Download presentation
Presentation is loading. Please wait.
Published byWilliam McCormick Modified over 8 years ago
2
Add potential impacts for a 53/135 interchange Meeting with FHWA to resolve issues Do not have a plan/timetable from FHWA for review. Submit to Cooperating Agencies (EPA and Corp of Engineers) 45 day review -April ? Publish in May 45 day public review Public hearing in 45 day period in Virginia area Preferred Alternatives Selection July 2014
3
- Contractors -3 grading -2 bridge -2 large firms -I JV - General Comments -Get a ROD as early as possible -Time = cost -Material delivery (ste el or geo grid) not an issue -Winter a huge risk -No consensus on flyrock - M-1 -Easiest to build – access and dry
4
- E-1a -Don’t dewater- many issues -Multiple crews needed – 24/7 construction -Access from both ends - E-2 -Use barges and traditional cranes -4- span Steel bridge is appropriate -Use drilled shafts -Candidate for launching girders (haunch issue) -Precast hollow bridge piers appropriate
5
25% of water to the Enterprise pit and local lakes West Two Rivers Reservoir ◦ 5.5 miles ◦ $13.7 million Minntac Cell 2 Tailings Pond 6 miles $21.6 3 month pumping + set up time Costs not in E-1a estimate
6
- Ongoing this week - Emphasis on constructability & geotech - Ott Construction Consultants - Geo Tech -Nick LaFronz – Geo tech from the “Hoover Dam” bridge -Options instead of dewatering -Ideas for testing underwater - Report on Friday 10-noon -Smart Board – CO G22
7
Proposed TH 53 & TH 135 Interchange -Only E-1a & E-2 -M-1 major impacts -Cost (not included) -E-1a $ 4 million (reduces cut) -E-2 $7 million
8
Elements No Build Alternative Existing US 53 Alternative Alternative M‑1 (2 bridges) Alternative E-1A (w/out future bridge) B Alternative E-2 (1 bridge) Construction$1 to $2N/A$153 to 211$74 to 106$120 to 150 ROW/Land/ Mitigation N/A $400 to $600 $96 to 108$ 7 to 11$ 87 to 104 Total Capital Cost for Construction $1 to $2 $400 to $600 $248 to 319$81 to 117 B $207 to 254 B-C Ratio04.504.2510.915.86
9
Existing Roadway $400- $600 million per initial estimate Does not include loss of revenue, jobs etc if mine cannot expand. Flawed methodology per mine geologists Rough calculations by geologists concur with range Need full depth cores and assay to validate Few cores done by MnDOT in 2001 in mine’s possession Will allow to view, but not test. Anecdotal information indicates high quality material with low silica Require condemnation and possible Loss of Going Concern
10
M-1 $95.5 million estimated $75 million in AQ mitigation (model non-compliance) $10 million in Minerals (Mine says too low) $10 million in mine operating costs $0.5 million for other properties Mine has stated that they will not cooperate. Will require condemnation- possible Loss of Going Concern claim Cliffs Natural Resources & RGGS Delay of 6 months +
11
E-1a $6.8 million $4.7 million estimated in ferrous minerals (assay results due end of March) No gold costs, but low risk of gold. Gold assay results due in May If gold, 3 D easement $500,000 in mine operating costs Remainder in other properties/agreement with other parties. Major agreement issues /risks Air and Water Quality No costs included.
12
E-2 $87.4 million $87 million in minerals discounted to present day Not in operating mine or under lease RGGS and School Trust Both open to sale “if the price is right” $0.4 million for other properties Outside any leased or permit to mine area No gold costs included Awaiting assay results – due in June (both gold and ferrous)
13
Changing EPA standards- re-evaluated every 5 years (NAAQS) Two years behind schedule May be new evaluation system with new standards Must meet at mine boundary or at public receptors Modeled or monitored non-compliance permitted by MPCA. Mine could lose AQ permit (closure) Existing T.H. 53 an exception to the permit to mine. New rules for changing permit to mine boundaries.
14
M-1 has modeled non-compliance over NW ¼ in mine PM 10 (dust from trucks) passing under road Southerly portion high – disperses dust E-1a has modeled compliance with a margin of safety Requires mine to relocate stock piles. All mining on one side of the road. Modeled at 4% grade – high above operation Several low volume roads in Permit to mine areas with monitors.
15
Mine Fewer trucks –large cost, need to retrofit crusher Alternate conveyance system in pit (rail, conveyor belts) More watering/dust control –winter issues Pave in-pit roads – continually changing routes State Cover and possible fans - $40-75 million Change permit to mine boundary – EPA variance – no process
16
All road run off must be captured or will re-open mine NPDES permit If mine NPDES re-opened must meet standards for entire mine ($$) M-1 – storm sewer and ponds on north end E-1a - sag in middle of pit Additional concern for drinking water supply. Series of ponds (need MPCA concurrence) Storm sewer- possible pumping Need agreement on storm/BMP’s to mitigate.
17
How do we transfer risk to mine? Agreement on issues and standards Possible payment Negotiate Permit to Mine Boundary with DNR Mining Commissioners Board Will mine need an EAW to expand boundary? Appropriate parties for negotiation. Next steps - Nex
18
May 5, 2017
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.