PEAK CAPACITY COST & DEMAND RESPONSE PACIFIC NORTHWEST DEMAND RESPONSE PLANNING COMMITTEE BILL DICKENS TACOMA POWER FEBRUARY 23, 2012.

Similar presentations


Presentation on theme: "PEAK CAPACITY COST & DEMAND RESPONSE PACIFIC NORTHWEST DEMAND RESPONSE PLANNING COMMITTEE BILL DICKENS TACOMA POWER FEBRUARY 23, 2012."— Presentation transcript:

1 PEAK CAPACITY COST & DEMAND RESPONSE PACIFIC NORTHWEST DEMAND RESPONSE PLANNING COMMITTEE BILL DICKENS TACOMA POWER FEBRUARY 23, 2012

2 DEMAND RESPONSE: OVERVIEW 2

3 3 Cost $.MWh Capacity Load With DR Load Power Supply With DR No DR ----------------------------------------------------- Cost With DR ------------------------------------------------------------------------------------ Cost No DR ECONOMICS of DEMAND RESPONSE Peak Demand Reduction Cost Reduction

4 TACOMA’S CAPACITY MARGIN: WINTER 1-HOUR 4

5 5 PeriodPeak LoadPeak SupplyPeak Load Planning Reserve Margin 1-hour1003 MW1266 MW26% 18-hour948 MW1266 MW36% 72-hour833 MW1178 MW41% PEAK LOAD-RESOURCE BALANCE SUMMARY

6 6 MID-C DOW JONES POWER PRICE INDEX

7 7 WHOLE-SALE POWER PRICE FORECAST

8 CONCLUSION STARS DO NOT ALIGN NO THERMAL RESOURCES NO CAPACITY CONSTRAINTS NO FLEXIBLE RATES NO RTO/ISO OPPORTUNITIES – WIND INTEGRATION QED 8


Download ppt "PEAK CAPACITY COST & DEMAND RESPONSE PACIFIC NORTHWEST DEMAND RESPONSE PLANNING COMMITTEE BILL DICKENS TACOMA POWER FEBRUARY 23, 2012."