Presentation is loading. Please wait.

Presentation is loading. Please wait.

The Intricacies of the Beginning and the End of a Project CM Leadership Manual Presented by: Todd Scholtz, LEED AP Carlos Sanchez, LEED AP BD+C.

Similar presentations


Presentation on theme: "The Intricacies of the Beginning and the End of a Project CM Leadership Manual Presented by: Todd Scholtz, LEED AP Carlos Sanchez, LEED AP BD+C."— Presentation transcript:

1 The Intricacies of the Beginning and the End of a Project CM Leadership Manual Presented by: Todd Scholtz, LEED AP Carlos Sanchez, LEED AP BD+C

2 CM Manual - Living Document A work in progress. A resource for document control. To fill your site-specific needs. 2

3 CM MANUAL – TABLE OF CONTENTS 8 Sections 1.Document Control 2.Mobilization and Start-up 3.Contract Administration 4.Quality Management 5. Safety 6. Schedule Management 7. Risk Management 8. Project Closeout & Turnover Glossary Appendix 3

4 Section 2 Mobilization & Start-Up 2.2 - Pre-construction Conference 2.3 - Substitution Requests 2.4 - Permits 2.5 - Insurance Certificates 2.6 - Performance and Payment Bonds 2.7 - Site Office 2.8 - Site Management Plan 2.9 - Meeting Schedule / Calendar 2.10 - Partnering 2.11 - Early Submittals 2.12 - Establish Risk Management Process 2.13 - Establish Project Controls Systems 2.14 - Establish Communication Plan 4

5 Section 2 2.2 Mobilization – Pre-Construction Conference Purpose – Inform all participants CM Role – Facilitate meeting 5

6 Section 2 2.3 Mobilization – Substitution Request Material –Submittal process Subcontractor –Approval process 6

7 Section 2 2.4 Mobilization & Start-Up - Permits Responsibility Payment Display NEPA compliance Environmental issues Right of way Limits and boundaries 7

8 Section 2 2.5 Mobilization – Insurance Certificates Types –Builder’s Risk –General Liability –Worker’s Compensation –Professional Liability (when required) Owner-Controlled Insurance Program (OCIP) 8

9 Section 2 2.6 Mobilization – Bonds Types –Performance Bonds –Payment Bonds 9

10 Section 2 2.7 Mobilization – Site Office Requirements in Division 1 Office set-up checklist –Office Set-up ChecklistOffice Set-up Checklist 10

11 Section 2 2.8 Mobilization – Site Management Plan Parking Safe access and egress –Regulatory requirements Site signage Temporary and permanent utilities –Application –Requirements –Payment –Coordination 11

12 Section 2 2.9 Start-up – Meeting Schedule / Calendar Attendance Format Schedule Coordination 12

13 Section 2 2.10 Start-up – Partnering Attendance Format Schedule Coordination Payment “Partnering is used to establish a collaborative solution – oriented process for the project. It does not replace contractual obligations” 13

14 Section 2 2.11 Start-up – Early Submittals Safety Plan QC Plan Schedule of Values Submittal Schedule Long-lead materials Initial Progress Schedule 14

15 Section 2 2.12 Start-up – Risk Management Process Section 7 in CM Manual Potential issues and how they will be handled – CM ManualCM Manual “Applying Risk Management to Project Performance” 15

16 Section 2 2.13 Start-up – Project Control Systems SOW for CM role Structured filing system (or PM software) Document Control System Daily reporting procedure (including photos) Schedule of meetings and invitees 16

17 Section 2 2.14 Start-up – Communication Plan Routing of paperwork Distribution Archiving parameters “It is important that the CM clearly understands their role and level of authority with regards to representing the owner” 17

18 Section 8 Project Closeout & Turnover Section 8 Project Closeout and Turnover 18

19 Section 8 Project Closeout & Turnover Project Closeout 8.1 - Punchlists 8.2 - Permits and Final Inspections 8.3 - Certificate of Substantial Completion 8.4 - Certificate of Final Completion 8.5 - Beneficial Occupancy 8.6 - As-built Drawings 8.7 - Training 19

20 Section 8 Project Closeout and Turnover Turnover 8.8 - O&M Manuals 8.9 - Attic Stock 8.10 - Warranties 8.11 - Building Turnover / Move-in 8.12 - Follow-on Contractors 8.13 - Furniture Fixtures and Equipment 8.14 - Project Record Archiving 8.15 - Project Closeout – Final Pay, Retainage Release 20

21 Section 8 8.1 Project Closeout - Punchlists Contractor notification – Initiates process – Notifies work is substantially complete CM and designer –Issue punchlist with SC Certificate Punchlists – Deficiency Log - SampleSample 21

22 Section 8 8.2 Project Closeout–Permits & Final Inspections Final Inspections by trades and AJUs Temporary CO (TCO) Certificate of Occupancy (CO) Other forms 22

23 Section 8 8.3 Closeout–Certificate of Substantial Completion Issued by the Designer CM provides to the contractor along with punchlist Warranties began 23

24 Section 8 8.4 Closeout–Certificate of Final Completion Issued by the Designer Punchlist has been completed 24

25 Section 8 8.5 Project Closeout–Beneficial Occupancy Notice date Take photos CM coordinates any work within the occupied space 25

26 Section 8 8.6 Project Closeout–As-built drawings As-built along with payment applications Final as-built upon project completion 26

27 Section 8 8.7 – 8.10 Project Closeout O&M Manual requirements Training –Schedule –Document Attic Stock Warranties 27

28 Section 8 8.11 – 8.13 Building Turnover & Move-in Coordination with contractor and –Moving crews –Follow-on contractors –Furniture, fixtures and equipment (FF&E) –LEED Enhanced Cx 28

29 Section 8 8.14 – 8.15 Project Turnover–Records & Closeout Project Records Archiving Project Closeout –Final Pay –Retainage Release –Release of Liens 29

30 Glossary In the Glossary you will find the definitions to 154 commonly used terms in the construction industry. Arranged alphabetically from A/E to Work 30

31 Appendix A Project Controls specification that outlines the basic requirements for the: Preconstruction Conference Progress Meetings Preinstallation Meetings Submittal Procedures The Contractors CPM Construction Schedule 31

32 Questions

33 Lessons Learned

34 Thank you!


Download ppt "The Intricacies of the Beginning and the End of a Project CM Leadership Manual Presented by: Todd Scholtz, LEED AP Carlos Sanchez, LEED AP BD+C."

Similar presentations


Ads by Google