Presentation is loading. Please wait.

Presentation is loading. Please wait.

December 17, 2014.  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low.

Similar presentations


Presentation on theme: "December 17, 2014.  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low."— Presentation transcript:

1 December 17, 2014

2  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low silica  The easement stated the following conditions: ◦ 3 years notice ◦ Up to April 30, 1987 – US Steel pays ◦ After April 30, 1987 – State pays ◦ Work started in 2010

3 1986 2010 2014 I see a pattern developing….. It is only a matter of time!

4  D1: Pat Huston - PM; Rob Ege – Design Mgr.; Andy Johnson – Construction  Bridge –Kevin Western  Geotechnical – Glenn Engstrom  Environmental – Lynn Clarkowski/Nancy Frick  Land Management – Bryan Dodds  CMGC – Jay Hietpas  Utilities – Mollie Zauner  Water Resources – Dave Mohar  Preliminary Design – FHWA  FHWA – David Dominguez

5

6

7

8  May 5, 2017  Plan to negotiated extension when more design is done and contractor input is received.  Only want to ask once!

9 Goal Allow existing TH 53 area to be entirely or partially vacated and mined by May of 2017 Construct the project to provide best value while minimizing future maintenance costs Minimize impacts to the environment Minimize or eliminate future risk to MnDOT related to mining operations. Minimize impacts to all project stakeholders (includes utilities)

10  Total Project cost: $290  Four lane facility  Interchange @ TH 135  Bridge Option on E1A or E2; fill option not moving forward  ROD by August of 2014  Start construction: Fall 2015  Finish construction: Fall 2017  Easement is permanent – no future moves  Preferred alignment will be selected by the end of October  Bridge construction will be steel or concrete

11  Monthly Coffee and Conversation meetings  Public Advisory Committee Meetings  Frequent presentations  Elected Officials  Commissioner and Upper Staff  Governor’s Office

12  TH 53 Re-Alignment PAC Update 12/15/2014  January 2015 Highway 53 Coffee & Conversation will not be held due to DEIS Public Hearing  Tentative DEIS Public Hearing 01/22/2015  Highway 53 Coffee & Conversation 02/05/2015  Highway 53 Coffee & Conversation 03/05/2015  Highway 53 Coffee & Conversation 04/02/2015  Highway 53 Coffee & Conversation 05/07/2015  PAC = Public Advisory Committee  DEIS = Draft Environmental Impact Statement

13 CMGC Contracting in a nutshell CMGC = Construction Manager General Contractor

14  CMGC stands for construction manager, general contractor  CMGC integrates planning, design and construction  It depends on collaboration  During the design phase, the CMGC can assist the owner with ◦ Project scope to meet budget ◦ Design to reduce costs ◦ Improve quality through innovation  Owner and CMGC work together to reduce overall project risk

15 The preferred alignment must still be vetted through the draft and final EIS process with all build and no-build options. The “final” alignment will not be final until the completion of the final environmental impact statement (FEIS).

16

17

18  Core Team Leaders dug into all available information and weighed risks, mitigations, pros and cons to come up with an alignment recommendation for each of their areas.  Their recommendations were based on technical merits only – without regard to cost.  The cost component was disclosed later.

19 AreaE1AE2 Construction CMGC Delivery Roadway Environmental Geotechnical Bridge Right of Way

20

21  When cost was considered, it added reinforcement to the technical portion of the recommendation.

22  The following costs are known as “total project costs”. They include construction, design, right-of-way and minerals among other things.  The costs are based on preliminary engineering and contain contingency.  The cost estimate for E2 will continue to change as more information is available and design begins.

23  M-1: $315-450 million  E-1A Bridge: ◦ Intersection Option: $175-270 million ◦ Interchange Option: Additional cost of $4 million  E-2: ◦ Intersection Option (with Straight Option and Curved Setback Option): $180-240 million ◦ Interchange Option (with Straight Option and Curved Setback Option): Additional cost of $4 million

24  Fall 2014: Proceed with contractor and designer selection after preferred alignment is recommended, announced and there has been an opportunity to hear stakeholder comments/concerns.  March 2015: Designer and CMGC on board- design E2 at risk  December 22, 2014: Publish Draft EIS for review/comment.  January 22, 2015: Public Hearing on DEIS  Summer 2014: Order bridge steel at risk  Summer of 2015: Publish Final EIS.  Late Summer/early fall of 2015: MnDOT publishes adequacy determination; FHWA publishes combined final EIS and Record of decision.

25  Fall of 2015: Start Construction Contract  Reminder: This schedule is best case scenario and is subject to change.

26  Funding  Project  Utility relocations  Trail  Utility Relocations  Trail  Width and use

27 The preferred alignment must still be vetted through the draft and final EIS process with all build and no-build options. The final alignment will not be “final” until the completion of the final environmental impact statement (FEIS).

28 Test Foundations – Winter 2014-2015 E2 West Pier Drilled Pile 2@24”, 1@16” E2 West Pier Drilled Shaft 1@72” Rotosonic and Cores – Winter 2014-2015 E2 West Pier E2 East Pier Roadway Soil Borings – Dec 2014 E2 fill ins

29

30


Download ppt "December 17, 2014.  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low."

Similar presentations


Ads by Google