CHAPTER-14 MRP AND ERP MD. TAZIDUL ISLAM. 2  Material Requirement Planning (MRP) is the concept of designing and developing information system to aid.

Similar presentations


Presentation on theme: "CHAPTER-14 MRP AND ERP MD. TAZIDUL ISLAM. 2  Material Requirement Planning (MRP) is the concept of designing and developing information system to aid."— Presentation transcript:

1 CHAPTER-14 MRP AND ERP MD. TAZIDUL ISLAM

2 2  Material Requirement Planning (MRP) is the concept of designing and developing information system to aid in managing resource requirement specially dependant demand inventory and scheduling replenishment orders.

3 3-Inputs to MRP 3 Inventory Transaction Inventory Records MRP Explosion Bills of Materials Engineering and Process designs Master Production Schedule Other Sources of Demand Material Requirement plan

4 MRP Explosion 4  A process that converts the requirements of various final products into a material requirements plan that specifies the replenishment schedules of all the subassemblies, components and raw material needed by the final products.

5 Concept of Bill of Material (BOM) 5  A BOM is a record of all the components of an item, the parent-component relationships and the usage quantities derived from engineering and process design.

6

7 Example: BOM 7 A Ladder-back chair B (1) Ladder-back subassembly F (2) Back Legs G (4) Back Stats C (1) Seat Subassembly H (1) Seat Frame I (1) Seat Cushion J (4) Seat frame board D (2) Front Legs E (4) Legs Support

8 Inventory Record 8  IR consists of:  Gross Requirements  Schedule Receipts  Projected on-hand Inventory  Planned Receipts  Planned Order release

9 Example: Inventory Record 9 Weeks12345678 Gross Requirements 1500012001501200 Schedule Receipts 230 Projected on- hand Inventory 117 Planned Receipts Planned Order release 37 Item: CLot Size: 230 Units Description: Seat SubassemblyLead time: 2 Weeks 117 -3 -153-273

10 Example: Inventory Record 10 12345678 Gross Requirements 1500012001501200 Schedule Receipts 230 Projected on- hand Inventory 117 227 77187 Planned Receipts 230 Planned Order release 230

11 Planning Factors 11  Lead time  Lot-sizing  Safety Stock

12 Lot Sizing Rules 12  Fixed Order Quantity (FOQ)  Periodic Order Quantity (POQ)  Lot for Lot (L4L)

13 Periodic Order Quantity (POQ) 13 POQ lot size to arrive in week t=(Total gross requirements for P weeks, including week t)- (Projected on hand Inventory balance at the end of week t-1)

14 Example: Periodic Order Quantity (POQ) 14 Weeks12345678 Gross Requirements 1500012001501200 Schedule Receipts 230 Projected on- hand Inventory 117 150 000 Planned Receipts 153120 Planned Order release 153120 Item: C Description: Seat SubassemblyLead time: 2 Weeks

15 L4L 15 L4L lot size to arrive in week t=(Gross requirements for week t)-(Projected on-hand inventory balance at the end of week t-1)

16 Example: L4L 16 Weeks12345678 Gross Requirements 1500012001501200 Schedule Receipts 230 Projected on- hand Inventory 117 00000 Planned Receipts 3150120 Planned Order release 3150120 Item: C Description: Seat SubassemblyLead time: 2 Weeks

17 Comparison of Lot-Sizing Rules 17  Average on hand Inventory (from W4-W8)  FOQ=181units  POQ=60 units  L4L=0 units  FOQ: Average on-hand inventory in very high, Sometimes ensure supply chain surplus, depending on machine capacity, discount etc.  POQ: Comparatively lower stock in hand.  L4L: Replenish orders more frequently therefore reduce the inventory cost but increases ordering and setup cost. Suitable for Make to Order and low volume items.

