PRE-BID MEETING CONSTRUCTION OF MEDUPI BORUTHO 400kV TRANSMISSION LINES PRE-BID MEETING PROJECT MANAGEMENT Presented by: Theo Meveni 13 January 2015.

Similar presentations


Presentation on theme: "PRE-BID MEETING CONSTRUCTION OF MEDUPI BORUTHO 400kV TRANSMISSION LINES PRE-BID MEETING PROJECT MANAGEMENT Presented by: Theo Meveni 13 January 2015."— Presentation transcript:

1 PRE-BID MEETING CONSTRUCTION OF MEDUPI BORUTHO 400kV TRANSMISSION LINES PRE-BID MEETING PROJECT MANAGEMENT Presented by: Theo Meveni 13 January 2015

2 2015/01/132 Scope of Work Executive Summary Medupi Borutho 400kV Line, Section A  Construction of 84 kms kilometers of Medupi Borutho 400kV Transmission Power Line in the Lephalale area of Limpopo Province.  Construction of 2 underpasses first one outside Medupi Power station and the second one 25 km away from Medupi P/S. Medupi Borutho 400kV Line, Section B  Construction of 90kms kilometers of Medupi Borutho 400kV Transmission Power Line in the Mokopane area of Limpopo Province.

3 Project Scope of Works  The construction need to be done in accordance with Eskom design and specifications.  Medupi-Borutho 400kV Line Final Design Report- U.TX201.031-06-002 Rev1  Medupi-Borutho 400kV Transmission Line Specification- U.TX201.031-07- 001 Rev1  Medupi-Borutho 400kV Line Templating Report- U.TX201.031-05-04-001 Rev0 3 2015/01/13

4 Scope of Work Cont…………. 4  The Scope of Work Includes:  Access roads and infrastructure  Bush clearing  Tower foundations and stay wire foundations  Fabrication and erection of structural steel transmission towers  Installation of hardware, conductor and insulators  Tower assembly, stringing and labelling  Conductor Regulation  The lines run through a predominantly game farming, agricultural land and a villages. 2015/01/13

5 Scheduling Requirements NO REQUIREMENT 1 A3 Hard copy 2Electronic copy (not PDF) must be available 318 Months Duration, assume effective start date (Both Section A and B) 4Durations of the activities 5Critical path 6Resource usage 7 Key milestone dates e.g foundation completion date, tower assemble, erection 8Calendar days including holidays 9Risk Allowance e.g rainfall 52015/01/13