Planned activities during (E)YETS… up to LS2 for PSB-PS equipment Etienne CARLIER On behalf of TE/ABT/EC
2
Prerequisite Analysis should be done for all the machines at the same time and not only for PS-PSB. Consolidation program up to LS2 still to be internally defined. Possible external requests impacting our activities still to be identified before deciding what will be internally done.
3
Boundary conditions BE-CO – LynxOS support – GM support – FESA2 support – PS-Complex positioning system support EN-EL – Cabling / de-cabling campaigns HSE – Safety
4
PSB “foreseen” Activities SystemContextWhenComment BI.STR, BI.KSW, BI.BSW, BI.DIS LIULS2Ready EYETS2016 BT.KFA10-20, BE.KFA14L1 ConsolidationLS2 Septa slow controlConsolidationEYETS2016 / YETS2017 Functional specification in 2015 Septa positioning control ConsolidationEYETS2016 / YETS2017 Functional specification in 2015 AllMaintenanceYETS & EYETSSoftware version follow-up, interlock checks, system re- calibration…
5
PS “foreseen” Activities SystemContextWhenComment PI.KFA45 / PI.KFA53LIU / ConsolidationLS2Configuration not yet defined PE.KFA71-79ConsolidationLS2 PE.KFA28ConsolidationEYETS2016Oil system Septa slow controlConsolidationEYETS2016 / YETS2017 Functional specification in 2015 Septa positioning control ConsolidationEYETS2016 / YETS2017 Functional specification in 2015 AllMaintenanceYETS & EYETSSoftware version follow-up, interlock checks, system re- calibration…
6
AD “foreseen” Activities SystemContextWhenComment Horn test benchConsolidationEYETS2016Restart HornConsolidationYETS2017Ignitron removal ELENAProject2015-2016Installation (on- going activity over the period) AllMaintenanceYETS & EYETSSoftware version follow-up, interlock checks, system re- calibration…