18 Classroom Exercise 18 The MPS for product A calls for the assembly dept. to begin final assembly according to the following schedule: 100u in W2; 200u in W4; 120u in W6; 180 in W7 and 60 in W8. Develop a Material Requirement Plan (MRP) for the next 8 weeks for item B following these information: No. of components require: 1 unit Lot-sizing rule: FOQ (LS=100) Lead time: 1 W Schedule Receipt: 30 Beginning (on-hand) inventory: 20

19 Solution 19 Weeks12345678 Gross Requirements 01000200012018060 Schedule Receipts 00000000 Projected on- hand Inventory 20200 00240600 Planned Receipts 280360 Planned Order release 280360 Item: BPOQ Lead time: 1 Week

20 20 The product structure tree for an end item E follows. The manager wants to now the material requirements for ordered part R that will be needed t complete 120 units of E by the start of week 5. Lead times for items are one week for level 0 items, one week for level 1 items a two weeks for level 2 items. There is a schedule receipt of 60 units of M at the start of weeks 2 and 100 units of R at the start of week 1. Lot for lot ordering is used. Classroom Exercise

21 21 End item P is composed of three subassemblies: K, L and W. K is assembled using 3 Gs and 4Hs; L is made of 2 Ms and 2 Ns; and W is made of 3 Zs. On-hand inventories are 20 Ls, 40 Gs, and 200 Hs. Scheduled receipts are 10 Ks at the start of week 3, 30 Ks at the start of week 6, and 200 Ws at the start of week 3. One hundred Ps will be shipped at the start of week 6 and another 100 at the start of week 7. Lead times are two weeks for subassemblies and one week for components G, H and M. Final assembly of P requires one week. Include an extra 10 percent of scrap allowance in each planned order of G. The minimum order size for H is 200 units. Develop each of the following: A. A product structure tree. B. An assembly time chart C. MPS D. MRP a.

22 Determining Components Requirement 22 C (1) Seat Subassembly H (1) Seat Frame I (1) Seat Cushion J (4) Seat frame board FOQ (300 units) LT: 1 Week L4L LT: 1 Week FOQ (1500 units) LT: 1 Week

23 23 Weeks12345678 Gross Requirements 1500012001501200 Schedule Receipts 230 Projected on-hand Inventory 117 227 77187 Planned Receipts 230 Planned Order release 230 Item: CFOQ Description: Seat SubassemblyLead time: 2 Weeks Weeks12345678 Gross Requirements023000 000 Schedule Receipts00000000 Projected on-hand Inventory070 140 Planned Receipts300 Planned Order release300 Item: HFOQ Description: Seat Frame (Lot size: 300)Lead time: 1 Week

24 24 Weeks12345678 Gross Requirements 1500012001501200 Schedule Receipts 230 Projected on-hand Inventory 117 227 77187 Planned Receipts 230 Planned Order release 230 Item: CFOQ Description: Seat SubassemblyLead time: 2 Weeks Weeks12345678 Gross Requirements023000 000 Schedule Receipts00000000 Projected on-hand Inventory00000000 Planned Receipts230300 Planned Order release230300 Item: IL4L Description: Seat CushionLead time: 1 Week

25 25 Weeks12345678 Gross Requirements120000 0000 Schedule Receipts00000000 Projected on-hand Inventory0300 00000 Planned Receipts1200 00 9000000 Planned Order release900 Item: JFOQ Description: Seat frame boards (Lot size: 1500)Lead time: 1 Week Weeks12345678 Gross Requirements023000 000 Schedule Receipts00000000 Projected on-hand Inventory070 140 Planned Receipts300 Planned Order release300 Item: HFOQ Description: Seat FrameLead time: 1 Week

26 Classroom exercise 26 M1M2M3M4M5M6M7M8M9M10 5005506105205505105006505200 M1M2M3M4M5M6M7M8M9M10 250220210050600500520550 M1M2M3M4M5M6M7M8M9M10 25151012221025 12

27 27 Further Information: Lot size: 500 P=3 LT=2 Weeks Schedule Receipt=200 U On-hand inventory=100 U Classroom exercise

28 Service Resource Planning 28  Hospital  Call Center  Bank  University  Hotel  Airline  Restaurant Bill of Resources (BOR)

29 Difference between manufacturing and service resource planning 29  Demand for service can be difficult to predict  Capacity availability can be difficult to predict  Labor flexibility can be an advantage in services  Service occur when they are rendered

30 30


Download ppt "CHAPTER-14 MRP AND ERP MD. TAZIDUL ISLAM. 2  Material Requirement Planning (MRP) is the concept of designing and developing information system to aid."