www.emwd.org 1 EASTERN MUNICIPAL WATER DISTRICT Cactus II Feeder Transmission Pipeline Joe Mouawad, PE Sr. Director of Engineering September 2, 2015
2
www.emwd.org 2 Background Pettit Pressure Zone (1764 PZ ) o City of Moreno Valley Corrects System Deficiencies o Transmission o Storage o Low Pressure Planned Development o Aqua Bella o World Logistics Planning o Cactus II Feeder Planning Study Alignment evaluation Pipe size o 1764 Storage Study Pettit Tank Site Expansion (6.2 MG) o Pipeline Construction Estimate: ≈ $50 Mil
3
www.emwd.org 3 Proposed Improvements 26,500 feet of 36-inch to 48-inch diameter transmission pipeline Up to 4 Pressure Reducing Stations
4
www.emwd.org 4 Engineering Services - Scope of Work Data Gathering, Analysis, and Planning Refinement o Hydraulic Evaluation (updated model) o Pipeline alignment and sizing verification Property/Easement Acquisition Support o PRV Stations o Construction Easements Preliminary Design o Pipeline Alignment Selection o Development of Design Criteria Final Design Investigations o Survey o Geotechnical (GDR/GBR) o Corrosion o Potholing CEQA Support/Permit Acquisition o City of Moreno Valley o RCFC&WCD/DDW Bidding Services Alessandro Blvd. & Kitching St. (Looking East)
5
www.emwd.org 5 Consultant Selection Process Issued Request for Proposals o April 27, 2015 Selection Panel o Engineering, Planning, & Operations Evaluation Criteria o Past Performance and qualification of the proposed team o Familiarity with project and capacity to handle all aspects of the work o Ability to commence work immediately and complete project within proposed time frame o Proposed approach, scope, manner, and thoroughness in which it is presented in the proposal o Firm’s experience, staff availability, stability, financial responsibility, and past performance on similar projects o Fee proposal
6
www.emwd.org 6 Consultant Selection Summary (2) FirmTechnical Proposal Ranking Base Proposal Fee Optional Tasks Fee Total FeesFinal Ranking Black & Veatch (1) 4.0$1,046,180$124,605$1,170,7851 IEC (1) 3.9$929,344$114,394$1,043,7382 Krieger & Stewart3.8$1,043,000$107,269$1,150,0003 Webb3.4$1,136,463$167,469$1,303,9324 GHD3.3$1,127,131$79,245$1,206,3765 AECOM3.2$1,635,628$109,526$1,745,1546 Tetra Tech3.1$789,938$132,685$922,6237 (1) Best and Final Fee Proposals. (2) Michael Baker International (formerly RBF) declined to participate. Kennedy Jenks partnered with Black & Veatch. HDR partnered with GHD.
7
www.emwd.org 7 Schedule Board Award – September 2, 2015 Kick-Off Meeting – October 2015 Preliminary Design – June 2016 Final Design – March 2017 Bid Phase – April 2017 Construction Duration-2 years Eastern Moreno Valley Development
8
www.emwd.org 8 Recommendation Approve and Authorize an Agreement with Black and Veatch Corporation, ($1,170,785) for Preliminary and Final Design of the Cactus II Feeder Transmission Pipeline, Administrative Award of Contracts, and Appropriation of Funds in the Amount of $1,783,400 Proposed Commencement Point – Heacock St/Cactus Ave. with Heacock/Pettit Booster Station (Left) and DWR crossing (Right)
9
www.emwd.org 9 Contact Information EASTERN MUNICIPAL WATER DISTRICT www.emwd.org Joe Mouawad, P.E. Sr. Director of Engineering 951-928-3777 Ext 4463 mouawadj@emwd.org