Download presentation
Presentation is loading. Please wait.
Published byJane Barber Modified over 8 years ago
1
2016 PG&E DATA CENTER BASELINE STUDY Jeff Stein, PE Brandon Gill, PE
2
About Taylor Engineering Data Center Baseline History Title 24 Part 6 Code Synchronization Electrical Baseline Updates M&V Guidelines Overview
3
Taylor Engineering Founded in 1995 Located in Alameda, California 8 Mechanical PE’s Expertise in : Data Centers Central Plants Laboratory Buildings Museums High Rise Buildings Control System Design Commissioning 6 Principals 2 Associates 6 Engineers
4
Authors Jeff Stein, PE, Principal Lead author for Title 24 2013 Data Center Code Requirements Lead Mechanical or Controls Designer: Multiple 20 to 40 MW Data Centers (NDA) Lead Cx Agent: 20 MW Data Centers in Salt Lake City, UT and Phoenix, AZ Principal Investigator for life cycle cost analyses to support Title 24 Part 6 code initiatives related to: Air and water economizers Minimum CRAC efficiencies Fan Power Limitations Humidity Control Limitation Containment Brandon Gill, PE, Senior Engineer Evaluation, Measurement & Verification Multiple Fortune 500 Custom Data Center Projects across PG&E and SCE territories Mechanical Design Mechanical Designer for a 20 MW Data Center Commissioning Commissioning Agent for 20 MW Data Centers in Salt Lake City, UT, and Phoenix, AZ
5
Published by PG&E in 2009 Adopted by statewide programs in 2010 Baselines developed from: Lead author’s experience Industry standard practice research Last updated in 2013 Last Version of the Baseline Covered: Mechanical Systems Transformers, UPS Systems, Rectifiers Baseline Origin
6
Standard Practice (not code) Baseline All systems but transformers No air or waterside economizing All data centers, excepting telecom facilities Load Dependent Air Management Schemes Containment not required globally Constant Speed Fan Controls All data centers except those with >10 kW/rack of load Key Old Baseline Features
7
2013 Title 24, Part 6 now covers data center mechanical systems Detailed M&V guidance was not provided by the existing baseline More detailed guidelines were necessary to address complicated baseline scenarios Why a new baseline?
8
Mechanical systems are now wholly covered by Title 24 Part 6 Prescriptive Requirements for Computer Rooms, Section 140.9 (a) Performance Path Requirements Documented in the 2013 Non-Residential Alternative Calculation Method (ACM) Reference Manual Implemented in IES, CBECC-COM, and EnergyPro v6 compliance modules All Title 24 “Computer Room” Specific Requirements reproduced in Baseline Appendix Mechanical Systems Baseline
9
Mechanical Baseline Highlights 20°F airside delta-T (implicitly assumes containment) Airside economizer 60°F design SAT Airflow and SAT Reset No humidity control System: <250 Tons: DX CRAC >= 250 Tons: CHW Plant Serving CRAHs
10
UPS Systems ENERGY STAR® Rating Baseline for New Construction Pre-existing (2013) Baseline for Retrofit Applications Rectifiers ENERGY STAR® Rating Baseline Low and Medium Voltage Transformers Revised based on 2016 Federal DOE Efficiency Mandate Electrical Systems Baseline
11
UPS Only Size Dependent 1.5 kW to 10 kW >10 kW Type Dependent Offline/Standby Line-interactive Double Conversion UPS and Rectifiers Communication Dependent E.g. Modbus/BACNet No Communication ENERGY STAR® Baseline
12
M&V Guidelines Provided for: New Construction Retrofit Includes Analysis Approach Requirements (e.g. retrofit isolation, whole building, etc.) Metering Points and Duration Requirements Regression Model Validation Targets Process Flowcharts Example M&V Procedures
13
Aims Simplify the Process Ensure High Rigor Level Results Requirements (1) verification site visit (1) month post-build IT load monitoring Mechanical Measures Compliance energy model true-up Electrical Measures Calculated (spreadsheet) approach New Construction M&V
14
Approach is baseline specific: Early Retirement (ER) and Retrofit Add-On (REA) Normal Replacement (NR) Replace on Burnout (ROB) New Load/New Added Equipment (NEW) Mixed Baseline Conditions Retrofit M&V
15
Early Retirement & Retrofit Add-On Whole Building Monitoring or Retrofit Isolation Pre- & Post-Retrofit Monitoring (4) months for weather dependent measures (1) month for non-weather dependent measures Curtailment only allowed with PG&E program manager approval Focus on robust regression analysis Targets: Mean Bias Error: 10% or less CV(RMSE): 30% or less Coefficient of Determination (R 2 ): 0.7 or more ***Regression targets globally applicable across project types Retrofit M&V
16
Normal Replacement Typically retrofit isolation (with an exception) Pre- & Post-Retrofit Monitoring Yes, Pre-Monitoring (4) months for weather dependent measures (1) month for non-weather dependent measures Curtailment only allowed with PG&E program manager approval Pre-monitoring Validate real world savings Post-monitoring used for: Real savings validation Code baseline savings analysis Retrofit M&V
17
Replace on Burnout Retrofit Isolation Post-monitoring only (4) months for weather dependent measures (1) month for non-weather dependent measures Curtailment only allowed with PG&E program manager approval Post-monitoring used for: Savings analysis Retrofit M&V
18
New Load/New Added Equipment Effectively treated as new construction projects Savings determined using simulation modeling Retrofit M&V
19
Mixed Baseline Existing and Title 24 Baseline Components Pre- and Post-Retrofit Monitoring Pre-Retrofit Model True-Up Adjust systems with T-24 baseline to reflect code level performance Savings Post-Retrofit Model – Trued-up Pre-Retrofit Model Retrofit M&V
20
Code Synchronization = Tougher Mechanical Baseline More efficient airside systems More efficient controls Electrical Baselines All linked to reference standards or Federal Requirements M&V Guidelines provided for New Construction and Retrofit Projects Study Summary
21
jstein@taylor-engineering.com bgill@taylor-engineering.com Questions
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.