March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th 2011 05:00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to MSS 09:00 Kautz Road Power Switch Rad Survey (possible limited access) 12:00ish Supervised Access Shutdown Ends: Thursday eve, March 10 th 2011 Friday Morning Kautz Road Power Reconfigured (09:00) Beam to users
2
March 7 th Shutdown Tunnel Work Replace MBEX beam pipe (MI-8) Leak Check/Repair 604-605 (RF Vacuum) Repair H2 IPM @104 Lay out ANU Magnet Stand Locations in MI-8 line Continue with Shielding improvements (MI-62 Penetrations) Leak Check P150 line (TeV side) Replace two MI-8 GeV line LEP Correctors Open beam pipe @113 for inspection Ion Pump Cable Re-Terminations Sump Pump Replacement (MI-50) Re-lamp MI-8 line Leak Check/Repair Vacuum on Recycler Cooling Tanks Sublimate TSPs BV100 – BV103 Sublimate Pelletron TSPs MI BPM 303 Inspect/support bus @ MI-50 alcove
3
March 7 th Shutdown Upstairs Work: FESS: Pump repairs Air Handler Maintenance Pond Pump seals (PV76, PV7) Clean Heat Exchangers at MI-10 and MI-60 (Mag., Cav., RF.) EE Support maintenance on many power supplies Additional: Open Pelletron
4
March 7 th Shutdown Tunnel Power Outages – No Lights: Thursday: 08:00-11:30 MI-10 power outage 12:45-16:30 MI-8 power outage