LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.

Similar presentations


Presentation on theme: "LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team."— Presentation transcript:

1 LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team

2 MAC No.19, 15-17 June 2006GR, AT-ACR2 Content Layout Fabrication status Installation status Schedule Conclusions

3 MAC No.19, 15-17 June 2006GR, AT-ACR3 QRL layout QRL is a continuous cryostat of ~3.2 km length no header (4 or 5) sectorisation  9 vacuum sub-sectors  vacuum insulation separate from machine QRL elements in one sector ~ 38 service modules ~ 40 fixed point/vacuum barrier elements ~ 235 straight pipe elements ~ 10 steps/elbows ~ 1-2 cryogenic extensions

4 MAC No.19, 15-17 June 2006GR, AT-ACR4 QRL layout Sector 3-4 8 sectors: - 7 installed by Air Liquide - 1 re-installed by CERN  = 650 mm E-F= 50-75 B,C,D = 4-20 K Sector 5-6

5 MAC No.19, 15-17 June 2006GR, AT-ACR5 QRL fabrication status

6 MAC No.19, 15-17 June 2006GR, AT-ACR6 QRL installation status External supports (~ 700/sector) Progress: 97 %

7 MAC No.19, 15-17 June 2006GR, AT-ACR7 QRL installation status Positioning and alignment (~ 325 elements/sector) Progress: 86 %

8 MAC No.19, 15-17 June 2006GR, AT-ACR8 QRL installation status Welding and testing: ~ 325 interconnections/sectors  ~ 2000 inner welds made by orbital welding machine »~ 180 “O” type interconnections (1 butt-weld per header) »~ 75 “C” type interconnections (2 butt-welds per header) »~ 70 “A” type Interconnections (3 welds per header)

9 MAC No.19, 15-17 June 2006GR, AT-ACR9 QRL installation status “C” type interconnections “A” type interconnections Special interconnections Inner weld progress: 85 % - Nominal rate: 20 int./w - Achieved rate: 30 int./w

10 MAC No.19, 15-17 June 2006GR, AT-ACR10 QRL installation status Mounting of superinsulation Welding of external compensators and visual check External weld progress: 81 % - Nominal rate: 20 int./w - Achieved rate: 35 int./w

11 MAC No.19, 15-17 June 2006GR, AT-ACR11 QRL installation status NDT tests »Internal (video camera) and external visual control: 100% »Radiography tests: from 100% to 10% as a function of weld quality »Leak tightness tests: 100 % Helium to insulation vacuum –each weld (header pressurization at 1 bar): < 10 -9 mbar·l/s –each sub-sector (header pressurization at 3 bar): < 10 -8 mbar·l/s –each sector (in parallel with pressure test): < 10 -7 mbar·l/s Air to insulation vacuum: 10 -5 mbar·l/s

12 MAC No.19, 15-17 June 2006GR, AT-ACR12 QRL installation status Percentage of defects of inner welds (visual and radiographic inspections) for the 3 types of interconnections: »According to machine parameters two categories are defined (B and CDEF) Air Liquide target value: 3% Main defects: porosity, lack of fusion, metallic inclusions

13 MAC No.19, 15-17 June 2006GR, AT-ACR13 QRL installation status Number of internal leaks (helium to insulation vacuum) »on installation welds: 8/12000 7 detected with the clamp shells 1 detected in sector 6-7 during the test of the sub-sector (reason: operator error during the test with clamp shells) »on internal compensators: 2 (sector 3-4) »on backing rings: 2 (sector 4-5) »on service modules (header F): 7 (6 in sector 8-1 and 1 in sector 4-5) Number of external leaks (air to insulation vacuum) on installation welds: »Sector 8-1: 12/4250 »Sector 4-5: 10/4250 »Sector 3-4: 11/4250 »Sector 5-6: 3/4250 »Sector 6-7: 6/4250

14 MAC No.19, 15-17 June 2006GR, AT-ACR14 QRL installation status Heat inleaks [W] E+F (50-75 K) B+C+D (4-20 K) Calculated9850593 Measured 9000 +/- 400 (~ 2.8 W/m) 634 +/- 50 (~0.2 W/m) Sector 8-1: - installation completed - pressure, leak and cold tests successfully performed

15 MAC No.19, 15-17 June 2006GR, AT-ACR15 QRL installation status Sector 4-5: - installation completed - pressure and leak test without the JR successfully performed - JR and sub-sector A pressure tested in parallel with the magnets

16 MAC No.19, 15-17 June 2006GR, AT-ACR16 QRL installation status Sector 3-4: - installation completed - pressure and leak test successfully performed - repair of an external leak in sub-sector I under way

17 MAC No.19, 15-17 June 2006GR, AT-ACR17 QRL installation status Sector 5-6: - installation completed - pressure and leak test successfully performed

18 MAC No.19, 15-17 June 2006GR, AT-ACR18 QRL installation status Sector 6-7: - installation completed - pressure and leak test successfully performed

19 MAC No.19, 15-17 June 2006GR, AT-ACR19 QRL installation status Sector 2-3: - 3 teams working in sub-sectors A to I - installation progress: 74.4 % - 3 sub-sectors under pumping

20 MAC No.19, 15-17 June 2006GR, AT-ACR20 QRL installation status Sector 1-2: - 3 teams working in sub-sectors E to H - installation progress: 11.7 %

21 MAC No.19, 15-17 June 2006GR, AT-ACR21 QRL schedule

22 MAC No.19, 15-17 June 2006GR, AT-ACR22 QRL dashboard Total to be installed contract

23 MAC No.19, 15-17 June 2006GR, AT-ACR23 Conclusions Fabrication »Production of pipe elements, fixed points and service modules under completion »Production of steps/elbows foreseen to be completed in CW30 (compatible with installation schedule) Installation »Installation of the last two sectors under way Thermo-mechanical validation »Sectors 8-1, 4-5, 3-4, 5-6 and 6-7 (and 7-8 sub-sectors A and B) successfully leak and pressure tested »Sector 8-1 (and 7-8 sub-sectors A and B) successfully cold tested Schedule »At present installation is about 2.5 weeks in advance (schedule revised in November 2005)


Download ppt "LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team."