Presentation is loading. Please wait.

Presentation is loading. Please wait.

MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.

Similar presentations


Presentation on theme: "MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006."— Presentation transcript:

1 MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006

2 Chris BoothUniversity of Sheffield 2 Since last CM: Regular meetings on mechanics Sheffield/RAL/Oxford –Convert standalone test setup → working device. –Engineering design for support and withdrawal mechanisms. –Material & techniques compatible with ISIS vacuum. Major progress in readout & control – see Lara’s talk. Support frame under construction at RAL. Ceramic liner made, indium seals tested. Not ready for planned January tests. Measures in place to be ready for June.

3 Chris BoothUniversity of Sheffield 3 Why did we miss ISIS tests? New drives were over 3 months late. (Manchester connection!) Sheffield technician’s accident – 1 month off work. Under-estimate of work involved (Sheffield & RAL ends) But we learned a lot by trying!

4 Chris BoothUniversity of Sheffield 4 Plans for (immediate) future Build our own drive units Facilities identified (within University or local companies) for: –Wire erosion of magnet material –Magnetisation –Coil winding –Vacuum potting of coils. Upgrade power electronics 10 A → ≥ 40 A –Manchester development in progress –Lancaster Elec. Eng. Dept. (via Rebecca Seviour)

5 Chris BoothUniversity of Sheffield 5 Major milestones Full mechanical assembly at RAL – end March Operate at RAL outside ISIS – end May Install & operate in ISIS – June. Detailed programme under preparation


Download ppt "MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006."

Similar presentations


Ads by Google