presentation on theme: "Details on the Accelerator Installation Plan E. Sargsyan & L. Lari www.europeanspallationsource.se 20 April 2016."— Presentation transcript:

1 Details on the Accelerator Installation Plan E. Sargsyan & L. Lari www.europeanspallationsource.se 20 April 2016

2 Introduction High Level Milestone – Beam on Target in June 2019 Partial and full access dates from CF Project 11 in P6 for deliverables from different IKC/WPs Time-area-activity relations – Understand better the sequence of main activities – Highlight parallel activities and cohabitation issues – Define required teams/resources – Overview and consistency check Logistics considerations needed Only one shift is considered so far 2

3 Gallery to Tunnel Mapping 3

4 Visualization (tunnel example) 4 ACCELERATOR SECTIONS ACCELERATOR SECTIONS ACCELERATOR COMPONENT S ACCELERATOR COMPONENT S TIME Activity A Activity B Activity A AREA Duration or time window Activity B Parallel activity of the same type – two or more teams Sequential activity of the same type – one team in cascade

5 Stubs installation 5 Two stubs in parallel Cable ducts 2 teams (4 persons) Total 1 week RF distribution 2 teams (4 persons) Total 2 weeks Cables pulling 2 teams (12 persons) Total 3 weeks Water cooling 1 team (2-3 persons) Total 2 weeks From 2018 3 teams are needed for CNPW

6 Tunnel installation – main stages 6 General Services Installation Cryo-Distribution System Installation & Tests Cryo-Modules & LWUs Installation NCFE Installation & Commissioning

7 Tunnel installation – general services 7 Drilling for supports 4 persons in parallel Total 6 weeks Floor markings 2 persons Work in cascade Total 4 weeks Water cooling install. 1 team (6 persons) Work in cascade Cable trays install. 2 teams (4 persons) Work in cascade Full access to Tunnel & FEB90 2 May 2017 Phase reference line installation 1 team (2 persons) Work in cascade Hardware commissioning in FEB90 Total 5 weeks Racks installation 2 teams (4 persons) Work in parallel Total 2 weeks Cable termination & test 4 persons in parallel Total 3 weeks Filling of racks WP technicians Total 9 weeks Cables pulling 1 team (6 persons) Total 3 weeks

8 Tunnel installation - NCFE 8 Shielding wall is installed in place of the DTL-5 to allow parallel work in SC Linac section ISRC & LEBT – Installation/assembly in the tunnel 2 weeks – Beam commissioning 13 weeks – LEBT dismantling 1 m upstream the RFQ (for bead-pull); need to re-assemble before the RFQ beam commissioning! RFQ – Assembly & tuning 2 weeks – RF conditioning 15 weeks MEBT – Installation/assembly in tunnel 4 weeks during the RFQ conditioning window – need to interrupt the RFQ conditioning – Pre-assemble MEBT sections to minimize time spent in tunnel! ISRC to MEBT beam commissioning 12 weeks DTL – Tanks 3&4 installation 2 weeks in parallel to LEBT partial dismantling – Tanks 3&4 RF conditioning 2 weeks in parallel with the RFQ conditioning – Tank 1 installation 2 weeks – Tank 1 RF conditioning 2 weeks ISRC to DTL-1 beam commissioning 5 weeks DTL – Tank 2 installation 2 weeks – Tank 2 RF conditioning 2 weeks ISRC to DTL-4 beam commissioning 5 weeks Shielding wall dismantling 1-2 weeks DTL – Tank 5 installation 2 weeks – Tank 5 RF conditioning 2 weeks The rest of the accelerator is already installed and cooled down Cold hardware commissioning ISRC to Dump beam commissioning Beam to target

9 Tunnel installation – CDS 9 Window of 6 months for CDS installation & testing for both spoke and elliptical sections CDS cooldown & commissioning (including warmup at the end) Total 4 weeks CDS install. & process pipe leak test 1 team for SPK (IKC) in cascade 1 team for MBL+HBL (IKC) in cascade Number of people TBD CDS pressure test (no access to tunnel) Total 1 week CDS final leak test & connection to Cryoplant 1 team for SPK (IKC) 1 team for MBL+HBL (IKC) Number of people TBD Total 1 week CDS final interconnections 1 team for SPK (IKC) in cascade 1 team for MBL+HBL (IKC) in cascade Number of people TBD

10 Tunnel installation – CM & LWUs 10 LWU installation 2 teams (6 persons) in parallel 2 week/LWU CM cooling & cable connections Cooling 1 team (1-2 persons) in cascade Cables 1 team (1-2 persons) in cascade 1 week/CM RF waveguide connections 1 team (2-3 persons) in cascade 1 week/CM CDS connections 1 team (persons TBD) in cascade 1 week/CM Cryomodule installation 1 team (3-4 persons) in cascade 1 week/CM LWU installation 3 teams (9 persons) in parallel 2 week/LWU CDS & CM cooldown Total 2 weeks Beam commissioning 6 weeks ISRC to DUMP 1 week ISRC to TARGET

11 Gallery installation - preview 11 Constrained by: Partial access dates Beam commissioning (June 2019 MS) Several parallel activities: General services (cabling, cooling) Installation & testing of RF equipment

12 Gallery installation – RF Cell example 12 Electrical - 2 RF cells/stubs in parallel – Cable trays, 2 teams (4 persons/1 week) Electrical – 2 rack rows in parallel – Cable terminations (4 persons/3 weeks) Electrical - 2 RF cells/stubs in parallel – Rack install. 2 teams (4 persons/2-3 weeks) Electrical - 2 RF cells/stubs in parallel – Cable trays install., 2 teams (4 persons/1 week) RFDS waveguides on walls –2 RF cells in parallel – 2 teams (4 persons/1 week) Electrical - 2 RF cells/stubs in parallel – Cable pulling 2 teams (12 persons/3 weeks) RFDS supports - 1 cell in cascade – 1 team (3 persons/2 weeks) Water cooling for RF – 1 cell in cascade – 1 team (6 persons/1 week) RFDS WG, circulators & loads – 1 cell in cascade – 1 team (3 persons/2weeks) Electrical - 1 RF cell in cascade – Cable trays to RF, 2 teams (4 persons/1 week) Klystrons – 2 RF cells in parallel (some exceptions) – 2 teams (4 persons, 1 week/klystron) Modulators – 2 RF cells in parallel (some exceptions) – 2 teams (4 persons, 1 week/modulator) Hardware commissioning of 6-8 weeks per RF cell at different stages

13 Summary High Level Milestone – Beam on Target in June 2019 – Constrain driving the developed strategy – Resource loaded plan requiring parallel activities and area consideration (cohabitation) Further details on sequences, durations & personnel – Installation procedures – Hardware commissioning/test procedures – Safety procedures – Benchmarking & tests (e.g. experience from other facilities, Integration Test Stand, stub mockup) Synchronization & coordination – Installation – Tests – Commissioning 13

14 Acknowledgements Thanks to all AD colleagues for discussions and inputs, in particular to E. Tanke for the first version of the installation sequence! 14


Download ppt "Details on the Accelerator Installation Plan E. Sargsyan & L. Lari www.europeanspallationsource.se 20 April 2016."