1
1 PFP QSR, 11/17/2010 Particles and Fields Package Monthly Status Review (MSR) November 17, 2010 Dave Curtis, PFP PM
2
2 PFP QSR, 11/17/2010 SSL Contracting Status Phase B/C/D Contract in place. An updated spending plan (phasing) has been completed
3
3 PFP QSR, 11/17/2010 Schedule Status No improvement in pre-CDR schedule –A few layouts lagging –SWIA/STATIC mechanical still behind but making slow progress –Due to personnel conflicts with RBSP RBSP FM2 completes environments this week! See next chart Result is the EM system testing completes right about the time of the ICDR. EM Test completion current showing June 3, after Instrument CDR. –Can reorganize test schedule to prioritize retiring risk early (Before ICDR) Package I&T before SWIA/STATIC Calibrations
4
4 PFP QSR, 11/17/2010 Manpower Concern with competition with RBSP-EFW for some key people –Power converter design team Reorganized team to streamline priority tasks Significant progress this month – most converter layouts complete –SWIA/STATIC/LPW boom mechanical engineers SWIA/STATIC EM mechanical parts behind Now of critical path to EM I&T Looking at hiring outside help to accelerate parts drawings –FSW lead keeping ahead of MAVEN schedule –Additional parts engineer to be added to QA team New hire: Interviewing.
5
5 PFP QSR, 11/17/2010 Accomplishments Almost all EM EEE parts at SSL –3 part types late – looking at work-arounds –First preliminary parts SEL test preliminary results look good PWBs are in layout –>50% layouts complete, some boards being loaded (see below) Most EM Mechanical parts are in fab –Some part-level design work still in progress on SWIA/STATIC PFP FSW Boot code 93% coded –All except Safe Mode/Zone Alert system –operational code started Heater sizing analysis complete –Will need to submit a CCR to cover operational heater power for SEP, SWEA, SWIA, STATIC More in instrument sections…
6
6 PFP QSR, 11/17/2010 Ongoing Work Supporting Project planning process Supporting EMC, Payload, SDT working groups Completing EM layouts, board loading Start EM board testing Completing EM mechanical part drawings, getting parts fabricated Preparing for STATIC TOF system acoustic test next month
7
7 PFP QSR, 11/17/2010 EM Status Summary SSL EM & GSE Layouts (23) –13 layouts complete (11 boards fabricated, 2 boards loaded) –9 layouts in progress (2 to be completed this week) –1 awaiting final schematic release LM Interface Test preparations (3/25/2011): –DCB PWB in assembly –GSE & FSW ready to start testing –Current schedule shows ready by 1/20/2011 for the LM test 1/26/2011 with power converter EM EEE Parts –Almost all EM Actives at SSL (3 problem parts) –Connectors on order –Passives being ordered EM detectors on order (MCP, SSD, foils, magnets) –SWIA MCP, STATIC foils, SEP magnets delivered EM Mechanical parts: –SWEA, SEP, LPW Boom (not sensor), STATIC TOF in fab –Remaining SWIA, STATIC parts into fab soon
8
8 PFP QSR, 11/17/2010 PFP RFA Status
9
9 PFP QSR, 11/17/2010 Trades, Issues LPW ‘hingeless whip’ pending ECR/CCR approval Solar array modifications pending ECR/CCR approval –MAG Team and EMEWG will continue to watch magentics SWEA Surface Treatment selected – Black Nickel –Passed testing –CESR looking for European vendor –Also looking at how to use US vendor Launch Loads issue closed –Atlas 5 selection lowers levels –Heritage design qualification no longer exceeded HV801 issue still open –Two options: Amptek HV801, Micropac 66353 –Have parts for EM
10
10 PFP QSR, 11/17/2010 Top Risks P10 (Operational Heaters) Retired; need heater power P16 (Launch Loads) Retired (Atlas 5 loads acceptable)
11
11 PFP QSR, 11/17/2010 Risks List
12
12 PFP QSR, 11/17/2010 PFP Mass No NTE mass added for SWEA shielding (CCR228 rejected) LPW mass CBE decrease ~330g –eliminate caging mechanism (CCR 237 pending) Harness mass CBE decreased due to PFDPU relocation At what point should I reallocate NTE amongst boxes?
13
13 PFP QSR, 11/17/2010 Mass Tracking Chart
14
14 PFP QSR, 11/17/2010 PFP Power Added Operational heaters for SWEA, SWIA, STATIC, SEP –Will need to submit a CCR to increase NTE by ~15W orbit average to get back to 15% margin [CCR 243 submitted] –Survival & Peak power also increase –LM looking at impacts
