2007. 09. 12 1&2 UNIT KORI NPP
2
2 General Introduction Ⅰ Ⅲ GOOD PRACTICE FIELD APPLICATION CONCLUSION Ⅴ Ⅱ GOOD PRACTICES EFFECT ANALYSIS ⅳ
3
3 Kori 1 Location : East in Korea Type : PWR Commercial Operation : 04. 1978 NSSS/TBN : Westinghouse/GEC-Al stom Output : 587 MWt/650 Mwe, 2 Loop Under getting renewal approval & permission to keep up operation Kori NPP
4
4 LOND O N Sizewell “B” Sizewell B Plant Location : Sizewell in Suffolk Type : PWR of British Energy Commerical Operate : 01. 1995 NSSS/TBN : Westtinghouse/GEC-Alstom Output : 3,411 MWt/1,200 Mwe, 4 Loop
5
5 ITEM19992000200120022003200420052006 S/W “B”485468635419251297321470 KORI 19856224975875551003607 ULCHIN 19571,056769989712612587758 OUTAGE (Unit : man-mSv)` COLLECTIVE RADIATION DOSE BY EUROPEAN
6
6 S/G CHANNEL HEAD (MAX) (Unit : mR/h) ITEM1st2nd3rd4th5th6th7th8th SW “B”360500620350-340-420 KORI 1--12,00020,00018,00014,00025,00020,000 ULCHIN18,3009,40013,7009,1609,7008,7008,20013,500 COLLECTIVE RADIATION DOSE
7
7 An systematic chemical treatment improved from HFT for operating the power plant.(Li-B pH Control mode) An systematic chemical treatment improved from HFT for operating the power plant.(Li-B pH Control mode) C hemical treatment improved Operate the 4RCPs at the stage of Acidic Oxidation after inserting hydrogen peroxide to remove crude Uses Inconel-690 of low cobalt for S/G Tube. Perform large-scale cleaning removing the residual cobalt Uses Inconel-690 of low cobalt for S/G Tube. Perform large-scale cleaning removing the residual cobalt Changed design & Cleaning
8
8 Radiation Protective Equipment Out sweat in the working clothes Not infiltrates pollution from outside Fine in weave & pollution is well removed See its ADR through clear plastic bag after wearing it. Out sweat in the working clothes Not infiltrates pollution from outside Fine in weave & pollution is well removed See its ADR through clear plastic bag after wearing it. Radiation Protective Equipment
9
9 Cavity Cleaning
10
10 Many Sized Shielders Shielding Movable / Permanent Shielding Easy Shielding Flexibility
11
11 Existing Clothes ADAPTING CONTENTS ADAPTING CONTENTS Vinyle ClothesHoodRubber Gloves Blue SuitLS ClothesClean CapThin Rubber Gloves
12
12 Assigned : 11areas Location : Rx+20.0m(2area), Rx+11.5m(2area), Rx+8.0m(3area), Rx+ 5.0m(1area), Rx± 0.0m(2area), Rx-3.4m(1area) Assigned : 11areas Location : Rx+20.0m(2area), Rx+11.5m(2area), Rx+8.0m(3area), Rx+ 5.0m(1area), Rx± 0.0m(2area), Rx-3.4m(1area) Object Major staff - white helmet with yellow rim Operator - white helmet with red rim HP - yellow jacket Object Major staff - white helmet with yellow rim Operator - white helmet with red rim HP - yellow jacket Assign Laydown area Assign Laydown area Safety helmet color differentiation Safety helmet color differentiation
13
13 Buffing, Grinding, Assembly/Disassembly of lagging (ISI) Wearing glasses inside goggle – Wilder, Enlargement Wearing glasses inside goggle – Wilder, Enlargement Assembly of lagging meterialsBuffing
14
14 Stretcher : In the C/V Medical treatment supplies : At the entrance of the C/V Stretcher : In the C/V Medical treatment supplies : At the entrance of the C/V Set up Medical treatment supplies in the C/V Set up Medical treatment supplies in the C/V StretcherMedical treatment supplies
15
15 FME (Foreign Material Exclusive) FME (Foreign Material Exclusive) View Zone hand rail Reactor Cavity Stud Bolt S/G 2 nd hand rail Reactor Cavity S/G 2nd Man-Way hand rail View Zone hand rail (S/G A Upper) Stud Bolt Reactor Cavity S/G 2nd Man-Way hand rail View Zone hand rail (S/G A Upper) Stud Bolt
16
16 Washing/Drying TIME
17
17 Disposal Water Amount 200L/Drum - 240 Blue Suit, 192 LS Clothes - 80 Existing Clothes, 200 Vinyl Clothes Drum Packages
18
18 ItemOperation PeriodOutage Instrument electric power consumption electric power consumption Blue Suit LS Clothes Existing Clothes Existing Clothes Blue Suit LS Clothes Existing Clothes 1time/1day (Washer 2set, Dryer 1set) 1time/1day (Washer 2set, Dryer 1set) 1time/1day (Washer 2set, Dryer 2set ) 1time/1day (Washer 2set, Dryer 2set ) 2time/1day (Washer 3set, Dryer 2set ) 2time/1day (Washer 3set, Dryer 2set ) 100KW/1day 473KW/1day 2time/1day (Washer 3set, Dryer 3set ) 2time/1day (Washer 3set, Dryer 3set ) 3time/1day (Washer 3set, Dryer 3set ) 3time/1day (Washer 3set, Dryer 3set ) 7time/1day (Washer 3set, Dryer 3set ) 7time/1day (Washer 3set, Dryer 3set ) 363KW/1day 1,656KW/1day Electric power consumption
19
19 No Contamination(Blue suit) Material Characteristics of LS clothing (Nylon99%+Carbon Fiber 1%) No Contamination(Blue suit) Material Characteristics of LS clothing (Nylon99%+Carbon Fiber 1%) Pollution removal rate R emoval rate 38 (Less 400Bq/100 ㎠ ) 33.4054.112’nd 12.4743.081’st Pollution removal rate(%) 394 ~ 3,702315 ~ 3,939 Range of Contamination(Bq/100 ㎠ ) 13 Object(suit) Existing ClothesLS ClothesItem
20
20 Blue Suit / LS Suit / Clean Cap / Thin rubber gloves flexibility Distinguish safety helmets by colors 2007. 05. 10 2007. 05. 10 – 5. 23 (ULJIN 1) 2007. 06. 22 – 06. 24 (KORI 1) 2007. 06. 22 – 06. 24 (KORI 1) Location : C/V L-5 & L-4 (27~28 ℃, 80%) Location : C/V L-5 & L-4 (27~28 ℃, 80%) Research period Subjects
21
21 KHNP, KPS, Samchang, KPS’s contractors KHNP, KPS, Samchang, KPS’s contractors PARTICIPANTS RESULT 95% satisfied(ULCHIN) Improvement Subjects Blue Suit - Separating winter and summer season - Elastic cord and string simultaneously - Thinner cotton - Size and tag mark LS Suit - Resistant to tearing - Sticks to body owing to sweat - Body types - Anti-crumple
22
22 Apply the applicable items in the field In nuclear power plants in Europe, through the improvement in radiation control parts. Make effort to reduce radiation exposure