Long-Baseline Neutrino Facility LBNF Far Site CF Scope Joshua Willhite Logistics Workshops August 11-13, 2015
2
LBNF Surface Scope 08.12.15Joshua Willhite | FSCF Scope2
3
LBNF Surface Scope 08.12.15Joshua Willhite | FSCF Scope3 Ross Dry & Control Room Cryogenic Compressor Building Power Feed
4
LBNF Power Supply Route 08.12.15Joshua Willhite | FSCF Scope4
5
LBNF Cryogenic Compressor Building 08.12.15Joshua Willhite | FSCF Scope5 Possibly used as temporary warehouse until needed at end of CF construction?
6
LBNF Cryogenic Compressor Building Elevations 08.12.15Joshua Willhite | FSCF Scope6
7
LBNF Ross Dry 08.12.15Joshua Willhite | FSCF Scope7 Used for CM, then science? Shared? Do Ops stay here? Is the control room shared or just DUNE? Dry must be shared with Ops.
8
LBNF Shaft Scope Utilities in the shaft include: Power Fiberoptics for data separate from fire alarm Cellular leaky feeder Nitrogen (three 12”, two 8”) and argon (one 8”) gas pipes Concrete slick line for construction in 6 winze Fire water pipe from 4100L to 4850L Existing 4” water line will feed a sump at the 4100L and continue past to service other water needs. 6” fire line from 4100L sump to 4850L Other shaft scope (early work managed by SURF): Ross rehab continues through mid-2017. New cage and skips 08.12.15Joshua Willhite | FSCF Scope8 Changing for 100% (2) 16” N2 pipes rather than (3) 12”
9
LBNF Yates Shaft Scope For the 100% preliminary design, Arup is including the following work for the Yates Shaft: Removal of bracing in the headframe to accommodate 17m long beams Replacement of timber within shaft from just above the 4850L to the bottom with steel Raising the brow at Yates to accommodate 17m long beams Enlarging the 4850L station to allow beams to come out of skip compartment 08.12.15Joshua Willhite | FSCF Scope9
10
LBNF Cryostat Steel Structure 08.12.15Joshua Willhite | FSCF Scope10
11
LBNF Cryostat Structure Bill Of Materials 08.12.15Joshua Willhite | FSCF Scope11
12
LBNF Yates Brow 08.12.15Joshua Willhite | FSCF Scope12
13
LBNF DUNE Delivery Route 08.12.15Joshua Willhite | FSCF Scope13 Coincides with Ross Campus Access
14
LBNF Underground Excavation 08.12.15Joshua Willhite | FSCF Scope14
15
LBNF Drifts – slashed and new access at the 4850L 08.12.15Joshua Willhite | FSCF Scope15 5m x 6m based on old assumptions – will optimize in FD
16
LBNF Phasing 08.12.15Joshua Willhite | FSCF Scope16
17
LBNF 08.12.15Joshua Willhite | FSCF Scope17 FY27 FY26FY25FY24FY23FY22FY21FY20FY19FY18FY17 FY16 Cavern #1 Excavation FY15 Surface Facilities Cavern #2 Excavation Cavern #3 Excavation SURF Operations Projects Waste Rock Handling Cavern #4 Excavation Utilities in the Shaft Dec-19 CD-2/3c Project Baseline/ Construction Approval Oct-15 CD-1 Refresh Approval Nov-21 CD-4a (early completion) Jan-16 CD-3a Approval Feb-27 CD-4b (early completion) FY28 Conventional Facilities Preliminary & Final Design Sep-19 Beneficial Occupancy Cavern Phase 1 Jan-20 Beneficial Occupancy Cavern Phase 2 Sep-20 Beneficial Occupancy Cavern Phase 3 Apr-21 Beneficial Occupancy Cavern Phase 4 Cavern #1 Outfitting Cavern #2 Outfitting Cavern #3 Outfitting Cavern #4 Outfitting Far Site Conventional Facilities (FSCF) Schedule Summary Overview
18
LBNF LBNF/DUNE Far Site – Critical Path Summary 07.14-16.15E McCluskey | LBNF Project Overview, Cost & Schedule18 Approval to Operate Cryostat #2 FY27 FY26FY25FY24FY23FY22FY21FY20FY19FY18FY17 FY16 Cryogenics Equipment FY15 Cryogenics Fluid Cryostat #2 Construction (including Steel Structure) Install Detector #1 Fill & Commission Detector #1 Install Detector #2 Fill & Commission Detector #2 Utilities in the Shaft Cryostat #1 Construction (including Steel Structure) Excavation and UGI Cavern #1 Conventional Facilities Complete Cryostat #2 Ready for Detector Installation Dec-19 CD-2/3c Project Baseline/ Construction Approval Oct-15 CD-1 Refresh Approval Nov-21 CD-4a (early completion) Jan-16 CD-3a Approval Cryogenics Construction Complete Feb-27 CD-4b (early completion) FY28 Excavation and UGI Cavern #2 DOE Activity DOE and Non-DOE Activity Non-DOE Activity Detector #1 Commissioned Detector #2 Commissioned SURF Operations Projects Waste Rock Handling LBNF AND DUNE
19
LBNF Access Management – Constraints on LBNF contractor 08.12.15Joshua Willhite | FSCF Scope19
20
LBNF Waste Hauling 08.12.15Joshua Willhite | FSCF Scope20 All LBNF CF Deliveries (explosives, ground support, MEP, etc.) will be delivered through the Ross shaft. Depending on phase and work location, these may go past Governor’s corner, through the trolley drift, or through the waste rock drift. Ross Campus access vary change as excavation progresses.
