Download presentation
Presentation is loading. Please wait.
Published byEustace White Modified over 8 years ago
1
Impact of Hurricane Ike on CenterPoint Energy’s Transmission System Paul Rocha Director, Transmission Planning Presented at October 2, 2008 ERCOT TAC Meeting
19
Hurricane Ike 9/12/2008 7 PM Energized Out Restored 0 Circuits Out
20
Hurricane Ike 9/12/2008 11 PM 14 Circuits Out Energized Out Restored
21
Hurricane Ike 9/13/2008 2 AM - Landfall 36 Circuits Out Energized Out Restored
22
Hurricane Ike 9/13/2008 5 AM 67 Circuits Out Energized Out Restored
23
Hurricane Ike 9/13/2008 8 AM 90 Circuits Out Energized Out Restored
24
Hurricane Ike 9/13/2008 3 PM 97 Circuits Out Energized Out Restored
25
Hurricane Ike 9/13/2008 Restoration – 7% 90 Circuits Out Energized Out Restored
26
Hurricane Ike 9/14/2008 Restoration – 41% 58 Circuits Out Energized Out Restored
27
Hurricane Ike 9/15/2008 Restoration – 70% 30 Circuits Out Energized Out Restored
28
Hurricane Ike 9/16/2008 Restoration – 87% 13 Circuits Out Energized Out Restored
29
Hurricane Ike 9/17/2008 Restoration – 94% 6 Circuits Out Energized Out Restored
30
Hurricane Ike 9/23/2008 Restoration – 100% 0 Circuits Out Energized Out Restored
31
Pole Damage 31
32
Pole Replacement 32
33
CenterPoint MW Load Restoration 33
34
Seawall Substation
35
Stewart Substation 35
36
West Bay Substation
37
Moody Substation
38
Galveston Substation
39
West Galveston Substation 39
40
Mobile Substation
41
Network Changes After reviewing damage assessments and analyzing power flow study results, CenterPoint Energy decided not to restore the 69 kV portion of damaged West Galveston substation and 69 kV Ckt. 13, Lamarque – West Galveston Removal of damaged 69 kV connections to Galveston Island could cause some increased loading on remaining three 138 kV connections to Galveston Island Timing depends on rate of load restoration and growth on Galveston Island CenterPoint Energy believes upgrades of remaining 138 kV facilities would be more practical, cost-effective, and timely than restoration of damaged 69 kV facilities CenterPoint Energy will evaluate upgrades to remaining 138 kV connections to Galveston 41
42
42 Galveston Island Network Changes - Temporary
43
Galveston Island Network Changes - Permanent 43
44
Emergency Entergy Connection Implemented emergency interconnection from CNP’s Crosby substation to Entergy’s Dayton substation 9/15/2008 From Dayton substation, CNP used new transmission line built by Entergy after Hurricane Rita to restore power to water plant on the Trinity River normally served by Entergy Disconnected Entergy emergency connection 9/19/2008 44
45
Planned Transmission Outages Deferred all planned outages during restoration process CenterPoint Energy expects to resume planned outages next week 45
46
Mutual Assistance No report would be complete without noting the tremendous mutual assistance support from other utilities across North America Far too many to list here, but we want to say… Thank You!!! 46
47
Transmission Network Summary Transmission Network Was Quickly Restored Network restored to necessary functionality within 4 days However, storm surge affected Galveston Island, including CNP substations Grid stability maintained despite tie-line and other outages ERCOT actions to adjust for increased probability of line outages was effective Generators performed well 2007 completion of STP– Hillje– WAP tie-line helped Availability of mobile substations aided restoration effort New Entergy 138 kV line expedited water plant restoration Relay and Control infrastructure performed well Hurricane training and drills were effective in preparing personnel 47
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.