ACO & AD0 DCS Status report Mario Iván Martínez
2
LS1 from DCS point of view Roughly halfway through LS1 now – DCS available through all LS1, as much as conditions (EL, Cooling) allow. Major topics for DCS during LS1 are: – M igration to WinCC OA 3.11 (from PVSSII 3.8) – Upgrade to newer OS (WS2008, SLC6) – Validate all existing and new tools in new environment – Replace obsolete hardware (new severs, new DB, phase out PCI, …) – Rationalize our installations in CR3 – Preparation for RUN2 operation (issues from Consolidation Task Force, new shifter training, …) 35th ALICE DCS Workshop26 March 2014
3
LS1 highlights up to now DCS running virtually untouched until May (when DAQ switched off) – Many post-run1 activities that required DCS operational Migration ‘tests’ started summer 2013 – Many issues discovered, thorough preparation to ease the process as much as possible for detectors, at the same time profiting to do major cleanup Major maintenance on Point 2 cooling infrastructure (phase 1) – Essentially no cooling from June to October – Significant increase in cooling power at P2, complete update of cooling control systems Replacement of obsolete UPS infrastructure – Many power interruptions from June to September
4
Migration phases Phase I (detector expert): preparing the project for the migration Phase II (ALICE DCS support): install Windows Server 2008, WinCC OA 3.11, applications (on request) Phase III (detector expert): install project, Framework, test and commissioning Important: – Use the guide and checklist available in https://espace.cern.ch/alicecontrols/DCSDocuments/default.aspx https://espace.cern.ch/alicecontrols/DCSDocuments/default.aspx – Always communicate to alice-dcs-support@cern.ch (JIRA)alice-dcs-support@cern.ch
5
DCS Operating Systems All servers already updated to ORACLE 11.2.04 Windows Server 2003 (32 bit) Windows Server 2008 (64 bit) SLC 5 SLC 6 Etm PVSS 3.8 Siemens WINCC OA 3.11 24/03/2014 Vasco Barroso on behalf of DAQ, DCS and HLT 5
6
Migration status phase completed phase started Almost all the central systems are now running WinCC OA mixed environment no major problems Deadline for the migration: end of April
7
DetectorDate Duration (hours)Notes MCH12 May 201448Scheduled EMC14 May 201448Imminent SDD & SPD & SSD19 May 201448Combined T00, V0021 May 201448Combined TPC-laser23 May 201424Single TOF26 May 201448 TRD28 May 201448 TRI29 May 201424 MTR02 June 201448 PMD04 June 201448 ACO & ADO09 June 201424Combined FMD10 June 201424 ITS-COO11 June 201424Single? MCH-GMS12 June 201424Single ZDC13 June 201424 OS and WinCC update schedule
8
DCS CR3 Cluster size Central DCS 56 machines 14 DELL Power Edge R310 1U 42 HP Proliant DL120 G6 1U Database Service 4+2 Power Edge M610 blades Storage: 4x Promise E310fs arrays Detector DCS 105 machines 95 DELL Power Edge R310 1U 10 HP Proliant DL120 G6 1U Fileservers 6 HP Proliant DL180 G6 2U
9
New Computing hardware New database service – Hardware ordered (DB servers and storage) – Installation in summer 2014 – Will completely replace the existing DB infrastructure in CR3 DCS Worker nodes – Purchasing procedure launched – Installation summer 2014 – 50 DELL PowerEdge R320 will replace HP Proliant servers
10
New UPS power Before: – 60+80 kVA UPS power for CRs (>90% loaded, regularly causing problems) CR1, CR2: only core of DAQ and HLT on UPS CR3: all DCS on UPS CR4: only critical systems (e.g. BCM, TPC drift HV) on UPS After: – 200+500 kVA UPS power for CRs CR1: all DAQ on UPS CR2: production part of HLT on UPS CR3: all DCS on UPS CR4: all racks (notably all detector HV power supplies) on UPS 35th ALICE DCS Workshop26 March 2014