Review of 2014/15
2
Topographic surveys
3
Lidar surveys 2014/15 Partial areas only All signed off and loaded to website
4
Lidar surveys 2013/14 Complete coverage of SE, mostly to MLWS One area [Medmerry] completely signed off. Of remaining 11, 4 polygons recently re-issued by Geomatics
5
UKHO survey status (March 2015)
6
Dark green in 100% swath bathymetry (IHO Order 1/1a)
8
Swath bathymetry surveys - CHP
9
Northeast
11
Waves, tides and met New tide gauge on Arun Platform (some set-up problems)
12
Eastbourne Pier (REX)
13
Terrestrial ecological mapping Specification refined Specification refined Work to be commissioned for F/Y 2015/16, to map 2013 ortho- photography, and compare with 2008 results Work to be commissioned for F/Y 2015/16, to map 2013 ortho- photography, and compare with 2008 results
14
Monthly website hits
16
Quarterly downloads from website (SE)
17
Medmerry
18
Next year?
19
Phase IV STAR schedule ActivityTimeStart DateTarget DateStatus Coastal Group agreement to prepare STAR Apr-13 Complete Free availability of project data to all (EA board) Aug-13 Outstanding Formation project board Oct-13 Complete Establish current financial rules for FDGIA Oct-13 Complete Consultation with various EA tiers on programme content (EA) Oct-13Jan-14Ongoing Consultation with LA operating authorities Oct-13 Complete Programme design Mar-14Sep-14Complete New programme elements - design and consultation Aug-14Sep-14Complete Project Board and Steering Group Sep-14Complete Local Authorities democratic process for lead authorities Sep-14Dec-14Started Develop procurement/delivery strategy Aug-14Sep-14Ongoing STAR production May-14Dec-14Started Present to Coastal Groups Winter 14/15 Submit STAR to LPRG Feb-15 OJEU Procedure advertise for framework tenders 167 days Jan-15Jul-15 OJEU Contract Notice Period 30 days Feb-15Mar-15 LPRG recommendation Mar-15 Contract documentation & award for 2016 Feb-16Mar-16 Coastal Monitoring Programmes for 2016 - 2022 (SE from 2017) 01 April 201631 March 2022
20
Phase IV STAR schedule ActivityTimeStart DateTarget DateStatus Coastal Group agreement to prepare STAR Apr-13 Complete Free availability of project data to all (EA board) Aug-13 Ongoing Formation project board Oct-13 Complete Establish current financial rules for FDGIA Oct-13 Complete Consultation with various EA tiers on programme content (EA) Oct-13Jan-14Complete Consultation with LA operating authorities Oct-13 Complete Programme design Mar-14Sep-14Complete New programme elements - design and consultation Aug-14Sep-14Complete Project Board and Steering Group Sep-14Complete Local Authorities democratic process for lead authorities Sep-14Dec-14Complete Develop procurement/delivery strategy Aug-14Sep-14Complete STAR production May-14Dec-14Complete Present to Coastal Groups Autumn/winter 2014/15 Complete Submit STAR to LPRG Feb-15 Complete OJEU Procedure advertise for framework tenders 167 days Jan-15Jul-15 OJEU Contract Notice Period 30 days Feb-15Mar-15 LPRG recommendation Mar-15 Aug-2015 Complete Contract documentation & award for 2016 Feb-16Mar-16 Coastal Monitoring Programmes for 2016 - 2022 (SE from 2017) Apr-16Mar-22
21