1 Car 1 Street Sweeper 10 Refuse Trucks 10 Pickups 6 Dump Trucks 10 Transit Busses 38 Total ◦ Started in 2011 with 4 Refuse Trucks ◦ 19 additional CNG vehicles on ordered which include: 2 Transit Connects, 4 Pickups, 1 Car, 1 Street Sweeper, 4 Dump Trucks, 1 Knuckle Boom, 6 Transit Busses
2
Time Fill (10 Posts, 2 Compressors) ◦ Design/Engineering and Site Work $109,000 ◦ Equipment and Installation 565,000 Total$674,000 Fast Fill (2 Hose) ◦ Design/Engineering and Site Work $ 40,000 ◦ Equipment and Installation 313,000 Total$353,000 80% ($818,000) of the original project was grant funded.
3
Equipment ◦ Processes to remove H2S, Siloxanes & CO2 ◦ Compression ◦ 5.7 Mile Pipeline Equipment Cost $1.5 Million Pipeline Cost 1.3 Million Total $2.8 Million Project partially funded by a $500,00 DOLA Grant
4
Renewable Identification Number (RIN) generation Intergovernmental agreement with City and County to purchase Compressed biogas (CBG) at fixed rate until the project cost have a net present value of 0. CBG sales @ $1.50 per GGE +RIN Revenue -Total Net Project Cost ($2.3 mm) = $0
5
More Specifically $(1.04) per GGE Production Costs $1.35 per GGE RIN Revenue $1.50 per GGE Fuel Revenue $ 1.81 per GGE 1.3 million gallons, 7+ years = $2.3 million
6
Jay Valentine Internal Services Manager City of Grand Junction, CO 250 N. 5 th Street Grand Junction, CO 81501 jayva@gjcity.org (970)244-1517