Tuesday 9 th January 2007 1 Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.

Similar presentations


Presentation on theme: "Tuesday 9 th January 2007 1 Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos."— Presentation transcript:

1 Tuesday 9 th January 2007 1 Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos

2 Tuesday 9 th January 2007 2 Visible Achievements Target test! Linac side stairs (but not pained) Trench strengthened & new access installed Floor cleaned & painted Holes (almost) all drilled – last two to go Solenoid in hall Linde cryoplant delivered to hall (not tested) Q35s stripped down; coils tested – ready to rebuild “Cable Store”  MICE Local Control Room –Have ownership (PK coordinating)... Many more “invisible” achievements  need to be made real!

3 Tuesday 9 th January 2007 3 Project Schedule Outline of work in the hall: –Front end shielding disassembly –Re-establish shielding & create a “door way” –Install concrete plinth & rail system for solenoid –Installation & commissioning of Linde Cryo-plant –Build of shielding and installation of beam line Solenoid Dipole 2 Quad triplets 2 & 3 –Installation of beam line power supplies

4 Tuesday 9 th January 2007 4 Prerequisites –Shielding Detailed shielding design has only just started Delivery of first set of shielding blocks is booked Need to organise cleaning prior to use Some special pieces of steel may need to be ordered –Concrete plinth needs to be manufactured (dwg ready)... Ditto rail system –Solenoid Vac test, MLI & heat shield repair... Trolley modifications

5 Tuesday 9 th January 2007 5 Prerequisites/Issues –Dipole 2 & Quad triplet stands design underway at DL –Dipole 1 & First triplets stands Designs nearly ready for manufacture –Limited in space! –Resource issues Mechanical Installation workforce is 2+ Electrical may be ok (covered by RAL & DL)

6 Tuesday 9 th January 2007 6 Slightly further away –Magnetic Shielding Walls –MICE Plinth & support structure –Diffuser - spec –ToF0 & CKOV –ToF1 –Spectrometer & Tracker

7 Tuesday 9 th January 2007 7 Issues RF power system –completion of test stand in 2007 –relationship with CERN & phase 2 FC Module –Tender spec nearing completion Hydrogen System –Spec almost ready for review

8 Tuesday 9 th January 2007 8 Financial Status Report to OSC (December) –By end October: spend ~£3.7M –Represents ~½ of project budget before WM&C ~£1M on non-staff costs ~£2.4M on staff-cost (Budget: £3.4M) ~£140k on travel (Budget: £200k) PPRP & OSC  Cost 2 Completion –Current staff cost extrapolation (prelim) Likely to be significantly over budget –but good chance to be within C&WM! –Material needs to be justified against original plans!original plans

9 Tuesday 9 th January 2007 9 RISK Register Changes proposed (2b reviewed by PSAG): remove some “zeroed” risks Increase risk (27/31) ToF/uCal because of timescale & funding position Decrease risk (29) delivery of spec. sol. Addressing (35) by Cost 2 Completion review

10 Tuesday 9 th January 2007 10

11 Tuesday 9 th January 2007 11 Cellar filling

12 Tuesday 9 th January 2007 12

13 Tuesday 9 th January 2007 13 High Level Holes

14 Tuesday 9 th January 2007 14 Stairs, trench