1 | Eton Range Realignment Project RAAG Presentation 10 March 2016.

Similar presentations


Presentation on theme: "1 | Eton Range Realignment Project RAAG Presentation 10 March 2016."— Presentation transcript:

1 1 | Eton Range Realignment Project RAAG Presentation 10 March 2016

2 2 | Agenda Deficiencies of Existing Crossing Safety Improvements Reinforced Earth Embankment (REE) Traffic Management Project Details Drive-thru Video

3 3 | Site of Fatal Accidents HV Traction Issues (11%) Width Constraints Slope Stability Issue High Speed Approaches (Up & Down) Composite Curve Deficiencies of Existing Crossing Hairpins 50 metre radii

4 4 | RE Embankment Vertical grade 7.5% 4 lanes 5 x CCTV Cameras for incident management Breakdown curves to control approach speed Safety Improvements Hairpin radius improvement, 55m to 75m

5 5 | Increase speed sooner Alignment follows the crest of ridge Sidelong cut/fill profile Traffic diverted to allow construction of up alignment Safety Improvements Traffic change over point for incident management

6 6 | Reinforced Earth Embankment (REE) Height 10m – 44m

7 7 | Reinforced Earth Embankment (REE)

8 8 | Reinforced Earth Embankment (REE)

9 9 | Traffic Management Stage 1A Site Office & Entry Traffic Lanes Work Zones Overtaking Lane Closed Duration 2 Months

10 10 | Traffic Management Stage 1B Site Office & Entry Traffic Lanes Work Zones Overtaking Lane Closed Duration 15 Months

11 11 | Traffic Management Stage 2 Site Office & Entry Traffic Lanes Work Zones Overtaking Lane Closed Duration 12 Months

12 12 | Traffic Management Stage 3 Site Office & Entry Traffic Lanes Work Zones Duration 1 Months

13 13 | Traffic Management Two Lane Operation at All Times except when Blasting All Motorist: VMS Boards used for advanced warning to roadworks Public notices on TMR website for project updates: www.tmr.qld.gov.au/Projects Stakeholder email notification group Heavy Vehicles: Truck pull-off areas maintained – OSOM management performed as normal by Police OSOM restrictions on TMR website - Advised to contact Fulton Hogan prior to travelling: www.tmr.qld.gov.au/business-industry/Heavy- vehicles/Excess-mass-and-dimension-conditions Stakeholder email notification group heavy haulage Permit Conditions

14 14 | Traffic Management Contractor: Fulton Hogan Construction Pty Ltd Project Duration: 16 March 2016 – Late 2018 If you would like to be added to stakeholder email notification group, please email: Mackay.Office@tmr.qld.gov.au Mackay.Office@tmr.qld.gov.au If you wish to contact the TMR project team, please email: ERRP@tmr.qld.gov.au CC: mark.g.weatherley@tmr.qld.gov.au CC: emma.k.lyons@tmr.qld.gov.auERRP@tmr.qld.gov.aumark.g.weatherley@tmr.qld.gov.auemma.k.lyons@tmr.qld.gov.au Project Manager: Mark Weatherley (Ph: 0459 800 467) Project Engineer: Emma Lyons (Ph: 0467 817 802)