Download presentation
Presentation is loading. Please wait.
Published byDaniela Porter Modified over 8 years ago
1
Stone Avenue Train Station Renovation Project Board Workshop June 7, 2010
2
Agenda Overview Status of Project Development Presentation – Revised Scope of Work and Cost Estimates Necessary Renovations Potential Upgrades Discussion Village Board Consensus and Direction
3
Team Introductions Marc Rohde, AIA, LEED AP, Legat Architects Patrick Davis, LEED AP, Senior Estimator, Mortenson
4
Existing Station and Platform Aerial Perspective
5
Current Conditions Existing Site and Floor Plan
6
Current Conditions Existing Building Elevations
7
Necessary Renovations Existions – Train Station
8
Necessary Renovations Existing Conditions – Outbound Platform
9
Necessary Renovations Existing Conditions - Site
10
Proposed Building and Platform Renovations - Repair and paint plaster walls and ceiling - Replace wood trim, fascia, moldings, and soffits with historically accurate no maintenance material - Consider additional period appropriate detail work inside station - Replace existing exterior windows & doors with historically accurate replacements units - Replace existing interior & exterior light fixtures with new, energy efficient, historically accurate light fixtures - Fabricate new exterior signage at the inbound station and outbound platform - Replace exterior gallery flooring with brick pavers around platform Plaster Repairing Tools Source: NPS files Repointing using mortar Photo: John Speweik
11
Necessary Renovations 1. New Aluminum Doors and Frames
12
Necessary Renovations 2. New Gutters, Downspouts, Roofing and Fascia
13
Necessary Renovations 3. New Aluminum Windows
14
Necessary Renovations 4. New Light Fixtures
15
Necessary Renovations 5. Basic Interior Upgrades
16
Necessary Renovations 6. Clean and Repair Exterior Masonry and Stone
17
Necessary Renovations 7. Replace Deteriorated Beadboard Soffit
18
Necessary Renovations 8. Provide ADA Compliant Ramps
19
Necessary Renovations 9. Brick Pavers at Outbound Shelter
20
Discussion and Consensus
21
The Next Steps Finalize conceptual scope of work Design Project (plans, specifications, bids) Continue to Pursue Grant Funding Opportunities Continue to coordinate design and grant agreement process with Metra / BNSF
22
Questions & Answers