Downtown Action Team Update Stockton City Council August 23, 2005 Steve Pinkerton Redevelopment Director.

Similar presentations


Presentation on theme: "Downtown Action Team Update Stockton City Council August 23, 2005 Steve Pinkerton Redevelopment Director."— Presentation transcript:

1 Downtown Action Team Update Stockton City Council August 23, 2005 Steve Pinkerton Redevelopment Director

2 Council Goal Revitalize Downtown and the Waterfront Revitalize Downtown and the Waterfront

3 Downtown Security Phase I was completed in September 2004 Phase I was completed in September 2004 Phase II was completed in April 2005, with 9 new security cameras added. Phase II was completed in April 2005, with 9 new security cameras added. A new digital system, which allows up to 32 cameras to be viewed at any given time, was installed and operating by April 2005. A new digital system, which allows up to 32 cameras to be viewed at any given time, was installed and operating by April 2005. There are approximately 35 security cameras currently located in the Downtown area. Two were installed at the Downtown ballpark. There are approximately 35 security cameras currently located in the Downtown area. Two were installed at the Downtown ballpark. 5 additional street lights are being considered for the ballpark area. 5 additional street lights are being considered for the ballpark area.

4 Location of Security Cameras (as of May 2005)

5 Wayfinding Program Directional banners have been installed with Weber Avenue signs installed later this year

6 Facade Improvement Forgivable Loan Program Projects underway or recently approved include: Projects underway or recently approved include: LDF Enterprises – 1700 W. Fremont LDF Enterprises – 1700 W. Fremont Thurman Realty – 2652 E. Main Thurman Realty – 2652 E. Main Ebenezer EDC – 701-711 E. Weber Ebenezer EDC – 701-711 E. Weber Tom McKeegan – 520-534 E. Weber Tom McKeegan – 520-534 E. Weber Center for Positive Prevention – 729 N. California Center for Positive Prevention – 729 N. California Dave Moscovic – 1045 N. El Dorado Dave Moscovic – 1045 N. El Dorado

7 “The Stockton” restoration nears completion and residents have moved in! Retail tenant improvements underway Retail tenant improvements underway 96 studio & 60 one-bedroom units of senior housing 96 studio & 60 one-bedroom units of senior housing 25,000 sq ft. retail 25,000 sq ft. retail Basement parking Basement parking Rooftop garden restaurant Rooftop garden restaurant Negotiations continue for retail tenants Negotiations continue for retail tenants Open House held March 17, 2005 Open House held March 17, 2005 Hotel Stockton

8 Starbuck’s Coffee Starbuck’s Coffee Cold Stone Creamery Cold Stone Creamery Moo Moo’s Moo Moo’s California State Automobile Assn California State Automobile Assn H&R Block H&R Block Emperor Express Emperor Express Plus 3 more restaurants on the way… Plus 3 more restaurants on the way… Red Brick Pizza Red Brick Pizza Thai Palace Thai Palace Misaki Sushi Misaki Sushi City Centre Cinemas Retail

9 Edmund S. “Ed” Coy Garage Under construction Under construction Garage should be completed by December 2005 Garage should be completed by December 2005

10 Southern Pacific Depot Grand Opening held October 24, 2003 Recently awarded $180,000 Planning Grant from CalTrans BeforeBeforeBeforeBefore A AAfterfterAAfterfter

11 Downtown Transit Center Located on Weber Avenue, project includes bus staging area, retail, SJRTD offices and Police Bike Patrol Located on Weber Avenue, project includes bus staging area, retail, SJRTD offices and Police Bike Patrol Demolition complete Demolition complete Site work underway Site work underway

12 The Henery Proposals for the renovation of The Henery were received in May 2005 and are being reviewed. Proposals for the renovation of The Henery were received in May 2005 and are being reviewed.

13 Kress Building (Main and Weber) The Kress Building is completely leased out. The Kress Building is completely leased out. Open House set for August 18 at 4:30 p.m. Open House set for August 18 at 4:30 p.m. Tenants include: Tenants include: Law Library of San Joaquin Law Library of San Joaquin California Rural Legal Assistance California Rural Legal Assistance The Bar Association of San Joaquin County The Bar Association of San Joaquin County Suntag & Feuerstein Suntag & Feuerstein

14 Block 15 – 500 E. Main Street Proposal submitted for approval by the City Council/Agency at August 16, 2005 meeting. Proposal submitted for approval by the City Council/Agency at August 16, 2005 meeting.

15 WorkNet Office Project Development agreement approved February 24, 2004 Development agreement approved February 24, 2004 Under construction Under construction 52,000 sf building at Lincoln & Washington 52,000 sf building at Lincoln & Washington County expects to begin moving in next week County expects to begin moving in next week

16 Proposed Office Buildings on the South Shore Office complex at Lincoln & Washington Streets Office complex at Lincoln & Washington Streets Currently under negotiation Currently under negotiation

17 Downtown Marina The final Department of Boating and Waterways ("DB&W") loan documents were signed in June. The final Department of Boating and Waterways ("DB&W") loan documents were signed in June. The new preliminary design was forwarded to DB&W shortly thereafter and are waiting to receive approval for the new design. The new preliminary design was forwarded to DB&W shortly thereafter and are waiting to receive approval for the new design.

18 Gleason Park Bound by Lafayette, Stanislaus, Hazelton & California Streets Bound by Lafayette, Stanislaus, Hazelton & California Streets Residential Developments Residential Developments Commercial Development Commercial Development Alex G. Spanos Elementary School Alex G. Spanos Elementary School Gleason Park Reconstruction Gleason Park Reconstruction Agency is making offers on properties within SUSD block. Agency is making offers on properties within SUSD block.

19 “Vintage Plaza” is Coming First new detached homes in Downtown in over 60 years! Located at Sonora Street between California & American Streets First new detached homes in Downtown in over 60 years! Located at Sonora Street between California & American Streets 16 detached units on less than 1 acre 16 detached units on less than 1 acre 1,531 to 1,589 square feet – 3 bedroom, 2 ½ baths 1,531 to 1,589 square feet – 3 bedroom, 2 ½ baths Break ground later this year Break ground later this year

20 More to look forward to… More to look forward to… in 2005!


Download ppt "Downtown Action Team Update Stockton City Council August 23, 2005 Steve Pinkerton Redevelopment Director."