DAVIS SR. HIGH SCHOOL ALL-STUDENT CENTER (MULTIPURPOSE BUILDING) PROGRAMMING OPTIONS August 6, 2015
2
DHS Stakeholder Group Identifies Project Needs Possible Project Funding Sources HMC Architects – Space Needs vs. Budget Board to Selects Final Program Budget Design Process Milestones Stakeholder Group Involvement with Final Design Project Approval & Bidding Phase PROCESS 2
3
PROGRAM / PLANNING VALUE OPTION #1 3 Total Project Funding $5.5M – Grande Property Sale Project Budget Drives Space Improvement Needs Total Areas Improved Reduced by 5,158 Sq. Ft. Program Areas Deleted Student Union/Store Kitchen Prep Areas Career Ctr. & Classroom
4
CONCEPTUAL FLOOR PLAN VALUE OPTION #1 4
5
BUDGET ESTIMATE OF VALUE OPTION 5 Total Estimated Hard Construction - $ 3.0M Contractor General Conditions/Profit - $ 401K Design Contingency - $ 509K Project Escalation (5%) - $ 195K Soft Costs (Architect Fee, Reports, DSA) - $ 680K Project Contingency (10%) - $ 478K Total Project Cost (Estimated) $ 5.26M
6
PROGRAM / PLANNING ORIGINAL PROGRAMMING 6 Total Project Funding $7.2M – Sources Grande Property Sale - $5.5M COPS - $1.7M Project Needs Drives Budget Needs Total Areas Improved 14,354 Sq. Ft. Added MPR Program Areas Student Union/Store Kitchen Prep Areas Career Ctr. & Classroom Storage Student Activities Director Office
7
ORIGINAL PROGRAM FLOOR PLAN 7
8
BUDGET ESTIMATE OF ORIGINAL ASC PROGRAM 8 Total Estimated Hard Construction - $ 4.42M Contractor General Conditions/Profit - $ 593K Design Contingency - $ 501K Project Escalation (5%) - $ 275K Soft Costs (Architect Fee, Reports, DSA) - $ 952K Project Contingency (10%) - $ 472K Total Project Cost (Estimated) $ 7.21M
9
June25, 2015 Programming Presentation August 6, 2015Final Program/Budget Options November 27, 2015District Approves Final Design March 1, 2016District Approves Const. Docs June 1, 2016Project Out to Bid July 1, 2016District Approves Bid (NTP) July 2016 – Sept. 2017Construction Activities August 2017Project Complete SCHEDULE 9
10
NEXT STEPS 10 Selection of Design Option (Budget Capped) Acceptance of Programming Scope Definition Commission HMC to proceed with Design Effort Finalize Design/Construction Milestones Re-Convene Stakeholder Teams Apply for Supplemental Funding Sources
11
RENDERING OF NEW ASC 11
12
QUESTIONS 12 QUESTIONS AND COMMENTS