2
LIU-SPS T. Kramer, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 20 th November 2015 20/11/2015 LIU-ABT Review - SPS2
3
Status Functional specification available ( SPU-M-ES-0001 /EDMS 1399660 ). 2 nd iteration submitted to LIU-ION management. Established 100ns test stand in 867 in February/March. 1 st measurements with diode configuration performed (>200ns tr / not optimized). 2 nd thyratron configuration still to be done. Mid 2015: decision to postpone project to after LS2 -> SPS ion inj. not LIU anymore! However: Feasibility study for 100 ns kicker shall be finished within LIU with reduced priority. Resources: Received 1 FTEC. LIU-ABT Review - SPS 3 20/11/2015
4
Budget 20/11/2015 LIU-ABT Review - SPS4 Year 201520162017201820192020 PV 430 50585 100400 2553 033 04 0 EV 150 AC 18 Covers only inj. kicker WU (as only WU with remaining activities)
5
Conclusions Functional Specification Functional Specification for SPS ion inj. available (v2.0, not approved). Decision taken to postpone project: Decision taken to postpone project: Budget Budget cut (saved 1.92M on kickers) <100k requested in 2016 (50k in 2017). Test stand established reduced priority.. Test stand established but operated with reduced priority. Presently remains within LIU - work to be done in 2016. Feasibility study (LIU) Feasibility study (LIU) to be delivered in 2016. 20/11/2015 LIU-ABT Review - SPS5
6
THANK YOU FOR YOUR ATTENTION!
7
New SPS Injection Layout for Ions (100ns) Use existing (fast) MKP-S kicker with additional PFL. Additional septa (MSI-V) needed. Requires ion injection dump upstream QD12110. MKP-S MKP-L TBSJ MSI MSI-V SPS LSS1 7 MSI MSI-V MKP-S TDI Element Magnetic Length [m] Deflection [mrad] MSI-V (2)1 per mag.12.3 MSI (4)2.1 per mag.42.8 MKP-S (12)8.63 all2.07 17 GeV/c/u PB 82+ 100 ns rise time Q20 compatible Low impedance impact FS chapter 3; page 6 f. LIU-ABT Review - SPS
8
HV-connection of PFL & PFN to Magnet (I) 20/11/2015 LIU-ABT Review - SPS8 2 x 3 RG-220U Transmission cables MS Thyratron PFN PFL 3 x 25Ω? 70m 2 x 3 RG-220U Transmission cables MS Thyratron (PFL) PFN PFL 3 x 25Ω? 70m MS Thyratron (PFN) Magnet Module n+1 Magnet module n Magnet Module n+1 Magnet module n 8.3 Ω 16.6 Ω Option 1Option 2
9
Initially Planned Schedule 20/11/2015 LIU-ABT Review - SPS9 SPS MKP 100ns PFL upgrade 2014LIU-SPS Ion Injection Functional Specification (Done, waiting for other WU and approval ) Early 2015Basic 100ns PFL test stand available (867). Mid 2015Basic 100ns PFL tests and analysis finished. Carry on with extended tests if necessary (see option1/2). Q4/2015Detailed system design & Technical Specification available. EOY 20151st drawings available. Q2/2016All Drawings available. Long lead items ordered. Production for “in-house” subcomponents started. 2017Production and preassembly. Q2/2018Preassembly finished – QA lab testing of produced components. Aug/2018Installation of PFL cables. Q4/2018Modification of PFN tank/ installation of PFL switch components. 2019Installation of RCS, connection of new components to controls system. EOY/2019All activities finished. Q1/2020HW/Beam commissioning. Activities in parallel with KFA-53(45?) development!
10
Budget (2014) 20/11/2015 LIU-ABT Review - SPS10 all in kCHF 100 ns Injection kicker Proto-type150 Design office150 6 PFLs300 6 switches420 6 connections PFN/PFL300 3 Resonnant Charging Systems (50% EC)150 BA1 modifications (40% EC)100 Cabling (50%EC)100 Slow controls90 Fast controls60 Interlocking30 FSU controls50 S 1900 FSU FPS200 Total2100