1
Library Renovation Projects Update November 12, 2008
2
Space Planning & Facilities Upgrades Renovations address these issues: ADA Accessibility Health, safety & welfare Deferred maintenance Space constriction Technology infrastructure
3
Response to Questions (Maintenance) Maintenance-oriented upgrades comprise 50% of the projects These upgrades include safety, preventative maintenance, deferred maintenance & accessibility
4
Response to Questions (ADA) If our libraries are “grandfathered”, do we need to make them accessible? Renovation triggers code compliance Aging demographic needs It’s the right thing to do
5
Space Planning & Facilities Upgrades A 7 th project enables RFID (Radio Frequency Identification) in all six libraries Security systems Self checkout Inventory control Automated materials handling
6
Response to Questions (RFID) RFID is a GPS for library materials – “smart” tags emit a radio signal locator Priority reasons to implement this over the next five years
7
Response to Questions (RFID) Security Currently $280,000 in missing materials Only Bala & Ludington have security systems; close to end-of-life
8
Response to Questions (RFID) Self Checkout RFID is quick and simple RFID libraries report 60-70% self-check rates Work efficiencies
9
Response to Questions (RFID) Inventory A full inventory is staff intense Performed only once per 5/10 yrs RFID locates misplaced items in minutes Missing items withdrawn & replaced
10
Space Planning & Facilities Upgrades Costs estimates & timeline 2009 Ludington Library - $10.6 million 2010 Bala Library - $6.3 million 2011 Ardmore Library - $1.1 million 2011 Gladwyne Library - $1.3 million 2012 Belmont Hills - $1.6 million 2013 Penn Wynne - $2.7 million
11
Response to Questions (Timeline) Why “front load” the timeline with the largest projects? Deferred maintenance at Bala & Ludington Campaign momentum
12
Response to Questions (Timeline) Could the projects be done in a different order designed to assist cash flow? Possibly. Staff can present scenarios
13
Space Planning & Facilities Upgrades The Lower Merion Library Foundation is carrying out a Capital Campaign to fund $5 – 7 million of project costs
14
Response to Questions (Campaign) Why not establish a threshold dollar amount prior to construction? Lower targets can result in lower returns Uncertainty can result in donor reluctance Public & private-sector grants requirements
15
Ludington Library - Proposed Renovation & Addition 2009
16
Bala Cynwyd Library Renovation 2010
17
Ardmore Library Renovation 2011
18
Gladwyne Library Renovation 2011
19
Belmont Hills Library Renovation 2012
20
Penn Wynne Library Renovation 2013