21
LBNF Waste Rock Handling - Underground 08.12.15Joshua Willhite | FSCF Scope21
22
LBNF Surface waste rock handling plan and elevation 08.12.15Joshua Willhite | FSCF Scope22
23
LBNF Controlling Impacts to other Facilities The Ross Campus is fairly close - ~100m from the nearest extent of the campus to the nearest excavation. The Davis Campus is ~1 km upwind of LBNF, so controlling impacts to this campus during most of the construction is relatively straightforward. The addition of raising the Yates shaft brow imposes new concerns at Davis. “The anticipated blast vibrations at the Davis Campus are anticipated to be less than 0.03 in/sec for typical controlled blasting techniques using up to 20 pounds of explosives per delay. This is approximately equal to the threshold of perception of motion indicating that blast vibrations will likely not be detectable by laboratory personnel at the Davis Campus.” CF has proposed a limit of 0.5 in/sec vibration and 134 dBL air blast overpressure, both derived from standard mining criteria. Vibration is controlled with explosives load size and distance, air blast is controlled with isolation walls and doors. 08.12.15Joshua Willhite | FSCF Scope23
24
LBNF Vibration Control (load size vs. vibration) 08.12.15Joshua Willhite | FSCF Scope24
25
LBNF Air Blast Control Most extreme situation is when building a cryostat in cavern 1 while blasting the second pit due to proximity and cross section – draft concept shown at right (under development) Control at Ross Campus is most challenged by retaining ventilation 08.12.15Joshua Willhite | FSCF Scope25
26
LBNF Life Safety Life safety analysis has defined compartmentation layouts and fire rated egress pathways in each phase. Note that ODH analysis and control is the responsibility of the cryo group, who have defined minimum air flow. Compartmentation for fire events also provides for ODH, but is not designed specifically for it. The existing refuge chamber is currently outfitted for 72 persons, 96 hours occupancy. One SURF Operations project is planning to upgrade this room to support as much as 150 occupants. This study will help determine whether this is adequate. 08.12.15Joshua Willhite | FSCF Scope26
27
LBNF Compartmentation and Egress 08.12.15Joshua Willhite | FSCF Scope27
28
LBNF Cyberinfrastructure 08.12.15Joshua Willhite | FSCF Scope28
29
LBNF HVAC - Ducting 08.12.15Joshua Willhite | FSCF Scope29 Note all exhaust through central cavern
30
LBNF Facility Ventilation 08.12.15Joshua Willhite | FSCF Scope30 Intake/Fresh Exhaust/Hot Adding Borehole for 100%
31
LBNF Plumbing and Fire Suppression Cryogenic gas pipes come through the shaft and are taken to the central utility chamber – No liquid cryogens outside of the LBNF footprint. Water is only required for the HVAC system (spray chamber makeup, cooling) and fire protection. Both will use industrial water supply. New supply will tie in with supply being installed for CASPAR and BHUC (derived from David supply), providing redundancy for all campuses. Potable water is provided via UV treatment (identical to Davis and Ross Campus systems) for miscellaneous us. Fire suppression systems (sprinklers) are provided in all areas (except mucking ramp) created for LBNF. Pre-action type in detector caverns. Wet in drifts. 08.12.15Joshua Willhite | FSCF Scope31
32
LBNF Electrical Loads 08.12.15Joshua Willhite | FSCF Scope32 Underground Electrical Load by AreakW Underground Load by FunctionkW Cryostat 1&2 Detector Electronics450Detector2088 Cryostat 1&2 Argon Pumps98CF1846 Cryostat 1&2 CF350898Total =3934 Cryostat 3&4 Detector Electronics450Aggregate Demand Factor0.736 Cryostat 3&4 Argon Pumps98 Demand Total = 2894 Cryostat 3&4 CF342890 Central Utility Cavern - Detector Cryogenics956 Central Utility Cavern - DAQ36 Central Utility Cavern - CF7531745 Spray Chamber165 Maintenance/Assembly Shops (2)84 Surface Electrical LoadkW Drifts152401Cryogen Building5000 Total =3934Control Room250 Aggregate Demand Factor x0.736Emergency/Standby Generator50 Demand Total = 2894 Total Surface Load 5300 Emergency/Standby Generator = 848Temporary Electrical LoadkW Aggregate Demand Factor = 0.393Construction Power 1653 Generator Demand Total = 334 Emergency/Standby Power 699 All fed from new supply originating at Ross Substation
33
LBNF Lighting Lighting at floor level in all space except detector caverns at 24 lux with occupancy sensors in drifts using UL wet location watertight fluorescent fixtures Lighting at 0.7m above the cryostats at 100-150 lux using UL wet location watertight LED fixtures Emergency lighting throughout with 90 minute battery supply and tied to standby generator 08.12.15Joshua Willhite | FSCF Scope33
34
LBNF Controlling EMI To control electrical interference between facility and experiment electronics, separate shielded transformers are provided, and the experiment ground is isolated using inductors and insulators. Additional requirements have been stipulated to avoid ground paths through detector caverns and provide minimum cable lengths to dampen EMI frequencies. 08.12.15Joshua Willhite | FSCF Scope34
35
LBNF Fire Detection Fire detection monitoring will include Smoke detection (VESDA) Oxygen concentration monitors CO detection Heat detection Sprinkler water flow switches Manual pull stations Notification will include alarm, voice, and visual (strobe) Control panels will be strategically located at the 4850L, as well as within the surface control room. System will be coordinated with existing Ross and Davis 08.12.15Joshua Willhite | FSCF Scope35
36
LBNF Structural 08.12.15Joshua Willhite | FSCF Scope36
37
LBNF Architectural 08.12.15Joshua Willhite | FSCF Scope37
38
LBNF 08.12.15Joshua Willhite | FSCF Scope38