FRONT VIEW OF PETROLEUM HOUSE
4
1. PLOT SIZE.175 ft x 200ft (35000 Sft) (3888.88 Sq yard) (7.778 Kannals) 2. DATE OF START 07 - 11 - 2007 3. STIPULATED DATE OF COMPLETION. 06 - 11 – 2009 4. EXPECTED DATE OF COMPLETION. 31 – 12 – 2012, Subject to Availability of funds. 5. a) ADMINISTRATIVE APPROVAL (1 ST REVISION) b)- Do – (2 ND REVISION) Rs. 452.44 0 (Million) Vide No. MPNR’S U.O No. 9(10) Dev IV/2006 Dated 27 - 04 -2007 Rs 857.37 (Million) Vide No.6(145) P/A-II-PC-2007 Dated 11 JAN 2012 6. TENDERED AMOUNT CIVIL WORK (AS PER CONTRACT AGREEMENT EXCLUDING ADDITONAL ITIES) =372.953 MILLION INTERNAL ELECTRICATION WORKS =22.881 MILLION EXTERNAL ELECTRIFICATION WORKS =19.417 MILLION HVAC SYSTEM =133.885 MILLION FIRE ALARM & TELEPHONE EXCHANGE =10.242 MILLION LIFT WORKS =29.07 MILLION TUBE WELL =2.932 MILLION SUI GAS WORK =1.499 MILLION IESCO DEMAND NOTICE PAYMENT =7.077 MILIION TOTAL AMOUNT =599.956 MILLION 7. TOTAL COVERED AREA (ACTUAL) 163100 Sft 8. BRIEF SCOPE OF WORK The Building Consist of 2 Basement, Ground Plus 9 Floors including allied infrastructures like as Boundary Wall, Drive way, Underground Water Tank 45,000 Gallons, Overhead Tank. 10,000 Gallons and Electrical/ Mechanical Services. 9. CAR PARKING SPACE 29629 Sft (2 No's Basement to Accommodate 50 No’s. Vehicles)
5
NAME OF SCHEME CONSTRUCTION OF PETROLEUM HOUSE G-5/2 ISLAMABAD APPROVED COST AS PER ORIGINAL PC I = 255.522 (M) (2005) REVISED PC-I FIRST REVESION = 452.44068 (M) (2006) REVISED PC-I 2ND REVESION = 857.37 (M) (2012) (2012) COVERD AREA OF THE BUILDING =163100.00 SFT (2 BASEMENT,GROUND + NINE FLOOR) (2 BASEMENT,GROUND + NINE FLOOR) CONTINUED CONTINUED
6
Total Funding / Expenditure (Up to 30-06-2012) S NO YearAllocatio n (Million) Release (Million) START RELEASE OF FUNDS AS PER PC-1 Expenditure (Civil + E/M) (Million) Cumulative Expenditure (Civil +E/M) (Million) REMARKS 1 2006-2007 48.888 39.401.195 I) THE PROJECT BECAME TIME CASE OVER RUN, RESULTED INTO REVISION OF PROJECT COST FROM RS 452.44 M /RS 857.37 M II) REVISION OF 2 ND PC-1 IS DUE TO INCLUDIG ADDIONALITIES LIKE, ONE ADDITIONAL BASEMENT, CLADING, SAFETY GLASS, 1250 KVA TRANSFARMER INSTEAD OF 500 KVA. 2 2007-2008 SPECIAL ALLOCATION 46.187 45.00 45.614 45.00 ----------- 90.614 85.96297.578 --------- 98.773 ---------- 3 2008-2009 SPECIAL ALLOCATION 25.00 130.00 20.612 130.00 ----------- 150.162 36.964 ------------- 162.326 191.000289.773 4 2009-2010 SPECIAL ALLOCATION 87.374 33.00 86.371 33.00 ----------- 119.371 119.412409.185 5 2010-2011 - NIL- 409.185 6 2011-2012 Special Allo 43.34 200.00 43.00 200.00 ---------- 243.00 128.69 (11.00 Civil + 74.69 EM) 537.875 TOTAL 652.035537.875 * Over all up to date physical progress: 68%
7
DETAIL OF ON GOING CIVIL WORKS RCC COLUMNS / SLABS HAVE BEEN COMPLETED UPTO GROUND PLUS 9 th FLOOR. PARTITION WALLS AND PLASTER WORKS INTERNAL HAS BEEN COMPLETED UPTO GROUND PLUS 9 TH FLOOR. RCC SLAB OF MACHINE ROOM STAIR CASE HAS BEEN COMPLETED. ROOF TREATMENT HAS BEEN COMPLETED. EXTERNAL & INTERNAL WATER SUPPLY & SEWERAGE WORK IS IN PROGRESS. BOUNDARY WALL, WORK IS IN PROGRESS. INTERNAL & EXTERNAL SANITARY WORK IS IN PROGRESS. KITCHEN CABINET WORK IS IN PROGRESS. FALSE CEILING WORK IS IN PROGRESS. PROCELAIN TILE WORK IS IN PROGRESS. GLASS CURTAIN WALL IS IN PROGRESS. WALL CLADING WORK IS IN PROGRESS. ALUMINUM DOOR AND WINDOWS WORK IS IN PROGRESS.
8
DETAIL OF E & M WORKS (ONGOING) WIRING OF INTERNAL ELECTRIFICATION COMPLETED WHEREAS ALL THE ELECTRICAL FITTINGS AND FIXTURES, L.T PANNEL BOARDS, DISTRIBUTION BOARDS ARE BEING INSTALLED. SUB-STATION EQUIPMENT I/C H.T SWITCH (INCOMMING/OUTGOING) TRANSFORMERS, PFIs HAVE BEEN PROCURED & INSTALATION WILL BE STARTED SHORTLY. TELEPHONE WIRING HAS BEEN COMPLETED & SYSTEM WILL BE INSTALLED AT FINISHING STAGE OF THE BUILDING. FIRE ALARM WIRING HAS BEEN COMPLETED & SYSTEM WILL BE INSTALLED SIDE BY SIDE WITH CIVIL WORK.
9
DETAIL OF E & M WORKS(ONGOING) HVAC SYSTEM; DUCTING & PIPE WORK HAS ALMOST COMPLETED EQUIPMENT HAS BEEN PROCURED & WILL BE INSTALLED SIDE BY SIDE CIVIL WORK WHERE AS CHILLERS, AIR HANDLING UNITS & FAN COIL UNITS ARE YET TO BE ARRIVED AT SITE ON PRODUCTION OF BILL OF LADDING. LIFTS HAVE BEEN ARRIVED AT SITE & INSTALLATION WILL BE STARTED SHORTLY. TUBEWELL WORK I/C BORING & INSTALLATION OF PUMP IS ABOUT TO START SUI GAS PIPING WORK HAS ALMOST COMPLETED & SUI GAS APPLIANCES HAVE BEEN PROCURED.