Wastewater Department Staff Report 2015
2
Gravity Thickener and pumps Replacement of both thickener pumps, valves, controls, grinder and electrical system Replacement of entire G.T. to include new coating, concrete repair, walkway, instrumentation, drive shafts, energy displacement baffles, flights, weirs and scum trough.
3
Primary Dewatering Processes Belt Filter Press, 12-14% Solids Screw Press, 30-32% Solids Replacement of entire system to include new dewatering equipment, inlet valves, sludge pipeline, electrical system, polymer system, flow meter, conveyors, holding area, instrumentation and structure
4
Secondary Clarifiers Replacement of entire system to include new drive shafts, inlet valves, energy displacement baffles, flights, chains, wear shoes, weirs and scum troughs Increased reliability, stability and capacity of the biology system and compliance
5
Blowers Existing natural gas blowers were replaced with high efficiency electric turbo blowers Saving the city an average of $8,000 per month in utility fees
6
Aeration Basins Replacement of entire system to include new stainless steel piping, diffusers, fiberglass walls, valves, and instrumentation Increased reliability, stability and capacity of the biology system and compliance
7
Supervisory Control and Data Acquisition Replacement of entire system to include new programmable logic controllers, human machine interface, fiber optic lines, servers, computers, instrumentation and program Provides real-time monitoring and controls and the ability to track and trend the system
8
Real-Time Monitoring
10
Effluent Sampling Biochemical Oxygen Demand 20142015 January7.00 8.65 February6.31 7 March8.90 9.1 April7.20 8 May8.92 6.8 June3.30 5.8 July4.90 NA August16.30 NA September6.50 NA October5.10 NA November6.80 NA December2.80 NA Yearly Avg 7.007.56 Min 2.805.80 Max 16.309.10
11
Effluent Sampling Tjeldahl Nitrogen
12
Effluent Sampling Ammonia-Nitrogen
13
Effluent Sampling Nitrate-Nitrogen
14
Effluent Sampling Total Nitrogen
15
Utility consumption (electrical)
16
Pond Maintenance Restoration of Pond 1, 2, 3, and 5 including Restored 3:1 slope Leveled top bank and bottom bed Removal of brush Pond 4 still needs to be rehabbed, found a large amount of material in the bottom due to lack of maintenance done in the past. Increase in percolation efficiency and pond capacity
17
Dean’s Wash Complete Restoration of Dean’s Wash including 2 Box culverts Primary effluent lines Primary sludge lines Electrical duct banks Compacted slopes Fencing
18
Collection System Staff Report
19
Manhole Maintenance and Repair Replacement of entire unit Increase in reliability and accuracy of permit required samples
20
General Cleaning
21
Restaurant Cleaning & Inspections
22
Sewer Cleaning & Inspections