Status of SESAME Synchrotorn-light for Experimental Science and Applications in the Middle East SESAME, Allan, Jordan Maher Attal On behalf of SESAME Team M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
2
Introduction SESAME is a joint 3rd generation light source being constructed in Jordan (in Allan, 30km west of Amman) for the Middle East and expected to serve the user community starting from the 1st half of 2017. SESAME machine consists mainly of: 800 MeV injector (22.5 MeV classical Microtron MeV Booster) (BESSY I injector). completely new hard X-ray storage ring with energy 2.5 GeV. maximum number of 25 beamlines. M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
3
Injector Commissioning is Done: Microtron
SESAME Microtron Main Parameters Extractable energy MeV Extractable turns – 42 Energy gain / turn keV Energy spread(FWHM) keV Magnetic field T Microwave frequency, power GHz, 2MW Pulse duration s Beam power kW at 21MeV H-emittance m.rad (100% of the 21MeV) V-emittance µm.rad (100% of the 21MeV) 3 mm 4.4 mm Full energy beam at end of Microtron-Booster transfer line (~22MeV) March 27, 2012. M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
4
Injector Commissioning is Done: Booster
TL1 Microtron Main Booster parameters Injection energy MeV Extraction energy MeV Circumference m H-emittance nm.rad Mom. com. factor RF frequency MHz RF max. power kW Operation freq Hz Inj. kicker pulse ~ 4.5µs Design current mA Booster Transfer line TL2 M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
5
Injector Commissioning is Done: Booster
Ibeam = 4 mA (~ 5% injection efficiency) was achieved for the best shots. The varying injection efficiency is due to instability in the electrostatic injection septum. Ibeam = 7-8 mA (8-9% injection efficiency) was recently achieved by compensating beam loading effect using RF Fast Feedback Loop. M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
6
Storage Ring Main Parameters
Main Storage Ring parameters: Energy GeV Circumference m H-emittance nm.rad Lattice type simple DBA (one dipole family, 2 qudarupole families, 2 sextupole families Bending magnet L = 2.25m, B = T, g = -2.79T/m. straight sections sections (8 x 4.4m + 8 x 2.4m) Beam lines beamlines ( 13 from dipoles + 12 from insertion devices). RF frequency MHz beam current up to 400mA y One super-period. The ring is composed of 8 super-periods. x x M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
7
SESAME Layout Service Entrance Labs Labs Storage ring Microtron
Booster Main Entrance Labs Labs 7 M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
8
Storage Ring Status: Magnets
Storage ring magnets are constructed through CESSAMag project in the frame of SESAME-CERN/EU collaboration (big support from EU and CERN) Dipoles are constructed by TESLA (UK) and magnetically measured at ALBA light source (Spain). Quadrupoles are constructed by Elytt (Spain) (coils by STS-Turkey) and magnetically measured at CERN. Sextupole are constructed by CNE (Cyprus) & HMC-3 (Pakistan) (coils by SEF-France) and magnetically measured at CERN. All magnets have been delivered to SESAME. M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
9
Storage Ring Status: RF System
The 500 MHz RF system is composed of 4 RF plants. Each plant consists of: kW Elettra cavity (detuned up to ±2MHz). Collaboration agreement was signed with Elettra. 2 M€ donation from Italy (4 RF cavities). Delivery of 4 cavities to be completed by Sep - 80 kW solid state amplifier(the 1st is built by SOLEIL, the 3 others by Sigmaphi-SE). Two amplifiers have been constructed. Delivery of 4 amplifiers to be completed by Sep - WR1800 waveguide (in-kind contribution from DESY) - Digital LLRF is constructed by Dimtel-LLRF (to be delivered soon) SSA-SOLEIL M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
10
Storage Ring Status: Vacuum Chamber
Vacuum chamber is constructed by FMB (Germany). ~ 70% of it is delivered to SESAME. Expected delivery date of last batch is June 2016. Chamber prepared for baking at SESAME M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
11
Storage Ring Status: Girders
0.9m 5.2m 0.953m Flatness < ± 50 µm, Pin-positioning < ± 50 µm, Deflection under load < 50 µm. Contstructed by Nortemecanica, Spain. All girders have been delivered to SESAME. M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
12
Storage Ring Installation is Going on …
12 cells out of 16 have been installed. Chamber baking oven (from SLS) Preparations to install cooling and cabling systems are going on(expected to be installed by Sep. 2016 Storage ring commissioning expected by end of 2016. M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea 12
13
SESAME Phase 1- Day 1 Beam Lines
No. Beamline Energy Photon Source Research Area Comment 1 Protein Crystallography 4 – 14 keV BM or IV U ? Structural Molecular Biology Daresbury 2 XAFS / XRF 4– 30 keV Bending Magnet Material Science, Environment Helmholtz-Zentrum Dresden-Rossendorf/ESRF. New focusing components. 3 IR Spectromicroscopy (EMIRA) 0.01 – 1 eV Environmental, Materials, Biological, and Archaeological Science Completely new beam line 4 Powder Diffraction 3 – 25 keV 2.1T Wiggler Material Science SLS (with source) 5 Soft X-ray, Vacuum Ultraviolet (VUV) 0.05 – 2 keV E.P.Undulator Atomic, Molecular and Condenced Matter Physics 6 SAXS / WAXS 8 – 12 keV Structural Molecular Biology, Material Science 7 Extreme Ultraviolet Spectroscopy 10 – 200 eV Atomic and Molecular Physics Daresbury & LURE “Day-one” beamlines M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
14
(BASEMA) XAFS/ XRF Beam Line
Beamline Scientist: Messaoud Harfouche Status: Under installation. Expected to be ready in late summer 2016 and fully operational in 1st half of 2017. Inside the optical hutch. Optical and experimental hutches installed. M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
15
(EMIRA) IR Beam Line SESAME IR Lab Beamline Scientist: Gihan Kamel
Designed in collaboration with SOLEIL. The experimental station ( IR spectrometer + IR microscope) is already at SESAME and being used in some biomedical research but using conventional IR source. Status: Under construction. Expected to be installed by end 2016 and operational by beginning 2017. Dipole chamber Protection wall Diamond window Experimental station Branch 1 Branch 2 SESAME IR Lab M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
16
Powder Diffraction (Material Science) Beam Line
Beamline Scientist: Mahmoud Abdellatif Status: Some parts should go through modifications or new design. Expected to be ready operational by end 2017. SLS wiggler W gap (mm) K B (T) Ec 2.5 GeV Power 400 mA Power 200 mA 8 10.4 1.84 7.65 10.7 5.35 45 10 9.0 1.6 6.65 7.98 3.99 40 12 * 7.8 1.38 5.8 6.01 3 25 14 6.7 1.19 5 4.47 2.24 20 * 12 mm is the minimum gap to be used for this wiggler. 16 M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
17
Many Thanks Other supporters to SESAME … many thanks to them: - International Organizations: IAEA (big supporter), ICTP, UNESCO, ESRF - National Organisations & Synchrotron Labs in: Brazil, France (SOLEIL), Germany, Italy, Japan, Portugal, Spain, Sweden, Switzerland, Taiwan, UK, USA. - Foundations: Canon, Lounsbery …… And many others M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea
18
Thank you M. Attal, Fusion Device & Accelerator Business Meeting, May , BEXCO Building, Busan, Korea