Presentation is loading. Please wait.

Presentation is loading. Please wait.

Andrew BurrillFall 2011 Project X Collaboration Meeting 650 MHz Developments at JLAB Andrew Burrill for the JLab Team.

Similar presentations


Presentation on theme: "Andrew BurrillFall 2011 Project X Collaboration Meeting 650 MHz Developments at JLAB Andrew Burrill for the JLab Team."— Presentation transcript:

1 Andrew BurrillFall 2011 Project X Collaboration Meeting 650 MHz Developments at JLAB Andrew Burrill for the JLab Team

2 Andrew BurrillFall 2011 Project X Collaboration Meeting Program Overview Jefferson Laboratory has designed a 5 cell, β = 0.61, 650 MHz cavity as an option for Project X. Based on this design two single cell cavities have been fabricated, processed and tested in-house. The cavities were fabricated from 4 mm RRR>250 niobium sheet. The cavities were chemically etched using 1:1:2 BCP to remove ~250 μm of material. Hydrogen degassing at 600 °C for 10 hours Cavity-A had a Qo value >1x10 11 at 1.6 K corresponding to a residual resistance of < 1.5 nΩ. Both cavities have exceeded E acc of 17 MV/m. Additional information may be found in: MOPO007 Proceedings of SRF 2011 MOPC114 Proceedings of IPAC 2011

3 Andrew BurrillFall 2011 Project X Collaboration Meeting Cavity Design 5 cell cavity design based on β=1 high average current cavity shape fabricated & tested at 748.5 MHz & 1497 MHz. –Cavity features flat cell walls Facilitates chemical etching and cleaning Reduces electron impact energy –multipacting –Large iris apertures & flat equator region Should aid in mechanical stability Increased cell to cell coupling Aid in field flatness sensitivity Reduce amount of post-fabrication tuning

4 Andrew BurrillFall 2011 Project X Collaboration Meeting RF Parameters JLab design utilizes a larger beamtube and iris ID Advantages: better cell-to-cell coupling better mechanical stability less field flatness distortion less HOM trapping and field tilts better cleaning Disadvantages trade-off with RF properties (see table)

5 Andrew BurrillFall 2011 Project X Collaboration Meeting 5 cell β=0.61 Multipacting Analysis

6 Andrew BurrillFall 2011 Project X Collaboration Meeting Fabrication & Processing at JLab 2 cavities fabricated from 4 mm RRR>250 sheet material from ATI Wah Chang Beamtubes made from reactor grade sheet Standard deep drawing and surface grinding of half cells Equator butt weld NbTi flanges with AlMg 3 seals Mating flanges are SS 250 µm bulk BCP w and w/o flow diverter Hydrogen degassing : 600C,10 hrs Light, 50 µm, BCP Single pass HPR, 1250 psi with 2 opposed 25 degree nozzles Drying and assembly in Class 10 space

7 Andrew BurrillFall 2011 Project X Collaboration Meeting 650 MHz Cavity A Vertical RF Test

8 Andrew BurrillFall 2011 Project X Collaboration Meeting Cavity Test Results Temperature dependence of the surface resistanceΔf/Δp of 4.4 kHz/mbar unstiffened and 1.7 kHz/mbar Lorentz Force detuning for the unstiffened (Cavity A), and stiffened (Cavity B)

9 Andrew BurrillFall 2011 Project X Collaboration Meeting

10

11

12 Current Research Path Finalize the mechanical design for the 5 cell β=0.61 cavity –Pressure calculation –Stiffening ring location optimization –Integration into the Fermi helium vessel Things we would like to do: Build a 5 cell β=0.61 to prove out the design, measure RF performance, compare BCP to EP, etc. Finalize the design & Fabricate a JLab β=0.9 prototype

13 Andrew BurrillFall 2011 Project X Collaboration Meeting Summary Jefferson Laboratory has designed a 5 cell, β = 0.61, 650 MHz cavity as an option for Project X. Based on this design two single cell cavities have been fabricated, processed and tested in-house. Cavity-A had a Qo value >1x10 11 at 1.6 K corresponding to a residual resistance of < 1.5 nΩ. Both cavities have exceeded E acc of 17 MV/m. Things we would like to do: Build a 5 cell β=0.61 to prove out the design, measure RF performance, compare BCP to EP, etc. Finalize the design & Fabricate a JLab β=0.9 prototype

14 Andrew BurrillFall 2011 Project X Collaboration Meeting Acknowledgments Frank Marhauser (RF design, simulations, copper model measurements) Peter Kneisel (Cavity Testing) Bill Clemens, Gary Slack (Cavity Fabrication) Cavity Production technical staff


Download ppt "Andrew BurrillFall 2011 Project X Collaboration Meeting 650 MHz Developments at JLAB Andrew Burrill for the JLab Team."

Similar presentations


Ads by Google