SPORTSVILLE MOUTERE HILLS COMMUNITY COMPLEX
2
Rangers Rugby Club Situation prior to new complex. Strategic Planning process. Identified Issues for growth. Solutions.
3
Other community groups RSA. Schools. Tennis. Playgroup. Soccer. Youth Group. Domain board Church. Wine growers. Business association. Other sports codes. Local sponsors. Local Council.
4
Steps towards start up. Must have an identified need. Must have a realistic proposal. Must have community support. Must have the ability to raise funds. Must have local body support. Must have an achievable time frame. Must have a pathway to completion.
5
TDC Council Input. Regional overview of development. Must provide community facilities. Well aware of the process required. Land purchase and negotiation. Community facility rate, July 2003. Up to 80% of costs funded. Compliance requirements. Advertising and promotion.
6
Designing the building. Possibly the most difficult part. All user groups had input. Architect on Trust. Code requirements. Research around preferred options. Consensus had to win. Plan 7B before accepted.
7
Considerations in design. Totally accessible. Capable of hosting specific numbers. Stage for productions. Commercial kitchen and bar. Water storage and catchments. Service access. Sports viewing and general outlook.
8
Funding and Sponsorship. Donations. Sale of Assets. Naming Rights. Business sponsorship. Community Vine Sponsorship. A Country occasion. Annual auction. Gaming machines and others. Internal event.
9
Building the Complex. Local Contractor engaged. Trust board input into all decisions. Sub Contractors.
10
Building Completion Opened two weeks before Rangers 50 th Jubilee. Major promotion around opening with a dawn blessing and an open day. Finished on time, within budget and with funds left in reserve already allocated for completion of specific projects.
11
Management Management Structure. Accommodating Key Stakeholders. Volunteer Based? Acceptance. Board Structure. Governance or Operation.
12
6 years on. Financial situation Current User Groups. Current programs. Staff. Board member training. Strategic planning. Moutere Hills Community Complex
14
Moutere Hills Community Complex. By the community for the community.