Download presentation
Presentation is loading. Please wait.
Published byAbel Jasper Morton Modified over 8 years ago
1
City Council Presentation Progress Report No. 12 For September 2006 November 6, 2006
2
pet1106i1-7310.ppt/2 Overview of Construction Status Work progressWork progress ScheduleSchedule Project administrationProject administration Submittal status Field/change orders CostsCosts Anticipated workAnticipated work
3
pet1106i1-7310.ppt/3 Ellis Creek North Crossing 42” secondary effluent42” secondary effluent 16” 42” headworks16” 42” headworks 20” recycled water20” recycled water Road for project construction trafficRoad for project construction traffic
4
pet1106i1-7310.ppt/4 Site Grading West access roadWest access road Aggregate base Polishing treatment wetlandsPolishing treatment wetlands Construction roadsConstruction roads
5
Headworks Facility Slab on grade grit areaSlab on grade grit area First wallsFirst walls
6
Oxidation Ditches Oxidation Ditch No. 1Oxidation Ditch No. 1 36 of 65 walls Oxidation Ditch No. 2Oxidation Ditch No. 2 21 of 57 walls
7
pet1106i1-7310.ppt/7 Secondary Clarifiers 10 of 12 walls No. 110 of 12 walls No. 1 7 of 12 walls No. 27 of 12 walls No. 2
8
Filter Support Building Slab on grade pouredSlab on grade poured
9
pet1106i1-7310.ppt/9 UV Disinfection Facility 65% of walls completed65% of walls completed
10
pet1106i1-7310.ppt/10 Thickener Building Slab on grade lower sumpSlab on grade lower sump Walls sump areaWalls sump area
11
pet1106i1-7310.ppt/11 O&M Building Maintenance wallsMaintenance walls Block walls continuedBlock walls continued
12
pet1106i1-7310.ppt/12 Yard Piping 23,272 completed of 91,000 lf23,272 completed of 91,000 lf Access roadAccess road 12” water 4” natural gas
13
pet1106i1-7310.ppt/13 Yard Piping (cont.) 20” Urban recycled water20” Urban recycled water 12” 3W12” 3W
14
pet1106i1-7310.ppt/14 Yard Piping (cont.) 42” polishing wetland effluent42” polishing wetland effluent 26” effluent pipe at pond 9 and pond 1026” effluent pipe at pond 9 and pond 10
15
pet1106i1-7310.ppt/15 Electrical Duct Banks West of ox ditch 2West of ox ditch 2 South of headworks to south Creek crossingSouth of headworks to south Creek crossing 8,189 of 46,000 lf8,189 of 46,000 lf
16
pet1106i1-7310.ppt/16 Existing Pond Facility Modifications Wetland pump stationWetland pump station Slab on grade poured Walls started Pond 8 to Pond 9 LeveePond 8 to Pond 9 Levee Finished pile installation Pond 8 returned to operations Aerated lagoonAerated lagoon Inlet structure formed and poured Pond 1Pond 1 7 horizontal brush aerators installed
17
pet1106i1-7310.ppt/17 Schedule Notice to Proceed – October 10, 2005Notice to Proceed – October 10, 2005 Base contract duration 1,278 daysBase contract duration 1,278 days Original completion date – April 9, 2009Original completion date – April 9, 2009 Time extension authorized – 46Time extension authorized – 46 Revised duration – 1,324Revised duration – 1,324 Revised completion date – May 25, 2009Revised completion date – May 25, 2009 Weather days included in base duration – 40Weather days included in base duration – 40 Weather days expended – 78Weather days expended – 78 Time expended – 355 daysTime expended – 355 days Percent time expended – 28%Percent time expended – 28% Work remains on scheduleWork remains on schedule
18
pet1106i1-7310.ppt/18 Costs Base Contract Amount $110,329,000Base Contract Amount $110,329,000 Change Orders Authorized $750,576Change Orders Authorized $750,576 Total Contract Cost $111,079,576Total Contract Cost $111,079,576 Percent Change to Date of Original Contract0.68%Percent Change to Date of Original Contract0.68%
19
pet1106i1-7310.ppt/19 Project Administration - Programming SCADA screensSCADA screens Speed control Analog set point Lead/Lad, Duty/ Standby Configuration of PLC 1,3,5,6,7,8,9Configuration of PLC 1,3,5,6,7,8,9 PLC2 75%PLC2 75% WAS/RAS pumping Aerator call order
20
pet1106i1-7310.ppt/20 State Revolving Loan Fund Update Requested $5,173,877Requested $5,173,877 SRF will save over $60 million in interest versus revenue bondsSRF will save over $60 million in interest versus revenue bonds
21
pet1106i1-7310.ppt/21 Project Administration SubmittalsSubmittals Received 510 Reviewed and returned 445 Pending 64 Field ordersField orders 25 active Total estimated cost $169,800
22
pet1106i1-7310.ppt/22 Change Order Summary Authorized $750,576Authorized $750,576 This month $292,655This month $292,655 HighlightsHighlights Levee repair Pond 8 to Pond 9 ($289,279) Anticipated next monthAnticipated next month Lower invert elevation influent line ($17,290) West access culvert ($20,000) PG&E connection West Access Road ($20,000) Oxidation Ditch Anchorage ($39,942) O&M Bldg beam seats wall pockets ($20,000) Two deductive changes (-$120,000) -Corrugated HPDE pipe for storm drains -Large Diameter HPDE thickness change
23
pet1106i1-7310.ppt/23 Project Management Team $4,701,586 $187,130 $31,377 $34,505 $85,676 $4,362,898 September $40,494,241 Total $1,887,439 Construction Manager Covello $676,257ProgrammerArcSine $477,853EnvironmentalESA $1,674,122EngineerCarollo $35,778,570Contractor Kiewit Total Earned RoleTitle
24
pet1106i1-7310.ppt/24 Anticipated Work for October Creek crossingsCreek crossings Removed and restored West access roadWest access road Paving, curbs, sidewalks HeadworksHeadworks Walls Oxidation ditches/secondary clarifiersOxidation ditches/secondary clarifiers Walls O&M buildingO&M building Masonry block walls Thickener buildingThickener building Sump walls
25
pet1106i1-7310.ppt/25 Anticipated Work for October (cont.) Main electrical buildingMain electrical building Excavated Electrical building (MCC9)Electrical building (MCC9) Excavated Duct bank UV buildingUV building Channel walls Floor Existing pond siteExisting pond site Pond 9 and 10 planting Pond 9 pump station walls Electrical work at aerated lagoon pond 1
26
pet1106i1-7310.ppt/26 Anticipated Work for October (cont.) Boiler buildingBoiler building Excavation Storm water pump stationStorm water pump station Tie in lines from oxidation ditch area Yard pipingYard piping 27” storm water pipe north of pump station Bridge over storm water pipes Culvert at main entrance Pond 9 and Pond 10 Levee 42” and 26” Pond 9 and Pond 10 double contained pipe Connections to thickener building Connections at filter support building In-plant pump station to headworks
27
pet1106i1-7310.ppt/27 Questions?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.