15
15 PFP QSR, 11/17/2010 PFP Power Trend
16
16 PFP QSR, 11/17/2010 PFP Data Rate Per 2009-6-9 allocations from Bruce
17
17 PFP QSR, 11/17/2010 Requirements Verification Status Nothing new to report.
18
18 PFP QSR, 11/17/2010 MAVEN PFP SWIA Status November 2010 Jasper Halekas, SWIA Lead
19
19 PFP QSR, 11/17/2010 SWIA Progress Layout Progress –Anode PWB complete, loading/testing in progress –Preamp/MCP board layout in progress, now top priority –Digital board layout complete, out for PWB fab soon –LVPS PWB complete, waiting for loading/testing –SWP prototype still in testing for stability issues Mechanical Design Progress –Most mechanical design now done for boards HV connectors making progress, waiting for ME time –Anode/MCP housing and clamp stack design complete Mechanical drawings reviewed, going out for fab –Attenuator design next to receive major effort, waiting for ME time –Analyzer detailed design progressing, waiting for ME time Microchannel plates arrived, waiting for MCP chamber refurbishment and mechanical parts for testing A121 preamps arrived, test board procured from AMPTEK, testing in next few weeks
20
20 PFP QSR, 11/17/2010 SWIA Issues Staffing –ME staffing hopefully easing soon Dalton and Johnson time should free up by end of November –Layout queue set schedule back Calibration Facilities –New chamber and ion gun may not arrive in time for initial testing Ion gun ordered this week – long lead time –Currently refurbishing MCP chamber for MCP testing –Plan to put old calibration chamber and ion gun back together as stopgap until new chamber and ion gun arrive
21
21 PFP QSR, 11/17/2010 MAVEN PFP SWEA Status November 2010 Dave Mitchell, SWEA Lead
22
22 PFP QSR, 11/17/2010 SWEA Status - CESR Mechanical –EM sensor assembled, initial functional tests show good performance –Starting fab of FM electronics housing –Fab of FM sensor pending completion & review of EM functional tests Front-end Electronics (MCP, HVPS) –Transformers fab & test – expect to be complete by Nov. 19. –Planetary Protection/AIV procedures in place – clean room testing underway EM sensor in vacuum chamber
23
23 PFP QSR, 11/17/2010 SWEA Status - SSL Pedestal Mechanical –Fabrication in progress. Expect delivery mid-November. –Solar absorber will not be used. Absorber would radiate in shadow and drive the temperature too low. Instead, SWEA will use heater power to maintain temperature [pending final thermal analysis]. LVPC –Layout complete. Digital –Layout complete, board is routed, currently under review at SSL. –Expect to make gerbers and send fab out for quote week of Nov. 15.
24
24 PFP QSR, 11/17/2010 Surface Coating for Deflectors, Grids, and External Surfaces –Black nickel (electroless) has been selected Good thermal properties (a ~ 0.83, e ~ 0.5) Electrically conducting Non-magnetic: < 10 nT @ 10 cm (< 0.01 nT @ 1 meter) after exposure to ~1000-G field Durable and easy to handle Not significantly altered by exposure to atomic oxygen (> 4 yrs equivalent in Mars environment with MAVEN orbit, including deep dips) Mechanical Design of Aperture –Existing SWEA design meets the load requirements. FM fabrication can proceed Two Key SWEA Issues Are Resolved
25
25 PFP QSR, 11/17/2010 MAVEN PFP STATIC Status October 2010 Jim McFadden, STATIC Lead
26
26 PFP QSR, 11/17/2010 STATIC Accomplishments EM Anode fabricated Preamp and TDC board signal routing complete (Hatch), External-to-internal custom HV connectors (for deflectors) were designed allowing sweep board layout modifications to proceed. Sweep HV board mods identified (Tiu) that stabilize the sweep. LVPS EM boards were fabricated and are in house. Finished the mounting design between analyzer and anode including updated nitrogen purge connection. New carbon foils received and initial test shows they do not have the breakage problems seen in previous batch –Manufacturer admits they missed a step in the first batch Carbon foil carriers with grids inspected and documented. Equipment ordered for streamlining carbon foil attachment MCP gain test equipment (preamps, MCA) ordered Ion gun quote received
27
27 PFP QSR, 11/17/2010 STATIC Open Issues Preamp and TDC boards schematic verification and fab preparation in process (Dalen). HV Sweep layout needs mods to accommodate external-to- internal HV connectors, and part changes to stabilize the sweep. LVPS needs BOM and needs to be kitted, built and tested (Berg). 15kV HV board needs to be kitted -- waiting on some parts from VMI and a custom HV connectors from the MEs. Digital board in layout. Parts drawings required for acoustics test in process (Johnson). STATIC FPGA still in development Still not getting much ME time on STATIC due to RBSP -- analyzer and mechanical attenuator still in development New vacuum calibration chamber not be ready for MCP testing so an older chamber will be readied and another chamber refurbished.
28
28 PFP QSR, 11/17/2010 MAVEN PFP SEP Status November, 2010 Davin Larson, SEP Lead
29
29 PFP QSR, 11/17/2010 SEP Accomplishments DFE boards received from manufacturer DAP board currently in layout (still) –Competing with STATIC for engineer time FPGA being designed by Jianxen Chen –Expect mid Dec completion Mechanical parts production delayed at external shop –Shop is behind schedule – partly do to Nustar –First of the parts have arrived Magnet selections made. –Awaiting magnet cage to assemble.
