1
September 2015 FOG STUD I0
2
Agenda Project Overview Building Improvements Existing Conditions Survey Restroom Accessibility Electrical and Lighting Wood Siding, Railings and Fascia Minor Structural Repairs Swallow Nesting & Building Maintenance Recommended Habitat Solutions Interpretive Center Schedule Boardwalk Improvements Interpretation Feedback
3
Project Overview
4
Existing Building Plan
5
Building Repairs New wood siding New wood decking New wood fascia New wood guardrails New wood vertical guardrail elements
6
Building Improvements - Restrooms
7
Restroom Plan Change Existing Restroom LayoutProposed Restroom Layout Toilet Sink Urinal Trough Sink Hand Dryer Changing Station Drinking Fountain ABCDEFGABCDEFG A A A A A ABB C B B G G D C BB F F
8
Restroom Finishes
9
Restroom Fixtures
10
Electrical and Lighting Upgrades Electrical Panel to be replaced Existing Entry Lighting Existing Overhang Lighting Proposed Restroom Lighting Proposed Overhang and Entry Lighting
11
Building Improvements – Wood Siding
12
Wood Types - Western Red Cedar, Redwood… Building Improvements – Wood Siding Looking for Local resources Longevity Character Constructability
13
Building Improvements – Wood Fascia & Decking
14
Building Improvements – Wood Railing Existing interpretive graphics are faded and do not comply with ADA requirements. Railings will be designed to accommodate new graphics system Existing railing openings do not comply with Code Existing steel railing sectionDeteriorated siding on railing support
15
Building Improvements – Wood Railing Wood rail and pickets Glass railing inserts to accommodate Children
16
Building Improvements – Structural Repairs
17
Swallow Nesting & Building Maintenance
18
Building Overhangs Swallow habitats Soffit boards
19
Swallow Nesting
20
Swallow Habitat Options Swallow habitat Opening cut in deck
21
Swallow Habitat Options
22
Swallow Habitat Option A 1 Example of artificial nesting box shelf, may vary to suit bird
23
Swallow Habitat Option B Example of artificial nesting box shelf, may vary to suit bird
24
Interpretive Center Schedule Project out to Public bid: Summer of 2016 Expected Construction duration: approximately 12 Months Schedules are subject to Environmental Permitting process
25
BAYLANDS BOARDWALK
26
Overview Structure and Constraints Structure Assessment Site Constraints Feasibility Study Repair Rehabilitation Replacement
27
Structure Assessment Closed to Public Serious Condition Superstructure Substructure
28
Site Constraints Environmental Conditions Subsurface Conditions Hydraulic Conditions Access and ADA Constraints
29
Repair Option Conduct Limited Repairs to Provide Limited Public Access Until Full Rehabilitation / Replacement Open: Nature Center to First Overlook Platform (approx. 200 ft.) Closed: Beyond First Overlook Key Advantages/Challenges: ADA Compliance: Match Existing Sea Level Rise: Not Addressed Design Life: Approx. 3-5 years Construction Costs: Low Cost Maintenance Costs: Similar to Exist Const. Duration: Approx. 1-2 months
30
Rehabilitation Option 1 Utilizes Temporary Support System to Support Exist Structure While Failed Substructure is Replaced Key Challenges: ADA Compliance: Difficult to Meet Current Standards Sea Level Rise: Difficult to Raise Exist Deck Level Design Life: Approx. 25-50 years Construction Costs: Similar to Full Replacement Costs Maintenance Costs: Similar to Exist Const. Duration: approx. 1-2 years
31
Rehabilitation Option 2 Constructs a New Support System Outboard of Existing Support System and Boardwalk Decking Key Challenges ADA Compliance: Difficult to Meet Current Standards Sea Level Rise: Less Difficult than Option 1 to Raise Exist Deck Level Design Life: Approx. 25-50 years Construction Costs: Similar to Full Replacement Costs Maintenance Costs: Similar to Exist Const. Duration: Approx. 1-2 years
32
Replacement Option 1 Replaces Existing Boardwalk with New Timber Boardwalk with Timber Plank Decking with Either Timber or Steel Supports Key Advantages ADA Compliance: Fully Compliant Sea Level Rise: Deck Elev. Raised Design Life: Approx. 50-75 years Construction Costs: Similar to Rehabilitation Costs Maintenance Costs: Less than Exist Const. Duration: Approx. 1-2 years
33
Replacement Option 2 Replaces Existing Boardwalk with New Timber Boardwalk with Timber Stringer and Decking with Either Timber or Steel Supports Key Advantages ADA Compliance: Fully Compliant Sea Level Rise: Deck Elev. Raised Design Life: Approx. 50-75 years Construction Costs: Similar to Rehabilitation Costs Maintenance Costs: Less than Exist and Slightly Less than Option 1 Const. Duration: Approx. 1-2 years
34
Feedback Comments on Proposed Improvements Comments on Proposed Bird Habitat Options Comments on Proposed Boardwalk Options Questions?