OVERVIEW Review of completed projects Update on large construction projects Update on other miscellaneous projects
3
COMPLETED PROJECTS Athletic Complexes $12M Mat-Su Day School $12.4M Valley Pathways $22.5M Big Lake ES Reno Ph I $2.2M Houston/Palmer Jr MS Lockers $335K Flooring Replacements Ph I $2M Palmer HS Mechanical Upgrades $5.5M Trapper Creek ES Roof $1M Swanson ES Ext Upgrades $200K Willow ES Roof $1.3M Joe Redington Sr MS/HS $65M CTHS Addition $16M Houston HS Exterior Siding $600K ADA Upgrades District Wide $1.5M Washroom Upgrade District Wide $800K Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M
4
DENA’INA ES $26.5M Design: Bettisworth North Construction: FE Const. 44,224 SF K through 5 school Work started April 2015, approx. 75% complete On schedule to occupy summer 2016
5
DENA’INA ES Classroom Exterior Siding
6
IDITAROD ES $25.2M Design: MCG Construction: Collins 50,605 SF replacement school. Pre-K thru 5 Work started May 2015, approx. 85% complete On schedule to occupy spring/summer 2016
7
IDITAROD ES Gymnasium Classroom
8
FRONTERAS CHARTER SCHOOL $6.9M Contractor: Howdie Const. Funded by USDA loan and $500K from MSB Access road from Seward Meridian is in place Work started July 2015, approx. 60% complete On schedule to occupy summer 2016
9
FRONTERAS CHARTER SCHOOL Classroom Exterior
10
ATHLETIC FIELD IMPROVEMENTS $6.4M Play court upgrades at Finger Lake, Snowshoe, Larson, Glacier View and Houston High completed in 2014 All summer 2015 work complete with the exception of the Iditarod softball/baseball turf in-fields which are on weather hold until May 2016
11
ADDITIONAL PROJECTS Back-Up Generators, District Wide $2.6M - Scope includes base bid - Wasilla MS, Wasilla HS, Palmer HS -- Awarded alternates - Big Lake ES, Butte ES, Snowshoe ES, Willow ES and the Operations & Maintenance Building - Assembly approved construction contract to Wolverine March 1 - Work scheduled to start summer break 2016 Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K - Remaining work involves new corridor lighting and ceiling tiles - Assembly approved construction contract to Wolverine Jan 12 - Work scheduled for summer break 2016 District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction (Ph I) - Scope includes upgrading building controls from pneumatic to direct digital controls and with Phase I approximately 65% complete - Phase II was advertised with contract to FE Contracting scheduled for Assembly approval Apr 19
12
ADDITIONAL PROJECTS cont. District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - New LED Gym lighting project is complete - Partial window replacements at 18 schools will be advertised this month for summer 2016 construction Flooring Replacements $900K (2010 and 2011 flooring bond balances) - Carpet scope includes Butte, Cottonwood, Finger Lake, Goose Bay, Sherrod, Swanson, Trapper Creek, and Willow Elementary Schools for a total of 108,000 SF of new flooring -- Assembly approved carpet install contract to CYS Enterprises April 5 - New gym floors at Big Lake and Willow ES will advertise this month Roof Bond Balance $800K - Sutton ES reroof and Tanaina ES roof modifications closed Jan 2016 - Contract to EP Roofing approved Feb 16 for summer 2016 completion
13
QUESTIONS