Download presentation
Presentation is loading. Please wait.
Published byAlison Reynolds Modified over 8 years ago
1
Modernization of Track for High Speeds
2
Modernization Transport more passengers/goods at high speed, safe, economic
3
Modernization Speed > 120 Kmph is considered as High Speed
4
Modernization In order to achieve this speed – track modernization is needed
5
Strength Requirements Rail Heavier sections of rail to provide adequate wearing strength
6
Strength Requirements Rail Heavier sections – 60 kg/m or 52 kg/m Presently – 24.80 kg/m to 44.61 kg/m
7
Strength Requirements Rail Joints Normal joint NOT suitable for High Speed Severe blow due to joints
8
Strength Requirements Rail Joints LONG WELDED RAILS (LWR) CONTINUOUS WELDED RAILS (CWR)
9
Strength Requirements Rail Joints No temperature stress Length – 200 m to 1 km – Indian Conditions
10
Strength Requirements Curve Radius Curve Radius 500 – 600 m
11
Strength Requirements Sleepers Concrete sleepers highly suitable for HS
12
Strength Requirements Sleepers High ‘Sleeper density’ recommended 1660 numbers/km (160 Kmph) 1540 numbers/km (130 Kmph)
13
Strength Requirements Ballast Better quality ballast Depth of cushion – 150 mm to 300 mm
14
Strength Requirements Bridges & Culverts Strengthening existing bridges & culverts Thickness of web/flanges to be increased to bear additional BM & Shear
15
Strength Requirements Track Drainage Should be free from silt
16
Strength Requirements Level Crossings Should be replaced with vehicle underpass
17
LEVEL CROSSINGS
18
Level Crossings Railway line & road surface meet at same level Surface of road kept at rail level
19
Level Crossings Guard rails are provided & spiked to wooden sleepers
20
Classification Procedure Classification of Level-crossing is based on the density of road and railway traffic
21
Classification Procedure Census of traffic passing through the level crossing is made for continuous period of 7 days
22
Classification Procedure Census of number of trains passing through the level crossing is also counted for same period
23
Classification Procedure Weighted figure of road traffic calculated: Bullock cart, car, tonga, truck – 1 unit
24
Classification Procedure Weighted figure of road traffic calculated: Cycle Rickshaw– 1.5 unit
25
Classification Procedure Weighted figure of road traffic calculated: Bicycle– 0.25 unit
26
Classification Procedure Average weighted figure of road traffic for 24 hours is then worked out
27
Classification Procedure Multiplication of average weighted vehicles & no. of trains leads to classification
28
ClassValue A>12000 B>3000 C>1000 D<1000
29
TUNNELLING
30
Full Face Method Adopted only for small tunnels, dimension do not exceed 3 m
31
Full Face Method
32
Vertical columns are fixed at the face of the tunnel
33
Full Face Method A series of drill holes 10-40 mm dia about 1200 mm centre to centre drilled
34
Full Face Method Holes are charged with explosives
35
Full Face Method Mucking tracks could be laid once for all on the tunnel floor and extended as the work progress
36
Heading & Bench Method Method adopted for railway tunnels
37
Heading & Bench Method Heading is the top portion which will be 3700 m to 4600 m ahead of bottom portion, called as bench
38
Heading & Bench Method Heading & Bench portion simultaneously bored and bench is used for removal of muck
39
Heading & Bench Method Advantage: drilling of holes for explosives and removal of muck do not interfere each other
40
Heading & Bench Method
41
Drift System Drift is first driven size of 3000 mm by 3000 mm All horizontal openings made in a tunnel is known as drift
43
Drift System Drill holes are provided all around the drift hole for the entire cross section-filled with explosives All horizontal openings made in a tunnel is known as drift
44
Drift System Drift may at centre or at sides All horizontal openings made in a tunnel is known as drift
45
Pilot Tunnel Method There are two tunnels: Main Tunnel Pilot Tunnel
46
Pilot Tunnel Method Pilot tunnel is first driven for full length
47
Pilot Tunnel Method Pilot tunnel is connected with main tunnel as many points as needed
48
Pilot Tunnel Method Main tunnel can be started drilling
49
Pilot Tunnel Method Pilot tunnel is useful for removal of muck, provide lighting, ventilation
50
Pilot Tunnel Method Also tunnel can be started from number of points
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.