30
30 PFP QSR, 11/17/2010 SEP Open issues Neglected “flex circuit” board design in schedule. –Doing a ‘rush’ job on it. –Layout completed. Fab Doc completed. Going to quote today. Expect 1 week turn around DAP / FPGA pinout still subject to change. Designer input has been provided. SEP cable pinout changes can be expected pending DAP layout.
31
31 PFP QSR, 11/17/2010 MAVEN PFP DCB, Power Converter & GSE Status November 2010 Dorothy Gordon Tim Quinn Peter Berg
32
32 PFP QSR, 11/17/2010 DCB Status Data Controller Board Fabrication Complete FLASH Daughter Board Fabrication Complete Parts Kitted and Delivered to Digicom Population in process Expected delivery date: 23 November 2010
33
33 PFP QSR, 11/17/2010 GSE Hardware/Firmware Status MISG FPGA Development –The MISG PFDPU mode is currently undergoing test and integration –STATIC Prototype (receives commands and emits messages) is being used to assist with GSEOS development MISG Production Status –Digicom is loading an additional 5 MISG boards Expected delivery: 15 November 2010 –First prototype chassis has been assembled
34
34 PFP QSR, 11/17/2010 GSE Software Status (1) MISG Development and Integration oDelivered GSEOS for MISG development and supported checkout and integration oMISG Time and Status message decoder refined oTelemetry and command displays refined oCreated procedure to jam MISG time to local time oGSEOS-MISG-STATIC prototype testing ongoing PFDPU oGSEOS delivered to FSW engineer for basic testing of PFDPU CTM processing
35
35 PFP QSR, 11/17/2010 GSE Software Status (2) GSEOS operating MISG in PFDPU MODE
36
36 PFP QSR, 11/17/2010 GSE Software Status (3) LPW oSet up basic test network oCreated first version of telemetry and command spreadsheet oCreated first version of init script for configuring LPW at startup and after reset oCreated first version of LPW telemetry decoder - processes MISG instrument message block, splitting out packets.
37
37 PFP QSR, 11/17/2010 Power Converter Status (1) Low Voltage Supplies –STATIC, SWEA, SWIA LVPS boards in house –Electrical BOMs in process STATIC High Voltage Supplies –STATIC ACC+MCP boards are in house –Electrical BOM has been completed REG Board –Working with a layout contractor PADSPCB part definitions Parts placement
38
38 PFP QSR, 11/17/2010 Power Converter Status (2) MCP Multiplier –VMI is working on the MCP multiplier on the ACC+MCP board. –The VMI design in in process, but delivery date is a risk –We are considering making our own multiplier for the ETU IIB Schematics –IIB schematics are nearing completion; recent changes in the interfaces are being incorporated. Sweep Supply Stabilization –Testing and modification of the sweep supplies is ongoing. The supplies have been exercised with the STATIC prototype board in order to evaluate the AC Response. Work continues (about half of the supplies still need refinement and further testing).
39
39 PFP QSR, 11/17/2010 MAVEN PFP Flight Software Status November 2 2010 Peter Harvey
40
40 PFP QSR, 11/17/2010 Technical Status Technical Developments (Boot) Discussions with Project about IV&V interaction, database, deliveries Respond to IV&V comments on L4 and L5 requirements Added 4 L5 requirements (re. Communication loss of safe status) Revised 8 L5 requirements (re. L4 more specific than L5) Coming Up “Safe” in Boot mode is proving more involved than it sounds Technical Developments (Operational) Oct 11 th discussion with LASP on DFB interface DFB specification review/update (Oct 27) Added Message #15 for LPW EUV aperture status If LPW/EUV off, no way to know aperture status. Direct 2-line hardware solution under discussion (Requirement TBD) Drafted APID 50 for LPW to study PF_SYS_004 review F1/F2/F3 requirement “in any order” conflicts with DFB spec “must be in order” LPW will autoincrement UTC if there is no message FSW will send F1/F2/F3 iff CDI buffer is not full Command/Telemetry organization Instrument GSE’s each have CTM’s Met with Tim to work out how PFDPU stays in sync with Inst-GSE’s CTM’s Modifications to Inst-GSE names, codes, etc., will be read by PFDPU CTM Scripts written for Inst-GSE will run on PF in the same way FSW Include file generation (*.h files) by CTM keeps FSW in sync too Other IT security training 10/30/10
41
41 PFP QSR, 11/17/2010 Metrics Track Progress Points=Telecons with GSFC. 1 pt for each telecon, 0 if the telecon did not happen. Management Effort. Expected 10% or less, but has required phase A requirements and plans to be written in phase B.
42
42 PFP QSR, 11/17/2010 Margin Track
43
43 PFP QSR, 11/17/2010 Schedule Milestones 8/27: Boot FSW Development Awaiting Fault Protection details 9/28: FSW Sim Requirements Development DWC sent email requesting clarification of input 1/07: Operational FSW Development Reviewing Instrument Specs for FSW control information
44
44 PFP QSR, 11/17/2010 1-Page Fever Chart 1.Boot Requirements changes in the works 2.Boot Specification (Fault protection) changes in the works 3.Boot Development halted 4.DCB ETU board unavailable for test of Boot FSW.